The Controlling the Program questions on the PgMP® certification exam, which constitute 10 percent of the exam, or 17 questions, continue to focus on phase four of the program life cycle from the Examination Content Outline and more specifically on monitoring and controlling the program and its components. The expected benefits need to be in line with the original plan, the level of risk must remain acceptable, and accepted best practices must be followed.
The Examination Content Outline focuses on the need to analyze variances in costs, schedule, quality, and risks to identify corrective actions or opportunities to the program because of these variances. The Program Management Plan and other plans may need updating as a result of corrective actions that are implemented. It also emphasizes the need to manage issues on the program to identify and select a course of action consistent with the program’s scope, constraints, and objectives to achieve the programs benefits. Impact assessments for various possible changes may need to be conducted and decisions made. Additionally, risks require monitoring, following the risk management plan.
In the Standard for Program Management—Third Edition (2013), monitoring and controlling is part of the Benefits Delivery Phase of this life cycle. Questions then cover program performance reporting, program financial monitoring and control, program performance monitoring and control, program procurement administration, program quality control, resource interdependency management, program risk monitoring and control, and program scope control.
You should expect to answer questions on earned value and should be familiar with the various earned value terms and formulas. You should also expect to answer some questions about program trends and the need to communicate these trends to the program’s stakeholders. Stakeholders are emphasized in the Manage Program Stakeholder Expectations process, covered in the stakeholder domain in this book. Other work involves governance oversight and managing benefits, covered in the respective domains in this book.
Because monitoring and controlling involves preventive and corrective actions, some questions include scenarios in which the program manager and the core program team must decide on the best course of action. Because the program manager is responsible for managing program issues, the use of an issue register is required, and its contents may be reviewed by the Governance Board. Many of these processes will occur throughout the program’s life cycle, from initiation to closure. Furthermore, it is essential to focus on monitoring and controlling the program’s scope, schedule, and budget, and if contracts are to be awarded, to focus on administering program procurements.
Following is a list of the major topics covered in Controlling the Program. Use this list to focus your study efforts on the areas that are most likely to appear on the exam.
Program Benefits Delivery
Preventive and corrective actions
Proactive and reactive cost control
Managing and controlling changes
Meetings and reviews
Program management controls
Earned value
Trend analysis
Variance analysis
Impact assessments
Issue register
INSTRUCTIONS: Note the most suitable answer for each multiple-choice question in the appropriate space on the answer sheet.
1. | a | b | c | d |
2. | a | b | c | d |
3. | a | b | c | d |
4. | a | b | c | d |
5. | a | b | c | d |
6. | a | b | c | d |
7. | a | b | c | d |
8. | a | b | c | d |
9. | a | b | c | d |
10. | a | b | c | d |
11. | a | b | c | d |
12. | a | b | c | d |
13. | a | b | c | d |
14. | a | b | c | d |
15. | a | b | c | d |
16. | a | b | c | d |
17. | a | b | c | d |
18. | a | b | c | d |
19. | a | b | c | d |
20. | a | b | c | d |
1. d. | Resource Interdependency Management Resources must be shared across the program, and the program manager controls the schedule for these shared resources. PMI®, The Standard for Program Management, 2013, 95 |
2. c. | Managing scope Scope control is necessary to ensure the program delivers its intended benefits. To administer and manage scope, a change management activity is necessary. PMI®, The Standard for Program Management, 2013, 106 |
3. b. | Include the spares data, even though they are non-project work, because they are part of the program At the program level, in preparing performance reports, these reports summarize progress of components in the program. The summarization incudes both the projects and the non-project work. PMI®, The Standard for Program Management, 2013, 87 |
4. c. | Recommend corrective actions To avoid penalties or ongoing lease payments, leased resources should be tracked to ensure that they are returned when the lease expires or when they are no longer needed. Based on the audit findings, it is now necessary to request changes or recommend corrective action requests. A program whose costs exceed budgets may no longer justify its business case. Even minor overruns must be justified. PMI®, The Standard for Program Management, 2013, 81–82 |
5. b. | Preparing program performance reports Program Performance Reporting coordinates performance data to provide stakeholders with information on resource use to determine effectiveness in delivery of program benefits. Customer feedback requests are an output of this activity. PMI®, The Standard for Program Management, 2013, 77 |
6. d. | Inform your Governance Board At this point, it is obvious the program will not meet its schedule. The first step is to inform your Governance Board and then make a decision as to the next steps and the corrective actions to be performed. PMI®, The Standard for Program Management, 2013, 81 |
7. d. | Determine a course of action After an issue is identified, it should be recorded in the issue register. This is an example of a program-level issue, and the program manager now must select a course of action consistent with scope, constraints, and objectives to achieve planned benefits. PMI®, Examination Content Outline, 2011, 11 |
8. a. | Determine if the program assumptions are still valid In program risk monitoring, often it is necessary to review the initial program assumptions and determine if they are still valid as assumptions are a key source of risks. PMI®, The Standard for Program Management, 2013, 100 |
9. b. | Architecture issues Controlling scope is critical to program success. These scope changes may originate from stakeholders, program components, previously unidentified requirements, architecture issues, or external sources. PMI®, The Standard for Program Management, 2013, 105 |
10. a. | Establish an issue analysis process A performance competency for program managers is to identify issues and risks continuously and take corrective actions as required. As part of this competency, an issue analysis process should be established to assess the impact and severity of issues, and an issue log should be maintained. PMI®, Examination Content Outline, 2011, 11 Levin, Ginger and Ward, J. LeRoy. 2011. Program Management Complexity A Competency Model. Boca Raton, FL: CRC Press, 50 |
11. b. | Update the program management plan In Program Scope Control, a change management activity is a necessity. When change requests are accepted and approved, the program management plan and the program scope statement are updated. PMI®, The Standard for Program Management, 2013, 106 |
12. b. | Budget baseline The program budget baseline is updated as an output of Program Financial Monitoring and Control. Monitoring finances and controlling expenditures are critical aspects of ensuring the program meets its funding goals. A change of this magnitude requires the need to update the budget baseline. PMI®, The Standard for Program Management, 2013, 81 |
13. a. | Update the program budget baseline As an output of the Program Financial Monitoring and Control, updates to the program budget baseline are needed when there are significant cost impacts. These updates are communicated to program stakeholders as appropriate. PMI®, The Standard for Program Management, 2013, 81 |
14. a. | Conduct impact assessments Impact assessments should be conducted for program changes in order to recommend decisions and obtain approval according to the program’s governance model. PMI®. Program Management Professional (PgMP)® Examination Content Outline, 2011, 11 |
15. a. | Key performance indicators In Program Performance Reporting, performance data on the program are consolidated and conveyed to stakeholders to provide information about the program’s performance. As an output, key performance indicators should be established. PMI®, The Standard for Program Management, 2013, 77 |
16. d. | Earned value and planned value For the earned value (EV) of the project, note that half the work has been completed, for an EV of $300,000. The planned value (PV) through month two is $200,000. Remember that the estimate was $600,000 spread evenly over six months (or $100,000/month). PMI®, The Standard for Program Management, 2013, 77 Pritchard, Carl L., 2003. The Project Management Drill Book: A Self-Study Guide. Arlington, VA: ESI International, Chapter 1 |
17. b. | Risk monitoring function Risk monitoring includes evaluation of whether cost or schedule contingency reserves need to be modified in line with the risks of the program as program risk responses are continuously monitored for new and changing risks. PMI®, The Standard for Program Management, 2013, 100 |
18. c. | Contract management plan The contract management plan is used to administer contracts for significant purchases and acquisitions. It covers contract administration activities throughout the life of the contract and is used effectively to manage a variety of suppliers. It is an output of Program Procurement so it should be followed in Program Procurement Administration. PMI®, The Standard for Program Management, 2013, 91 |
19. c. | Ensure the budget is being spent properly As contracts are awarded during Program Procurement Administration, it is the program manager’s responsibility to maintain visibility in the procurements to ensure the budget is spent properly to obtain program benefits. PMI®, The Standard for Program Management, 2013, 91 |
20. a. | The SV is −$4,222, and the program is behind schedule Schedule variance (SV) is calculated by subtracting the planned value (PV) from the earned value (EV); that is, SV = EV − PV. At this point, the SV is −$4,222. The program is behind schedule; however, without additional information, the effect on the critical path is not known. PMI®, The Standard for Program Management, 2013, 81 PMI®, PMBOK® Guide, 2013, 224 |
3.19.63.106