Revision | Date of Revision | Details of Revision | Revised By |
The Project is to be known as ‘???????’ , and unless requested by the Project Board, this shall be the only title stated on all documentation including correspondence, meeting notes, documentation and drawing title blocks. Within the body of documents, and in informal communication, the abbreviation ‘?????’ may be used.
Description of why the project is required, and explanation of project to date.
Outline items to be included within the project.
Description of project timescales and the pressure on this.
The project has been established to achieve the following outline programme milestones:
Please give elemental breakdown of programme.
Element | Original Cost Plan | Forecast Expenditure | Actual Expenditure | Variance |
---|---|---|---|---|
Brief description on location of the building and why this location has been selected
Insert Picture of Location Here
School of Computing, Science and Engineering | = | CSE |
Mechanical and Electrical | = | M & E |
Project Manager | = | PM |
Post Project Review | = | PPR |
Quantity Surveyor | = | QS |
Senior Management Team | = | SMT |
Construction (Design and Management) Regulations | = | CDM |
Principal Designer | = | PD |
Change Request Form | = | CRF |
Employers Agent (depending on Procurement) | = | EA |
Higher Education | = | HE |
Programme bar chart (duration, completion) | = | Project Plan |
Give description on whether planning is required, the type of planning request and likely timescales.
Give description on whether Building Regulations approval is required, the type of planning request and likely timescales.
Highlight the potential or foreseen legal issues.
The Project directory will be maintained and updated by the Project Manager throughout the life of the project.
Role | Company Name/Address | Contact Name | Phone | Mobile | |
Project Chair | |||||
Senior User | “ | ||||
Senior Supplier | “ | ||||
Board Advisor/Head of Financial Accounts TBC | “ | ||||
Course Leader | “ | ||||
Project Manager | “ |
Role | Company Name/Address | Contact Name | Phone | Mobile | ||||
Construction/Design Team | ||||||||
Main Contractor Construction Manager | ||||||||
Lead Consultant Principal Designer Project Manager Lead Designer | ||||||||
The Project Board will encompass the following roles with the following key responsibilities:
The limits of the Senior Supplier and also the Project Board’s delegated authority to make decisions are restricted to the works, budget and programme approved within the business case, and only when exceeded should an issue be referred to the Campus Masterplan Programme Board. The Project Board will be accountable for delivering the Project within the delegated authority, and the Board will meet on a needed basis to:
Initial Project Board Meeting | ???? |
Pre-Start Construction Meeting | ???? |
Mid-Project Review Meeting | ???? |
Handover and Close-Out Meeting | ???? |
The list above is not exhaustive if more meeting are required they will be appropriately arranged.
The Project Chair is responsible for all external communication relating to the Project, or an appointed designate. Should Project parties wish to communicate externally on project matters they should seek approval from the Project Executive, via the Project Manager before doing so. Should any incidents happen on site, or immediately adjacent, or with regard to the Masterplan development that may be of interest to the general public or news organisations, be it positive or negative, the Project Manager is to be notified immediately to allow the correct course of action to be agreed.
All Programme/Project team members are asked to promote good neighbourly and public relations. The Main Contractor will be required to sign up to, and promote the principles of the Considerate Constructors.
The following consultants have been appointed as follows: – (for contact details please see the Project Directory)
Client -
Principal Designer -
Lead Consultant -
Quantity Surveyor -
All design, specification and cost management services are to be complete by (enter name).
Individual scopes of service are contained in the appointment documentation of the relevant consultant. The Responsibility Matrix in Appendix B below details the broad division of responsibilities on the Project.
Please state who the main contractor is and how they have been appointed, include procurement method and evaluation.
B4 – Direct Appointments
Please name any direct appointments made by the client.
In order for works to be carried out in a timely and cost-effective fashion, it is important that all members of all project teams communicate effectively and efficiently. It is envisaged that the majority of issues arising throughout the Project will be able to be coordinated by the Project Manager.
Communication between parties involved in the project should predominantly be by oral (telephone and meetings) and electronic (e-mail) means. It is of vital importance that a record is kept of all decisions made concerning the Project, and, therefore, an e-mail (or letter) or minutes should be sent confirming the content of any decision made. E-mail communication should, where possible, only be used to issue information, a set of instructions or confirm a decision made, and should not be used in a ‘conversational’ manner to avoid inefficient practices.
Communication should follow the routes indicated and be between the key individuals from a relevant organisation. Those key individuals are then responsible for distributing that communication within their organisation.
Alternative communication routes may be followed in the event of an urgent situation or a party/parties not being available, provided that the course of action taken is in the best interest of the Project as a whole. In such a situation, the party/parties who would in the normal way have been involved, must be kept fully informed.
The Project Manager must be copied in on all relevant communications.
The hierarchy of correspondence is as follows:
Meetings form one of the prime opportunities for face-to-face communication and are considered fundamental to the successful execution of the project. Meetings will be organised on a needed basis. An agenda for a meeting should be issued with the minutes from the previous meeting. Generally minutes should be a succinct record of the key points discussed at the meeting, with an emphasis on recording the decisions taken and on future actions required.
All correspondence and documentation is to be issued with the Project title clearly referenced.
Minutes and other correspondence relating to meetings should be distributed to all meeting invitees, or as appropriate. Thought should be given to ensuring excess distribution is avoided; however, effort should be made to ensure all relevant parties receive information appropriately.
Each piece of correspondence should be clearly noted for each addressee as either action or information. This will assist all parties to prioritise issues and manage paperwork.
All parties are obliged to respond to communications within the requested period. If an extension to this period is required, it must be agreed by all relevant parties.
All report problems should be addressed to the Project Manager in a timely manner.
Drafting of the Contract and the administration of it is to be completed by????????
The principle of change management is to establish an approved baseline of information, and if anyone involved in a Project suggests varying from it, a change would be raised for the team to consider, review and for the Senior Supplier to approve and instruct (if acceptable) or to escalate under an exception if it is outside of the scope of the delegated authority.
Unplanned change is highly disruptive and without the explicit control of change, there is a greater chance that project objectives will not be met.
Leadership from the client and active participation by the full project team are critical to the successful operation of a change management process.
The Change Management Procedure will apply to all change irrespective of the originator – e.g. Client, stakeholders, user groups, project team and other third parties.
The Change Management Procedure will apply to all change irrespective of scope, anticipated cost (subject to delegated authority levels).
The change management procedure will be determined by the Employers Agent and agreed with the UoS prior to implementation.
When assessing changes, the project team may find the following classification helpful in determining which instructions are given priority:
It is recommended that changes required for corrective action are prioritised so that agreed project objectives are met.
The Change control system has two component parts:
The Stage 2 Change Control Form is used to communicate a need for change and to analyse its impacts. Up until approval the responsibility for the management of communication is held by the change originator.
Use of the Stage 2 Change Control Form supports:
The key duties and responsibilities in managing the change control system are as follows:
In the event that a change is not identified by its originator prior to implementation, a Stage 1 Early Warning Form will be issued by the Cost or Project Manager to initiate the formal change process, even if this is after the change has been incorporated into the design.
The scope of change instructed must be limited to the work described on the Stage 2 Form. Whilst design development will be permitted following sign-off of the change, any material alteration to the scope of the change will require further approval via a further Stage 2 Form.
Early warning is a key aspect of the change management system. The approach to early warning will be informal and the assessment requires minimal technical input. However, early warning must be used consistently if abortive work and possible delay and extra cost are to be avoided.
Early warning provides high-level reporting of the cost implications of brief or design development at any stage of a project. It focuses exclusively on issues of affordability, which may include the cost implications of an extended development or build programme.
The Employers Agent will undertake a proactive role through the early warning system to identify change which is not identified by other members of the project team.
No comment on the broader implications of a change is required under the early warning system.
Use of the early warning system will not result in the issue of an approved Stage 2 change order.
The early warning system operates through the issue of a stage 1 form.
Generally, Stage 1 forms will be issued by the Employers Agent as revised information is received. Other Project Team members are encouraged to request the generation of a Stage 1 form by the Employers Agent where they believe that an aspect of the project may be moving outside of its established budget.
The change control procedure is the mechanism by which change orders are approved and issued for action. No change can be issued without client approval obtained through the change control procedure.
The change control procedure applies to all change proposed after Contracts have been executed.
Changes that fall within the scope of the procedure include:
The change control procedure is the mechanism by which change orders are approved and issued for action. No change can be issued without client approval obtained through the change control procedure.
The change control procedure applies to all change proposed after Contracts have been executed.
Changes that fall within the scope of the procedure include:
The impact of the change will be assessed against the following criteria.
The impact of change will be assessed against current baselines for cost, programme and Specification as defined in the Contract.
The assessment of the impact of the change should include consideration of a ‘do nothing’ option.
A request for a Stage 2 Change Control form is to be raised by any party whenever it is considered that there is, or may be a change.
The stage 2 form will be issued by and channelled through the Project Manager for each party to the change process.
Organisation | Name | |
Client | ||
Project Manager | ||
Principal Designer |
Change number suffixes are based on initials of each project party. Due to duplication of initials the following references are to be used on the project.
Organisation | Codings |
TBC | |
TBC | |
TBC | |
TBC | |
TBC | |
TBC | |
TBC | |
TBC |
Response times relating to priority codes on the Stage 2 forms are as follows:
Priority | Response Time |
Low | 10 working days |
Medium | 5 working days |
High | 48 hours |
Priority Response time
Subject to any level of delegated authority being agreed by the client, all change instructions must be assessed using the Change Control procedure prior to issue.
Organisation Name E-mail
Throughout the Construction Period the Project Manager will be responsible for co-ordination of formal submissions and responses between the consultant team and the Client.
All members of the Professional Team will maintain sufficient hard and soft copy filing systems to enable effective storage of information originating from that organisation.
Design Information control will be administered by the Contractor. The Project Manager will be responsible for ensuring that all Project Team members comply with the protocols established as part of the system.
UoS require that the correct attention be given to all Health and Safety matters arising from the Project in accordance with the CDM 2015 Regulations. The client will appoint a Principal Designer who will take the lead in planning, managing, monitoring and co-ordinating health and safety during the project.
All Project Team members have a duty to raise any concerns that they have regarding Health and Safety on the project as soon as they become apparent either directly with the Contractor (when appointed) or the client.
All members of the team must adopt a value-based approach. This approach involves employing lateral thinking and keeping an open mind to question why things are done in a certain way, and trying to identify more effective and efficient methods (particularly their tasks on the project).
Risk Management has been established at Project level, and encompasses the review of strategic/high-level risk. Key Project risks are identified to ensure that they are dealt with in a timely and appropriate manner. The Risk Management Strategy for this Programme will differentiate between project risks and project issues as follows:
Risk – A risk is an uncertainty, which, if it occurs, will have a negative impact on the project.
Issue – An issue is something which is certain to happen, or has already happened, which will have a negative impact on the project.
The Risk Management Strategy is, firstly, to identify risks and issues which could negatively affect the chances of achieving the Project objectives; secondly, to determine the perceived relative importance of each risk identified in order to prioritise them with respect to each other; and, thirdly, to discuss how each risk/issue can be mitigated and who should take responsibility in each case. It is vital that all parties actively participate in this process as risk is subjective, and certain risks may be more important to one party than to another. The outputs from this process will be included within the Risk Register, by the PM, following each meeting. A Risk Management Workshop may be held to expand on the above, if deemed necessary. The Risk Management process will review the value criteria established, and focus on the risks to delivering those objectives.
Appendix A
{The following provides a list of typical requirements at completion. The Client requirements and contract documents should be referred to in creating a project-specific list.}
Completion Checklist | |||
---|---|---|---|
AAVT Temporary | |||
By Whom? | By When? | ||
1. | Practical Completion certificate issued. | ||
2. | Building Control Certificates of Completion received. | ||
Building Control approval confirmed and certificate received. | |||
Copy of original outline and detailed approvals issued to Client. | |||
Statutory signage installed. | |||
Fire-fighting appliances installed and ready for use. | |||
3. | Design team confirming that Contract Requirements have been met. | ||
Consultants confirmation that the Contractors design and the works comply with the Contract Requirements. | |||
4. | All test certification has been signed by required parties and issued. | ||
A copy of all certificates is included in the Building Manual. Test certificates to be included but not limited to: | |||
Building Control Completion Certificate | |||
17th Edition Electrical Test Certificate | |||
Earth Test Certificate | |||
Water distribution pipework pressure test certificate | |||
Water by-laws compliance certificate | |||
Certificate confirming chlorination of water distribution pipe work | |||
5. | Building Manual, including as-built drawings is complete, approved and issued in required format. | ||
Approved As-Built drawings issued. | |||
6. | Final account agreed. | ||
All contract instructions signed off and copies issued. | |||
7. | Condition surveys agreed between Contractor and Building Management. | ||
Building accepted by Building Management and handover recorded. | |||
8. | All snags rectified and signed off. Procedure agreed for defects and outstanding works. | ||
Agreed procedure and programme for the recording and rectification of works or defects outstanding or arising. | |||
9. | Statutory and main services authorities satisfied. | ||
10. | Project Review carried out and attended by all. |
Appendix B
Responsibility Matrix
Project Board/Project Team
The Project Board is ultimately responsible for the project, supported by the Senior User and Senior Supplier. The Board’s role is to ensure that the project is focused throughout its life cycle on achieving its objectives and delivering a product that will achieve the forecast benefits.
Throughout the project, the Project Board ‘owns’ the Business Case.
Specific Responsibilities
The Project Board is responsible for the overall business assurance of the project – that is, that it remains on target to deliver products that will achieve the expected business benefits, and that the project will be completed within its agreed tolerances for budget and schedule.
Business assurance covers:
The Senior User is responsible for specifying the needs of those who will use the final product(s), for user liaison with the project team and for monitoring that the solution will meet those needs within the constraints of the Business Case in terms of quality, functionality and ease of use.
The role represents the interest of all those who will use the final product (s) of the project, those for whom the product will achieve an objective or those who will use the product to deliver benefits. The Senior User role commits user resources and monitors products against requirements. This role may require more than one person to cover all the user interests. For the sake of effectiveness the role should not be split between too many people.
Specific responsibilities
The assurance responsibilities of the Senior User are to check that:
Senior Supplier
The Senior Supplier represents the interests of those designing, developing, facilitating, procuring, implementing and possibly operating and maintaining the project products. This role is accountable for the quality of the products delivered by the supplier(s). The Senior Supplier role must have the authority to commit or acquire supplier resources required.
Specific Responsibilities
The Senior Supplier is responsible for the specialist integrity of the project. The supplier assurance role responsibilities are to:
Project Manager
The Project Manager has the authority to run the project on a day-to-day basis on behalf of the Project Board within the constraints laid down by the board.
The Project Manager’s prime responsibility is to ensure that the project produces the required products to the required standard of quality and within the specified constraints of
time and cost. The Project Manager is also responsible for the project producing a result capable of achieving the benefits defined in the Business Case.
Specific Responsibilities
Stakeholder Lead
Specific responsibilities
Project Assurance
Assurance covers all interests of a project, including business, user and supplier.
Specific responsibilities
Project Administrative Support
Specific responsibilities
The following is a suggested list of tasks:
3.142.119.114