PMI® in the PgMP® Examination Content Outline has established a Program Life Cycle consisting of:
In this life cycle, Initiating represents 6% of the questions or 10 questions on the exam.
We have elected to provide 20 questions for you for practice in this book, even though the sample 170-question exams will contain 10 questions.
The questions on the exam concentrate on additional methods to gain greater support and approval for the program. They focus on the need to ensure that the program’s values and objectives are aligned with those of the organization as documented in the program mandate.
In The Standard for Program Management—Third Edition (2013), initiating is covered in the “Program Management Supporting Processes” in the program definition phase in its program management life cycle. It focuses on further definition of the program’s purpose, securing financing, and showing how the program will deliver its desired benefits. A program manager is assigned, a program charter is prepared, the financial framework is prepared, and the program roadmap is defined in greater detail. Once the charter is approved, its authorization leads to program commencement.
Questions may address the roles and responsibilities of the program manager and the core team as well as possible program organizational structures. Other questions may address the contents and purpose of the charter, when the business case should be updated, and a high-level program scope statement that then sets the stage for a more detailed scope statement in the planning phase of the life cycle. As well, questions may involve developing a high-level milestone plan by using the goals and objectives of the program to ensure the program is aligned with stakeholder expectations, especially those of the sponsor. A program resource accountability matrix is another potential area for questions during this phase as roles and responsibilities are identified for the program’s core team. The importance of a program kickoff meeting with stakeholders is another area of emphasis.
Following is a list of the major topics covered in Initiating the Program. Use this list to focus your study efforts on the areas that are most likely to appear on the exam.
Program Initiation
Key Roles
Program charter
Program roadmap elaboration
Program cost estimates
Program financial framework
Resource accountability matrix
Program kickoff meeting with stakeholders
INSTRUCTIONS: Note the most suitable answer for each multiple-choice question in the appropriate space on the answer sheet.
1. | a | b | c | d |
2. | a | b | c | d |
3. | a | b | c | d |
4. | a | b | c | d |
5. | a | b | c | d |
6. | a | b | c | d |
7. | a | b | c | d |
8. | a | b | c | d |
9. | a | b | c | d |
10. | a | b | c | d |
11. | a | b | c | d |
12. | a | b | c | d |
13. | a | b | c | d |
14. | a | b | c | d |
15. | a | b | c | d |
16. | a | b | c | d |
17. | a | b | c | d |
18. | a | b | c | d |
19. | a | b | c | d |
20. | a | b | c | d |
1. c. | Funding and available resources Programs are often unrelated to other initiatives within a common portfolio; however, all initiatives typically compete for funding and other resources, both of which are finite in most organizations. PMI®, The Standard for Program Management, 2013, 10 |
2. a. | You should develop a high-level milestone plan Such a plan uses the goals and objectives of the program, any applicable historical information, and other available resources. It is useful to align the program with the expectations of stakeholders including sponsors. PMI®. Program Management Professional (PgMP)® Examination Content Outline, April 2011, 8 |
3. a. | Used input from all stakeholders Stakeholder involvement in the development of the charter helps to gain their support for it and their commitment to the program. PMI®. Program Management Professional (PgMP)® Examination Content Outline, April 2011, 8 |
4. c. | A high-level program scope statement Building on the program mandate and the strategic goals and objectives of the program, a high-level scope statement should be prepared by negotiating with stakeholders.Miller, L. Trae. “Program Initiation” in Levin, Ginger. 2012. Program Management A Life Cycle Approach. Boca Raton, FL: CRC Press, 68–69 PMI®. Program Management Professional (PgMP)® Examination Content Outline, April 2011, 8 |
5. c. | Expand on the roadmap that provides a chronological representation of the program’s direction In program initiation, the roadmap along with the program charter is used to communicate overall program direction. PMI®, The Standard for Program Management, 2013, 84 |
6. d. | Program charter The program charter provides the basis to commence the program. Among other things, the charter defines the vision (or the end state) of the program, describes how the program will benefit the organization, and describes the key program outcomes that are required to achieve the vision. PMI®, The Standard for Program Management, 2013, 84–85 |
7. d. | Conduct a program kickoff meeting with key stakeholders A kickoff meeting with the program team is a recommended best practice once the team has been established. However, one is also recommended with the key stakeholders in the initiating phase and is especially important after the charter has been approved to familiarize the organization with the program and continue to obtain stakeholder buy in to it. PMI®. Program Management Professional (PgMP)® Examination Content Outline, April 2011, 8 |
8. b. | Roadmap Among other things, the roadmap shows the various milestones, details, descriptions, and the benefits to be delivered. It establishes the relationship between the program activities and expected benefits. PMI®, The Standard for Program Management, 2013, 29, 84 |
9. a. | How the program will deliver the desired benefits In program initiation, the purpose is to define the program, secure financing, and demonstrate how the program will deliver the desired benefits. PMI®, The Standard for Program Management, 2013, 83 |
10. c. | A program mandate The business case and a program mandate are key inputs for organizational leaders to charter and authorize programs. PMI®, The Standard for Program Management, 2013, 28 |
11. a. | Secure program funding Program costs tend to occur far earlier than related benefits. An objective is to determine the funding source and obtain funds to bridge the gap between paying out monies and obtaining benefits. PMI®, The Standard for Program Management, 2013, 78 |
12. b. | Assign a program sponsor for these initiatives This program could be set up to include project work for the Web initiatives as well as work on the ongoing activities to focus on benefits delivery from this work. A program sponsor should be assigned to oversee the program, secure funding for it, and deliver its intended benefits. PMI®, The Standard for Program Management, 2013, 83 |
13. a. | The parent organization Programs can be funding in different ways. In this situation, the City is the parent organization, and the program will be funded by the City. PMI®, The Standard for Program Management, 2013, 78 |
14. c. | Program financial framework When programs are initiated as a result of a decision to bid on a contract, program costs will occur before benefits are realized. A financial framework for the program will be necessary to dictate the financial environment for the program’s duration. PMI®, The Standard for Program Management, 2013, 78 |
15. d. | A high-level milestone plan This plan uses the goals and objectives of the program along with applicable historical information and other available resources such as a work breakdown structure, scope statements, and a benefit realization plan in order to align the program with the stakeholders, including sponsors. PMI®. Program Management Professional (PgMP)® Examination Content Outline, April 2011, 8 |
16. c. | Stated as part of the program charter Approval of the charter authorizes program commencement. Among other items, it includes a discussion of program components to describe how the projects and other components are configured to deliver the program’s benefits. This often includes a high-level program plan for the components. PMI®, The Standard for Program Management, 2013, 84 |
17. d. | The program funding source The program funding source is part of the program’s financial framework. Programs have a variety of potential funding sources and can be funded by more than one source, with components funded by different sources. PMI®, The Standard for Program Management, 2013, 78 |
18. a. | Program manager and program sponsor The program manager and program sponsor are selected and assigned in program initiation. PMI®, The Standard for Program Management, 2013, 83 |
19. d. | Guide the initiation process The program manager is assigned as the program is initiated as early as possible to guide the initiation activity and facilitate the development of Its outputs. PMI®, The Standard for Program Management, 2013, 83 |
20 a. | Conduct a SWOT analysis A SWOT (strengths, weaknesses, opportunities, and threats) analysis is a recommended approach to take in developing a viable program charter and project plan. PMI®, The Standard for Program Management, 2013, 31 |
3.133.142.193