The Planning the Program questions on the PgMP® certification exam, which constitute 11 percent of the exam, or 19 questions, focus on many critical areas in program management and emphasize the importance of detailed and comprehensive program planning. In The Standard for Program Management, a project plan is mentioned in Program Strategy Alignment, and its Program Definition Phase of its life cycle emphasizes program preparation with a program management plan. In the Standard, its Program Management Supporting processes each have a planning component, most of which will be covered in the questions in this section. According to the Standard, once the program management plan is formally approved, the Program Benefits Delivery Phase begins. Note that Benefits Management; Stakeholder Management, including Communication Management; and Governance are covered in separate sections of this book, and their planning components will not be covered in depth in this section.
Similar to the PMBOK® Guide’s work breakdown structure (WBS), which is essential for project planning, the PgMP® includes the preparation of a program WBS (PWBS). This PWBS does not replace the WBS for each of the projects in the program, but it does provide an overview of the program and shows how the projects and non-project work fit into the overall program structure.
The Examination Content Outline has nine tasks on Planning the Program, which also will be covered in the planning questions in this section and in the two practice tests. The emphasis is to ensure that the program’s mission, vision, and values support those of the organization. The planning processes are iterative, and because of the length of the program and the multiple projects in it, plans need to be revisited and updated when components are initiated or closed, during the organization’s fiscal year and budget planning cycle, and when unplanned events occur.
Following is a list of the major topics covered in Planning the Program. Use this list to focus your study efforts on the areas that are most likely to appear on the exam.
Program Preparation
Supporting Processes
Program Scope Statement
Develop Key Performance Indicators
Key Human Resources
INSTRUCTIONS: Note the most suitable answer for each multiple-choice question in the appropriate space on the answer sheet.
In this PWBS, a program package is—
1. | a | b | c | d |
2. | a | b | c | d |
3. | a | b | c | d |
4. | a | b | c | d |
5. | a | b | c | d |
6. | a | b | c | d |
7. | a | b | c | d |
8. | a | b | c | d |
9. | a | b | c | d |
10. | a | b | c | d |
11. | a | b | c | d |
12. | a | b | c | d |
13. | a | b | c | d |
14. | a | b | c | d |
15. | a | b | c | d |
16. | a | b | c | d |
17. | a | b | c | d |
18. | a | b | c | d |
19. | a | b | c | d |
20. | a | b | c | d |
1. d. | Use the scope management plan As the program schedule is prepared, it begins with the scope management plan and the PWBS in which the program components that produce the program benefits are identified. PMI®, The Standard for Program Management, 2013, 101 |
2. b. | $32 million You will earn the difference between $20 million plus 70 percent of the additional $25 million and $2.5 million in expenses plus 30 percent of the additional $10 million in expenses, or— [$20m + (0.7 × $25m)] − [$2.5m + (0.3 × $10m)] = ($20m + $17.5m) − ($2.5m + $3m) = $37.5m − $5.5m = $32m NOTE: Remember that expected value is calculated as probability multiplied by the monetary value of the risk. Milosevic, Dragan Z. 2003. Project Management ToolBox Tools and Techniques for the Practicing Project Manager. Hoboken, New Jersey: John Wiley & Sons, 311–314 Shimizu, Motoh. Fundamentals of Program Management Strategic Program Bootstrapping for Business Innovation and Change. 2012, Newtown Square, PA: Project Management Institute, 146–147 |
3. d. | Program scope statement The program scope statement is the basis for future program decisions, and it defines and articulates the scope of the program. It also contains a list of the program’s deliverables and success criteria. In program procurement planning a best practice is to evaluate commonalities and differences for the various procurements across the scope of the program. PMI®, The Standard for Program Management, 2013, 90 and 104 |
4. a. | Prepare a competitive analysis of service providers In Program Procurement Planning, the program manager considers all program components and develops a comprehensive plan for procurements to meet goals and objectives. This planning is complemented by considering a program-wide approach to competition. PMI®, The Standard for Program Management, 2013, 90–91 |
5. b. | An iterative process, and as issues arise and are addressed, the plan will naturally fluctuate As competing priorities, assumptions, and constraints are worked and resolved to address critical factors, such as business goals, deliverables, benefits, time, and cost, the plan will change over time. PMI®, The Standard for Program Management, 2013, 85 |
6. b. | $17.5 million Decision-tree analysis is used to show the situation and the implications of each of the available choices. It also provides the expected monetary value for the various alternatives. If no risks occur, the value of your program would be calculated as follows: $20m − $2.5m = $17.5m Milosevic, 2003, 311–314 Shimizu, 2012, 146–147 |
7. d. | An understanding of the steps needed to move from a development state to an operational state Transition planning involves identifying all the steps that are necessary to transition the program to an operational state. Transition planning from deliverables to capabilities and benefits to the organization is critical to program success. The transition plan defines the criteria to meet to ensure all administrative, commercial, and contractual obligations are met when the program is complete. PMI. Program Management Professional (PgMP)® Examination Content Outline, 2011, 9 Thiry, Michel. Program Management. 2010. Surrey, England: Gower Publishing Limited, 139 |
8. c. | Identify those skills that are critical to the program but are not possessed by current team members Competency is the knowledge, attitudes, and skills, and other personal characteristics that can affect one’s job. The first step is to identify the competencies that are critical to the program but are not possessed by existing team members. This ensures that these key resources can be obtained and will be available when required. A competency model can assist in determining the performance and personal competencies deemed necessary in program management. PMI®, Project Manager Competency Development Framework—Second Edition, 2007, Newtown Square, PA: Project Management Institute, 73 Levin, Ginger and Ward, J. LeRoy. 2011. Program Management Complexity A Competency Model. Boca Raton, FL: CRC Press. |
9. a. | The top two levels of each project’s work breakdown structure (WBS) can be included in the PWBS
The PWBS typically extends to the first one or two levels of each project’s WBS. The bottom-up approach can show these levels as the PWBS is developed. PMI®, The Standard for Program Management, 2013, 105 |
10. a. | Determining the order and timing of program packages During schedule development at the program level, the order and timing of the program packages and the non-program activities must be determined to produce the program benefits. This enables the scheduler to forecast the completion date of the program and of each milestone within the program and the key deliverables for each project. PMI®, The Standard for Program Management, 2013, 100–101 |
11. d. | Budgeted Cost budgeting is based, in part, on how any financial constraints impose boundaries on the budget. Fiscal year budgetary planning cycles impose such boundaries, causing the program team to possibly use different techniques over the life cycle. The program’s financial management plan should discuss the initial budget as well as funding schedules and milestones. Many organizations as well agree to an overall financial management plan and commit to a budget only for the next phase at each governance milestone. PMI®, The Standard for Program Management, 2013, 78–79 |
12. b. | Ensure infrastructure and operational costs are included In developing the program’s financial management plan, it expands on the financial framework. While the component costs comprise the majority of the program’s budget, operational costs and infrastructure costs are also included. PMI®, The Standard for Program Management, 2013, 79–80 |
13. b. | Procure the services of a product integrator
Rather than relying on multiple contractors, on many programs, the program manager and the team may decide to outsource the services of a product integrator to bring together the product outputs of the various projects. The goal of program procurements is to optimize procurements for the components, PMI®, The Standard for Program Management, 2013, 89 |
14. d. | The provisions the vendor has in place to protect intellectual property Protecting intellectual property is of paramount concern for any company when outsourcing, and, in particular, when outsourcing to a company in a foreign nation, especially considering the differences in legal systems and standards of protection. As a performance competency for program managers, it is necessary to ensure intellectual property is properly retained during the program. PMI. Program Management Professional (PgMP)® Examination Content Outline, 2011, 9 Levin and Ward, 2011, 60 |
15. c. | Interproject risks In Program Risk Analysis, at the program level the emphasis is to integrate relevant component risks and to manage the interdependencies among these risks and the program to provide significant benefits to the program and the projects. A performance competency for program managers is to identify key program risks and issues, which includes identifying interdependencies between component risks. PMI®, The Standard for Program Management, 2013, 98 Levin and Ward, 2011, 38 |
16. d. | Apply the use of normalized templates, forms, and guidelines to make the process consistent across all projects One function of a program management office is to define the program management processes and procedures to be followed. By having standard processes in place, it can reduce the time involved in requirements gathering because teams can get started right away without first having to design their own methods for gathering requirements. Also, an effective program management information system can include requirements management activities and tools. PMI®, The Standard for Program Management, 2013, 13, 86 |
17. a. | Adhere to legal and finance obligations In procurement planning, a number of activities are performed. Because of the need to optimize program procurement management, and to adhere to legal and financial obligations, the people responsible for procurement at the program level must work together during the planning phase. PMI®, The Standard for Program Management, 2013, 90 |
18. c. | Set standards that are relevant to the entire program A key purpose of program quality planning is to identify the standards that are relevant to the entire program and to specify how to satisfy them. To ensure overall program quality, the different quality assurance and quality control specifications can be coordinated, and others added as needed. PMI®, The Standard for Program Management, 2013, 92 |
19. d. | Plan The PWBS is a deliverable-oriented hierarchical description of the total scope of the program. A program package is the lowest level of the PWBS. Selections a., b., and c. are not at the lowest level of the PWBS. PMI®, The Standard for Program Management, 2013, 104–105 |
20. c. | Balanced scorecard The balanced scorecard was developed by Kaplan and Norton to be able to serve as such a strategic performance measurement tool. It tracks the execution of activities of staff members and the impact arising from these actions. PMI. Program Management Professional (PgMP)® Examination Content Outline, 2011, 9 Hibson, Kathleen M., “Change Management The Good, the Bad and the Ugly” in Levin, Ginger. 2012. Program Management A Life Cycle Approach. Boca Raton, FL: CRC Press, 45 |
3.145.121.81