Index

Note: page numbers in italics refer to figures; page numbers in bold refer to tables.

aditional work 97, 138, 158 (see also variations)

approvals and consents 85

architect role 2, 19

architect’s instructions see instructions

archiving 21415

articles of agreement 1234

‘As-constructed’ Information 103, 136, 196, 198, 232

Association of Consultant Architects, PPC 2000 48, 178

 

bills of quantities 33, 99, 122, 1589, 227

BIM (Building Information Modelling) 98, 224, 232

budget see Project Budget

Building Contract

documentation 1227

forms of contract 6, 438

selecting 49

signing 124, 1257

Building Information Modelling (BIM) 98, 224, 232

building performance evaluation 2234, 227

Building Regulations 85, 201

building services 58, 72, 84

commissioning 194, 196

defects 200

Business Case 16, 17, 232

 

CAD (computer-aided design) 89, 103

CAWS (Common Arrangement of Work Sections for Building Works) 97

CDE (common data environment) 89, 101

CDM coordinator 197

CDM Regulations 98, 105, 197

CDP (contractor’s designed portion) 323, 228

certificate of making good defects 206, 207

certificate of non-completion 1757

certificate of Practical Completion 1778, 183, 1845, 198

certificates of progress payments see interim certificates

Change Control Procedures 34, 73, 78, 103, 1279, 232

Chartered Institute of Building (CIOB) contracts 48

claims against the contract administrator 137

claims for lost time and expense 167, 1701, 1734

clerk of works 156

collaborative working 401, 22930

collateral warranties 50, 228

commissioning 194, 196

Common Arrangement of Work Sections for Building Works (CAWS) 97

common data environment (CDE) 89, 101

Common Standards 29, 232

Communication Strategy 29, 2323

compensation events 1589, 168, 228

completion date 138, 146, 166, 175 (see also Practical Completion)

computer-aided design (CAD) 89, 103

Concept Design 58

Concept Design stage 5666

concurrent delays 174, 228

conditions of contract 1234

consents and approvals 85

Construction (Design and Management) Regulations 2007 (CDM regulations) 98, 105, 197

construction management contracts 201, 389, 64, 227

practical completion 178

retention monies 2012

construction phase health and safety plan 119

Construction Programme 14551, 233

Construction Project Information Committee 97

Construction stage 13286

Construction Strategy 59, 73, 85, 136, 233

contingency sums 97, 158, 227

contract administration systems 137, 140

contract administrator role 1821, 34, 1389, 227

contract administrator’s instructions see instructions

Contract Award Notice 119

contract documents 227 (see also Building Contract; drawings; specifications)

contract sum 33, 34, 143, 159

contract sum analysis 77, 163, 228

contractor-led projects 50, 51, 59, 73, 778

contractors (see also subcontractors)

claims for lost time and expense 167, 1701, 1734

pre-construction services 59, 60, 62

prequalification 74, 88, 913, 230

responsibilities 32

tender list 912, 934, 967

unsuccessful 121

contractor’s designed portion (CDP) 323, 228

drawings 157

Contractor’s Proposals (CPs) 233

one-stage design and build 767

two-stage design and build 63

Contractual Trees 233

construction management 39

design and build procurement 35

develop and construct 36

management contracting 40

traditional procurement 32

cost consultants 99, 139, 147, 163, 165, 203

Cost Information 41, 58, 97, 233

cost reimbursement contracts 33

covering up of work 144, 153

CPs see Contractor’s Proposals (CPs)

critical path analysis 145

 

dayworks 1656, 228

defect lists 155, 185, 200, 205, 206

defects 1556, 199201, 205, 228

and completion 1778

rectification 199200, 2058

defects liability period see rectification period

delays in the works 1667 (see also extensions of time)

design, construct, manage (and maintain) 378, 62

design and build contracts 1920, 348, 228 (see also one-stage design and build; two-stage design and build)

Construction Programme 146

contract administrator role 139

contract documents 122

interim certificates 163

issue of instructions 146

one-stage 747, 86

revision to completion date 171

two-stage 603, 73, 86

design change notices 128 (see also Change Control Procedures; variations)

Design Programme 58, 72, 86, 233

Design Queries 157, 233

Design Responsibility Matrix 29, 33, 84, 233

design team 32, 228

drawings 98

instructions issued by 151

novation 367, 229

develop and construct 35

Developed Design 72

Developed Design stage 708

discrepancies between drawings, specifications, etc. 167

document received sheet 103, 104

documentation (see also drawings; specifications)

archiving 21415

Building Contract 1227, 227

control 90, 1013

discrepancies in 167

tender documents 512, 62, 85, 97108 (see also Employer’s Requirements (ERs))

drawings 98, 102, 124

contractor’s designed portion 157

discrepancies 167

revisions to 103, 151

drawings register/issue sheets 1023

 

early warning procedures 169

electronic tendering (e-tendering) 8990, 228

employer’s agent 1920, 136, 138, 139, 228

Employer’s Requirements (ERs) 61, 64, 756, 2334

energy performance certificates 199

energy performance targets 225

errors in schedules 11315

EU procurement requirements 37, 88, 90

exceptionally inclement weather 167, 228

extensions of time 16673, 2023, 228

extranets 8990

 

Feasibility Studies 28, 62, 234

Feedback 212, 21516, 224, 234

FIDIC forms of contract 48, 159, 228

final account 203, 208

final certificates 20812, 228

Final Project Brief 58, 234

fitting out 198

fixed price contracts 33

force majeure 229

form of tender 105, 107

forms of building contract 6, 438

 

Gantt charts 145

glossaries

contract administration 22731

RIBA Plan of Work 2013 2326

Government Construction Strategy 41

government procurement see public sector procurement

 

handover 181, 1948

Handover and Close Out stage 190217

Handover Strategy 29, 59, 136, 194, 234

health and safety advisers 98, 105, 115, 197

health and safety file 197, 199

health and safety information (tenders) 98, 105

health and safety plan 119

Health and Safety Strategy 59, 234

Housing Grants, Construction and Regeneration Act 1996 162

 

In Use stage 21925

Information Exchanges 234

information release schedules 146

Initial Project Brief 28, 234

inspections 144, 1527, 181, 205, 206

instructions 143, 14651, 227

insurance 141, 186

interim certificates 1625, 229

International Federation of Consulting Engineers see FIDIC forms of contract

interviews with contractors 39, 62, 65, 77, 91, 115

invitation to tender 946

invitation to tender letter 108, 10910

 

Joint Contracts Tribunal (JCT) contracts 7, 47, 175, 229

 

late completion 1757

late information 1745

late tenders 112

latent defects 177, 201, 21113, 229

Latham Report 40, 45

letters see model letters

letters of intent 119, 120, 229

limitation periods 21213, 229

liquidated and ascertained damages 166, 175, 202, 203

loss and expense 166, 1734, 229

lump sum contracts 33

 

Maintenance and Operational Strategy 59, 73, 85, 225, 234

management contracting 3940, 635

management contracts 201, 3840, 635, 229

Construction Programme 146

contract administrator role 136

detailed design 73, 86

practical completion 178

tendering stage 59

MEAT (most economically advantageous tender) 88

mobilisation of contract 143

model letters

to client following Practical Completion 185 to client issuing certificates 165

to client issuing the final certificate 211

to contractor following Practical Completion 184

to contractor issuing contract documents 126

to contractor issuing the final certificate 212

preliminary invitation to tender 956

to successful contractor 120

tender invitation 10910

tender issue to client 111

tender report to client 11718

to unsuccessful contractors 121

‘most economically advantageous tender’ (MEAT) 88

 

NBS Building 97

NBS Contract Administrator software 7

NBS Create 97

NEC3 478, 229

compensation events 1689

‘taking over’ the works 181

variations 1589, 166

negotiated tenders 88

non-completion certificate 1757

non-compliance with tender instructions 112

notice of non-completion 1757

novation 367, 229

 

occupants’ guide 196

Official Journal of the European Union (OJEU) 92, 119

one-stage design and build 747, 86

one-stage tendering 229

open tendering 88

opening up the works 167

operating and maintenance (O&M) manuals 196, 198

 

partial possession 179, 229

parties to the Building Contract 1234

partnering 401, 22930

partnering contracts 41, 489, 178

PAS 91:2013 93, 230

patent defects 177, 201, 230

payments 1616

performance-based specifications 99

periodic inspections 152, 230

PII (professional indemnity insurance) 137

possession of the site 167

Post-occupancy Evaluation (POE) 2134, 234

PPC 2000 41, 489, 178

PQQs (prequalification questionnaires) 923

Practical Completion 1334, 17786, 234

tasks and procedures before 1948

tasks and procedures following 199203

Practical Completion certificate 1778, 183, 1845, 198

pre-construction information (health and safety) 98, 105

pre-construction services 59, 60, 62

pre-construction tasks 75, 1404

pre-contract meetings 1414

pre-handover meeting 181

preliminaries and contract details 1035

preliminaries and general conditions 97, 230

preliminary enquiries 946

Preparation and Brief stage 2652

pre-qualification 74, 88, 913, 230

pre-qualification questionnaires (PQQs) 923

prescriptive specifications 99

procurement (see also public sector procurement)

contract administrator role in 1821

options 3043

in RIBA Plan of Work 35, 4

Stage 1 activities 502

Stage 2 activities 59

Stage 3 activities 73

Stage 4 activities 85

procurement route 30

professional indemnity insurance (PII) 137

professional services contract 18 (see also Schedules of Services)

progress meetings 15961

progress monitoring 35, 137, 146, 1515

project archiving 21415

Project Budget 11618, 234

Project Execution Plan 29, 59, 73, 85, 2345

Project Information 194, 21415, 235

project managers 18, 19, 20, 139

Project Objectives 28, 235

Project Outcomes 28, 194, 213, 223, 225, 235

project partnering contract PPC 2000 489, 178

Project Performance 21516, 2234, 235

Project Programme 17, 235

Project Roles Table 29, 235

Project Strategies 58, 72, 84, 235

project team 2, 1718, 29, 230

design and build contracts 19

partnering contracts 41

provisional sums 97, 113

public sector procurement 37, 88, 90

project partnering 41

Soft Landings 195

tendering 118, 119

 

Quality Objectives 28, 235

quasi-arbitrator 34, 230

 

rectification period 178, 179, 186, 199, 2038, 230

relevant events 167, 202

re-measurement contracts 33, 1589

requests for information (RFI) 157

Research and Development (R&D) 223, 2356

retention monies 162, 178, 179, 2012, 208, 230

revisions to drawings 103, 151

RIBA contracts 467

RIBA Plan of Work 2013 1011

contractor-led projects 51

glossary 2326

management projects 63

one-stage design and build 74

traditional project 87

two-stage design and build 60

Risk Assessments 29, 423, 236

 

schedule of tenders received 113, 114

schedules of defects 155, 185, 200, 205, 206

schedules of rates 101, 2301

Schedules of Services 29, 222, 236

schedules of work 1001, 113, 124, 231

seasonal commissioning 194

sectional completion 134, 162, 175, 179, 231

sectional completion certificate 180

selective tendering 88

Site Information 28, 236

site meetings 15961, 197

site visits 1523, 161

smaller projects

client’s contractor 92

defective work 205

design team instructions 151

final account 203

pre-contract meetings 144

pricing of work 101

project roles 2, 18

site meetings 159, 161

site visits 153

at Stage 0 15

tender list 94

valuations 163

snagging 156, 231 (see also schedules of defects)

Soft Landings 195, 231

specialist subcontractors 323, 86, 146, 156

specifications 99, 124, 167, 231

speculative buildings 198

staged contracts see sectional completion

standard forms of building contract 438

standard letters see model letters

statutory consents 85

statutory limitation period 21213, 229

Strategic Brief 16, 17, 21, 236

Strategic Definition stage 1422

subcontractors, specialist 323, 86, 146, 156

substantial completion 178

supervision 152

supporting tasks at Stage 0 17

at Stage 1 29

at Stage 2 59

at Stage 3 73

at Stage 4 85

at Stage 5 136

at Stage 6 194

at Stage 7 223

suspension of the works 167

Sustainability Aspirations 28, 236

Sustainability Strategy 236

 

Technical Design 84

Technical Design stage 82129

technical queries (TQs) 157

Technology Strategy 29, 236

tenants 50

tender documents 512, 62, 85, 97108 (see also Employer’s Requirements (ERs))

tender list 912, 934, 967

tender process 90122

tender acceptance and award 11819

tender invitation letter 108, 10910

tender issue 10811

tender opening and assessment 11216

tender received schedule 113, 114

tender report 11718, 117

tender return 11112

tender summary forms 105, 106

tendering 8790, 231

document control 90

electronic 8990, 228

main forms of 88

number of tenderers 108

Stage 2 activities 5965

Stage 3 activities 748

Stage 4 activities 86

third party rights 50, 231

third party submissions 85

time at large 1378, 231

TQs (technical queries) 157

traditional contracts 19, 314, 231

contingency sums 97, 158

contract administrator role 1369

contract documents 122

training of users 194, 196, 198

two-stage design and build 603, 73, 86

two-stage tendering 231

 

user guides 196

user training 194, 196, 198

 

valuations 162, 163

value added tax (VAT) 163

variations 33, 147, 151, 1579, 170, 231

 

weather, exceptional 167, 228

websites 89

Work in Progress 236

work packages 39, 63

..................Content has been hidden....................

You can't read the all page of ebook, please click here login for view all page.
Reset
3.146.105.194