Creating Milestones in Your Schedule

You can designate certain tasks as milestones in your project plan. Having milestones flagged in your project plan and visible in your Gantt Chart helps you see when you’ve achieved another benchmark. Milestones often indicate the beginning or end of major phases or the completion of deliverables in your project. As you complete each milestone, you come ever closer to completing the project. Milestones are also excellent reporting points.

A milestone, as such, has no additional calculation effect on your schedule. However, you typically link a milestone to other tasks. You might also set a date constraint or deadline on a milestone.

The simplest method for entering a milestone is to create a task that’s worded like a milestone (for example, “Website launched”) and enter a duration of 0. Any task with a 0 duration is automatically set as a milestone. The milestone marker and date are drawn in the chart area of the Gantt Chart, as you can see in Figure 6-16.

Project 2010 interprets any task with a 0 duration as a milestone.

Figure 6-16. Project 2010 interprets any task with a 0 duration as a milestone.

Another easy way to create a milestone task is to use the Milestone button. In a task sheet, click where you want the milestone task to be inserted. On the Task tab, in the Insert group, click Milestone. A task labeled “<New Milestone>” is added above the selected row. The task has a duration of 0 days, and its date is set as the project start date. To correct the date of the new milestone task, link it as appropriate with its surrounding tasks or enter a start or finish date to correct the milestone date.

Project 2010 interprets any task with a 0 duration as a milestone.
Project 2010 interprets any task with a 0 duration as a milestone.

Milestone

Note that a milestone doesn’t have to have a 0 duration. You might want to make the final task in each phase a milestone, and these are likely real tasks with real durations.

Caution

Before you make tasks with durations into milestone tasks, be aware that you might be creating a new set of problems. The Gantt bar is replaced by a milestone marker at the finish date, so the duration is not shown unless you create a custom Gantt bar for this purpose. Also, if you export task data to other applications or copy task data between different projects, the milestone tasks are not likely to appear as you expect.

To change a regular task into a milestone, follow these steps:

  1. Select the task you want to become a milestone.

  2. On the Task tab, in the Properties group, click Information.

  3. In the Task Information dialog box, click the Advanced tab.

  4. Select the Mark Task As Milestone check box, and then click OK.

    The Gantt bar for the task changes to the milestone marker at the finish date in the chart area of the Gantt Chart. (See Figure 6-17.)

    You can set any task as a milestone.

    Figure 6-17. You can set any task as a milestone.