In this chapter, general guidelines for designing a polymer injection pilot will be provided. Best practices will also be discussed to make the most out of any injection trial.
Given the current recovery factors (averaging 35% oil originally in place (OOIP) after waterflood), there is a high potential for enhanced oil recovery (EOR) in brownfields, using existing infrastructure to facilitate the implementation. General guidelines were provided in Chapter 4 to assess the feasibility of polymer injection in a field. The two principal screening rules for polymer flooding are:
Polymer flooding has been applied in both sandstone and carbonate reservoirs. Because injection in carbonates requires a good reservoir understanding and thorough laboratory studies to find the most efficient chemistry, only sandstone reservoirs will be considered here; however, the main screening parameters apply to carbonates as well.
We can narrow the primary parameters needed to check whether polymer flooding is a viable option, by order of importance:
Table 0
Parameter | Preferred condition |
Lithology | Sandstones preferred |
Wettability | Water‐wet |
Current oil saturation | Above residual oil saturation |
Porosity type (matrix/fractures) | Matrix preferred |
Gas cap | See comments |
Aquifer | Edge aquifer tolerated |
Salinity/hardness | See comments |
Dykstra‐Parsons and facies variations | 0.1 < DP < 0.8 |
Clays | Low (see comments) |
Water‐cut | See comments |
Flooding pattern and spacing | Confined – small spacing |
The presence of clays can result in detrimental polymer loss within the reservoir, but solutions exist to minimize their impact on polymer efficiency. The potentially high salinity of the injection water is not a show‐stopper but will obviously impact the choice of chemistry and the dosage required to reach the target viscosity.
If screened reservoirs meet these criteria, there is a good chance that polymer flooding is technically viable. The next question is, is it economically viable? This aspect is very dependent on the particular field and should be discussed case by case.
The first step to de‐risk the technology and evaluate the possible benefits is a pilot test. The primary goals of this approach are the following:
A pilot will not necessarily break even and should not be designed as such. Proving a concept sometimes requires an innovative approach to de‐risk as many parameters as possible and find the optimum injection strategy for full‐field deployment (Figure 5.1).
Once a reservoir with acceptable characteristics has been chosen and polymer flooding is deemed applicable, the design can start. The first step consists of selecting the most appropriate zone for pilot injection. This decision is based on two main parameters:
The response time varies based on many factors including spacing, reservoir thickness, injection rates, production history, etc. The general ideas are as follows:
A detailed pattern analysis can be continued once the number of candidates has been narrowed using these criteria (Figure 5.2).
Defining a target viscosity (we should even say a resistance factor) is usually a prerequisite before starting any laboratory study or pilot design. If the reservoir is heterogeneous, with crossflow between layers, a calculation using Darcy's law shows that the ideal viscosity is equal to
The permeability contrast can be simply defined as the higher permeability divided by the lower permeability for adjacent layers with crossflow. In a case where no crossflow occurs, this term can be removed from the equation and only the mobility ratio considered. Seright [1] details the Daqing case where the end‐point mobility ratio is 10 and the permeability contrast is 4, yielding an optimum polymer viscosity of 40 cP. Obviously, in some heavy oil pools, this strategy is barely applicable, given the viscosity needed and the associated costs (not including injectivity aspects). But when possible, the mobility ratio value targeted should be less than 1, to take heterogeneities into account [2].
The volume of polymer injected is also very important. A rule of thumb is that at least 30% (or 50% in heavy oil pools) of the reservoir pore volume should be filled with polymer. However, from a reservoir engineering standpoint, and for good efficiency, the more the better. In Daqing, 60% of the reservoir has been filled with polymer; the volume is 80% in Mangala oil field (India), 50% in Shengli oil field (China), and 60% in Suffield (Canada) [1]. Stopping the injection depends largely on economics. When the cost of injecting polymer exceeds the benefits coming from the oil production, the process should cease [1], or a slug with a viscosity taper can be implemented to protect the back end of the entire polymer slug. A producer can be shut in when the water‐cut increases again to uneconomical values. If only 30% of pore volume has been injected, but oil is produced at economical rates, polymer injection should be continued. From a technical standpoint:
Additionally, in heterogeneous reservoirs, the size of the bank injected will have a huge impact on the following:
Simulation studies and sensitivity analyses can be performed to optimize bank size, determine the impact of water chase on slug integrity, and evaluate the benefits of injecting a higher‐viscosity polymer plug.
Once the parameters have been set, it is possible to design the injection protocol and set a list of variables that should be monitored during the injection.
Before the start of injection, the injection wells should be cleaned to allow good injectivity. When injecting in a mature reservoir, it is paramount to have a good water injection baseline, with stable injection rates and pressures to compare with polymer injection. There are different ways to start a polymer injection:
The first strategy helps obtain a good understanding of the flow regime, differentiating between linear and radial/matrix flow. In theory, if the flow is radial, an increase in viscosity from 1 to 2 cP at a given rate should lead to almost 50% injectivity loss (compared to water; see Section 5.3). If all injection guidelines to prevent polymer degradation have been respected, and if no significant injectivity loss is observed, then microfractures are likely present (see Section 5.3).
Hall plots can be used to monitor the reservoir response (see Section 5.4). If pressure does not stabilize and reservoir integrity is threatened, the best strategy is to decrease the injection rate without adjusting the viscosity.
No clear rule defines how to stop polymer injection, but, generally speaking, two approaches are possible:
However, in both cases, once water injection is resumed, there is a high risk that the water‐cut will rise rapidly in the producers, along with small fractions of the injected polymer, which can occur over a very long period.
The voidage replacement ratio (VRR) is the ratio of reservoir barrels of injected fluid to reservoir barrels of produced fluid. Balancing injection and production is a common reservoir management practice for conventional oil‐bearing formations. Recent studies [3 4] and analyses have suggested, for heavy oils, that targeting a VRR below 1 could improve recovery by:
Other authors have discussed this topic and shown that no clear correlations could be made with current field data, especially for Pelican Lake, where comprehensive information is available [5]. The compaction/dilation effect was also studied for a specific field in Suriname, showing that the injection strategy was indeed important, in addition to reservoir characteristics (heterogeneity), to explain the results observed in the field. The conclusions of the work were that there is an optimum rate, pressure, and viscosity to flood compressible formations. High injection rates could result in pressure and energy waste, dilating the formation and impairing oil displacement [6]. Other possible issues with VRR < 1 include the following:
In conclusion, the injection strategy depends on the reservoir and field constraints. A thorough reservoir analysis is required to understand all the parameters that influence oil recovery. For polymer injection, it is recommended, when possible, to balance injection and production; this will help with understanding the changes in fluid production and will enhance history matching.
A reservoir management strategy to maximize oil recovery may consist of purposefully building reservoir pressure at the start of polymer injection. For example, a strategy for a simple newly drilled pattern with two horizontal injectors and a central producer could be as follows:
This strategy has the advantage of building a homogeneous polymer front in the injection well, maximizing the reservoir length contacted and minimizing the formation of water/polymer fingers. An obvious drawback is the absence of fluid production during pressure build‐up. This time can be shortened by optimizing the spacing and injection strategy.
Concerns about injectivity issues are often raised, since a viscous solution is injected instead of water [7]. Mathematically speaking, the injectivity index, II, is defined as:
where Q = injection rate (std bbl/d); P bhi = bottom‐hole pressure; P e = reservoir pressure (in psi); k w = permeability (mD); μ w = water viscosity (cp); B w = water formation volume factor (res vol/ST vol) r w and r e are the wellbore and drainage radii, respectively (ft); h i = injection height (ft); and S = total near‐wellbore skin.
Looking at this equation, there are two important parameters for polymer injection: bottom‐hole pressure and viscosity. It is very difficult to know these values precisely at any point in the injection facilities, especially in the well and the near‐wellbore area, for these reasons:
A clarification is required regarding the definition of an injectivity issue. Given the previous equation and polymer injection, an injectivity issue it translates into a decrease of the injected volume into a given reservoir, compared to waterflood. Let's consider three cases:
Looking at all existing and past projects, published or not, very few cases have been reported where an injectivity decrease was observed at the start of polymer injection. A probable reason is the presence of microfractures in the near‐wellbore area created during the well's drilling/completion or during water injection (or injection of cold water into a hot reservoir). Some existing flow paths are beneficial to polymer injection, in that microfractures can be extended slightly, decreasing the shear rate in the near‐wellbore area and therefore minimizing possible mechanical degradation [9, 10] . In some specific cases, it is also possible to pre‐shear the polymer solution to remove very‐high‐molecular‐weight molecules and enhance injectivity. However, some benefits may be lost, such as viscoelasticity. One last method to improve polymer injectivity is hot‐polymer injection, whereby the polymer is warmed prior to injection and viscosity in the near‐wellbore area is low; as the polymer flows further from the wellbore, it is cooled in the reservoir, gaining in situ viscosity.
Understanding what happens in the near‐wellbore area is critical to the success of polymer injection. To build a business case, it is necessary to make predictions about the volumes injected and assume that the viscosity will remain intact during the project. In the near‐wellbore area, the main risk is mechanical degradation, either through perforations or at the sand face.
First, a differentiation should be made between vertical and horizontal injectors. Very often, the characteristics of horizontal wells make them good candidates for polymer injection: their length is important and the injection rate is not very high, especially onshore in shallow reservoirs. The area available for flow is therefore important, with low shear rates and little chance of mechanical degradation. Authors have also discussed the impact of completion [11], compaction/dilation, and fracture propagation in unconsolidated formations [12]. It is also possible to calculate the shear through orifices for completion with screens.
For verticals, completion is critical to ensure that little to no degradation occurs. The length and diameter of the perforation can be maximized to reduce shear; and the more perforations, the better (>12 shots per foot). But understanding the flow regime is also critical: the pressure drop and shear rate will not be the same if fractures exist.
Well tests and basic monitoring can help understand what happens in the well. First, it is necessary to obtain a steady water‐injection baseline and test reservoir pressure limits. Hall plots combined with pressure tests and other monitoring tools (step rate test) should be used to determine the parting pressure and set a maximum allowable pressure limit not to cross to minimize fracture propagation.
Another simple tool consists of analyzing injectivity through the value q/ΔP:
Where q = injection rate (barrels per day [BPD]), P = pressure drawdown (psi), k = permeability (md), h = formation height (ft), μ = fluid viscosity (cp), r e = external drainage radius (ft), and r w = wellbore radius (ft).
In order for this relationship to prove useful, very accurate measurements of the bottom‐hole injection and reservoir pressures should be known. In addition, flow capacity can be best represented if the injection well in question has been cored.
A careful review of existing field cases shows that most of the injections (water and polymer) were done under fracturing conditions [9, 10 13–15]. Several reasons can be given;
Given these possibilities, there is little chance that polymer will encounter the rock matrix immediately after the perforations.
The best way to check injectivity is to run a trial with polymer: injecting a relatively low viscosity will give information about the flow regime. In theory, if the flow is radial, the following equation can be used to predict injectivity, relatively to water:
with I/I 0 = injectivity relative to water; r p = radius of polymer front (ft); r e = external drainage radius (ft); r w (wellbore radius); and F r = resistance factor.
In that case, given an external drainage radius of 1000 ft, a wellbore radius of 0.3 ft and a resistance factor for polymer of 2 (1 for water), we obtain the plot of I/I 0 versus radius of polymer front shown in Figure 5.4.
Assuming no fractures, injectivity relative to water should decrease by 50% just by increasing the resistance factor from 1 to 2. First, this has never been observed in any field case documented. Second, if, during the trial, such a decrease is not observed, then it is likely the flow is not purely radial and microfractures exist. Such a test can be performed at a low injection rate to create favorable conditions for the polymer, to minimize potential mechanical degradation.
If fractures exist, there are important consequences:
Using microfractures or forcing their creation will help minimize mechanical degradation and maintain reasonable injection rates. Obviously, their extension should be controlled such that there is no direct connection between the injector and producer; the maximum distance should not be equal to more than one‐third the spacing. Fracture propagation can be followed with pressure and tracer tests, for instance. If rapid connection is observed, the injection rate should be decreased to allow partial closure of the fracture.
A thorough geomechanical analysis is also a good tool to understand fracture propagation and directions (vertical, horizontal, new versus reopened): geological properties of the reservoir, layering, facies, reservoir production history, reservoir depth, and injection rates will often limit fracture propagation (fluid leak‐off). Considerable information can be gathered from the hydraulic fracturing industry, where many efforts have been undertaken to understand fracture initiation and growth in tight formations. Below a certain depth, fractures grow vertically. Their growth will be limited by other geological formations or barriers, and there will be an increasing loss of fluid as it leaks into the most permeable zones [16]. In many formations, fracturing can be envisioned as similar to shattered glass, creating a complex fracture network that follows heterogeneities and whose extension is rapidly limited by fluid leak‐off (Figure 5.6).
Changes at the production side are another aspect that should be considered when discussing injectivity and injection rates. If the injection rate is decreased, but, at the production side, the oil‐cut and water‐cut percentages are switched in favor of oil production, then an economic balance can be reached. Here is a simple example: assume a void replacement ratio of 1 with 100 m3 d−1 water injected and 100 m3 d−1 of total fluid produced. If the water‐cut is 95% during the waterflood, then only 5 m3 d−1 of oil are produced. Now assume a decrease of 25% injectivity during polymer injection, and keep a void replacement ratio of 1; the total fluid injected and produced equal 75 m3 d−1. Assuming a decrease in water‐cut of 10% down to 85%, this translates to oil production of more than 11 m3 d−1, doubling the rate during waterflood. The fact that water‐cut decreases has a significant economic impact, since less water has to be treated and/or disposed of.
Before polymer injection, several tests can be performed to gain a better understanding of the reservoir and near‐wellbore area. These tests are also paramount for establishing a good baseline before switching to polymer injection. Typical tests include the following:
Water quality can be monitored in conjunction with probes for oxygen and salinity (conductivity), and periodic sampling for iron content. The level of contaminants should be clearly determined to adapt the injection strategy, water treatment facilities, and choice of polymer and its protective package (if required).
During polymer injection, pressure and injection rates are usually continuously recorded at the injection side. The Hall plot, shown in Figure 5.6, can be used to track trends and detect either plugging or fracture formation. At the production side, parameters such as total fluid produced, water‐cut, and oil‐cut should be recorded. In the long term, for a brownfield, we should look at the following:
In theory, the results of a pilot (total oil recovered) should be analyzed once the water‐cut again reaches the economic limit (98% or 99%).
3D modeling is a useful tool that can help predict the efficiency of polymer flooding, assuming the user has a good understanding of polymer physics and flow properties. The most critical part is modeling the near‐wellbore area to duplicate the results observed in the field during pilot injection. Two runs should be made and their differences analyzed:
Keywords related to shear‐thinning or shear‐thickening properties should be used carefully, with a good understanding of the wells' completion and the presence of damages or fractures. The most important parameters that can be obtained from laboratory experiments are resistance factors and retention. If no porous‐media experiment has been performed, it is possible to use the low‐shear viscosity obtained in conventional rheometers for simulation purposes, since, in the middle of the reservoir, the polymer solution will likely show Newtonian behavior given the low shear rates. Polymer degradation in the reservoir is usually limited, since the chemistry is always selected to remain stable during propagation throughout the reservoir. Input can be gathered from long‐term stability tests. A conservative approach should be taken for the residual resistance factor, using a value of 1. Sensitivity analyses should be made of slug size and viscosity, based on the water chase and a low Rk value, as mentioned earlier.
The model should be updated during the pilot injection and the results used to build the true business case.
The most important parameter in polymer flooding remains viscosity. Not everything can be controlled or anticipated, but many precautions can be taken to minimize the risk of degradation. If all engineering guidelines (for both surface facilities and well completions) are respected, along with close monitoring of water quality, then chances are that the viscosity will remain intact when entering the reservoir. There are currently two ways to control viscosity at the wellhead:
If not carried out properly, manual sampling can lead to polymer degradation due to the following:
Specific sampling methods and devices have been developed to avoid degradation during sampling and the measurement itself. The main drawback of manual sampling is manpower. To solve this problem, inline viscometers have been developed that display the viscosity value in real time [17]. Discrepancies from expected viscosity values can be observed quickly and actions taken to remedy the problem.
Product quality can be controlled with standard tests such as yield‐viscosity determination and filter ratio. All indications are provided in the certificate of analysis along with procedures to verify that the product falls within the specifications.
The design of polymer injection offshore is complex for several reasons. The first is footprint. When infrastructure is already in place, space and weight limitations often make the installation of new equipment complicated. This aspect, together with local constraints (weather and marine conditions), will dictate the choice of product form (powder or emulsion). The second aspect is related to the presence of devices such as chokes, which are difficult to replace or change and can dramatically degrade the polymer solution. Solutions exist that can still make the process viable:
A third aspect that impacts polymer injection is well spacing. Offshore, the residence time in the reservoir is quite long, and the response time is a matter of years. Without a decrease in spacing to get faster results, little can be done to accelerate the process:
The fact that distances are very significant drives people to choose very robust chemistries, always assuming that the polymer will be efficient all the way from the injection well to the producer. With current developments and new chemistries, polymers have robust designs that provide good stability. What might not be stable is the displacement of the polymer slug by the water chase, which will render the process inefficient and the use of expensive chemistries not completely justified. A compromise should be found to minimize expenses while ensuring good sweep efficiency and mobilizing oil in the long term.
Finally, water treatment can be a problem offshore if polymer is present in the effluents and the latter must be disposed of. The polymer will negatively affect standard equipment such as induced gas flotation (IGF), dissolved gas flotation (DGF), and hydrocyclones. The impact will greatly depend on how much polymer is produced and, therefore, how much polymer is injected (see the discussions in previous sections). In all cases, the best (and often only) strategy is to reinject the water containing polymer after separation and treatment. Studies are ongoing to understand the fate of polymer in a marine environment (see Chapter 4).
18.222.148.124