Chapter 21
In This Chapter
Recognising the right time to close your programme
Understanding the closure process
Everything comes to an end (though The Archers radio show is making a good stab at immortality), and at some point your programme needs to be closed.
If you've been part of the management team of a programme for three or four years and it's reaching the end of its last tranche, you need only a little advice on how to close your programme. No doubt you're already an expert on subjects such as your stakeholders, benefits and the outcomes (if not, check out Chapters 14, 15 and 16, respectively). Therefore, this chapter comprises just a few short checklists of some of the activities you may need to do when closing your programme.
I also reflect on when to close a programme (it's certainly not as simple as when the last project finishes), including the different circumstances in which you need to close a programme prematurely.
In essence, you can close the programme when benefits realization is embedded in business as usual.
In this section I describe the precise circumstances in which you close the programme in a planned way. You carry out closure when:
Some of the tests you can apply to decide whether closure is appropriate are as follows:
You need to continue benefits management after the end of the programme. Benefits take quite a time to materialise and may not have reached the target levels mentioned in documents such as the Benefits Realization Plan as the programme nears its close. New benefits continue to appear. Recording those unexpected benefits may be useful, particularly if the organization is going to run other programmes. Recording them means creating new Benefit Profiles so that other programmes can look at how those benefits accumulated.
The Business Change Managers are responsible for realizing these benefits, but they stop calling themselves Business Change Managers when the programme ends: they just have their business-as-usual roles and job titles.
Here are some guidelines on when the programme finishes officially:
No doubt in your programme the circumstances in which your programme closes is something you need to discuss at length.
In all the following circumstances you need to carry out a premature closure of your programme:
In this section I look in detail at the programme closure process (check out Figure 21-1 for an overview).
You need to consider some fairly straightforward inputs, illustrated in Figure 21-1, as follows:
Again looking at Figure 21-1, the principal controls are pretty straightforward. The Sponsoring Group has to authorise closure. Any other controls that were specified in the governance document baselines also have to be carried out. Probably this includes a formal assurance review of the programme; the reasons for closure may in themselves be a type of control as well.
The focus of the roles and responsibilities in this process is back up at the senior level that initially identified the programme and that's reflected in the key roles.
The activities themselves are a pretty straightforward checklist:
Responsibilities are spread around rather more than in many processes:
The outputs shown In Figure 21-1 are the sorts of closure disbandment items that you'd expect:
18.117.71.211