Consider the report in Figure 9-9, showing earned value figures for a project. Answer the questions by analyzing the data. Answers are provided in the Answers section at the back of the book.
1. | Is the task ahead or behind schedule? By how much? |
2. | Is the task overspent or underspent? By how much? |
3. | When the task is completed, will it be overspent or underspent? |