Section 3

Project Time Management

1 QUESTION

Project Time Management comprises which seven major processes?

ANSWER

  • Plan Schedule Management
  • Define Activities
  • Sequence Activities
  • Estimate Activity Resources
  • Estimate Activity Durations
  • Develop Schedule
  • Control Schedule

[Planning and Monitoring and Controlling]

2 QUESTION

Define total float.

ANSWER

The amount of time that an activity can be delayed from its early start without delaying the project end date or violating a schedule constraint.

[Planning]

3 QUESTION

Why is the key benefit of the plan schedule management process?

ANSWER

To provide guidance and direction on how the project schedule will be managed throughout the project

[Planning]

4 QUESTION

How are performance reviews used in control schedule?

ANSWER

As a tool and technique to measure, compare, and analyze schedule performance such as actual start and finish dates, percent complete, and remaining duration for work in progress

[Monitoring and Controlling]

5 QUESTION

What is included in the define activities process?

ANSWER

Identifying the specific actions to be performed in order to produce the project deliverables.

[Planning]

6 QUESTION

What are the four project documents that may need to be updated as an output of sequence activities?

ANSWER

  • Activity lists
  • Activity attributes
  • Milestone list
  • Risk register

[Planning]

7 QUESTION

Describe the relationship between the WBS and an activity list.

ANSWER

The activity list is developed from the identified work packages in the WBS.

[Planning]

8 QUESTION

What is another term used for the precedence diagramming method?

ANSWER

Activity-on-node.

[Planning]

9 QUESTION

What is the result of a critical path method (CPM) calculation?

ANSWER

Early and late start and finish dates for each activity based on a specified network logic and a single deterministic duration estimate. The focus is on calculating float to determine which activities have the least scheduling flexibility.

[Planning]

10 QUESTION

What is a planning package?

ANSWER

A component below the control account but above the work package that identifies project work that does not have detailed schedule activities.

[Planning]

11 QUESTION

What is included in sequence activities?

ANSWER

Identifying and documenting relationships among the project activities

[Planning]

12 QUESTION

What often happens as a result of resource leveling?

ANSWER

The original critical path will change.

[Planning]

13 QUESTION

Is elapsed time included when estimating required work periods?

ANSWER

Yes. For example, if “concrete curing” requires four days of elapsed time, it may require from two to four work periods, based on which day of the week it begins and whether weekend days are considered work periods.

[Planning]

14 QUESTION

Describe the four types of activity dependencies

ANSWER

  • Mandatory dependencies – ones that are legally or contractually required or inherent in the nature of the work
  • Discretionary dependencies – established based on knowledge of best practices or some unusual aspect of the project where a specific sequence is desired
  • External dependencies – involve a relationship between project activities and non-project activities
  • Internal dependencies – involve a precedence relationship between project activities and generally are within the team’s control

[Planning]

15 QUESTION

What is the critical path?

ANSWER

The longest path through the network, which represents the shortest amount of time in which the project can be completed.

[Planning]

16 QUESTION

List two tools and techniques used in plan schedule management.

ANSWER

  • Expert judgment
  • Analytical techniques

[Planning]

17 QUESTION

How does resource leveling work?

ANSWER

Start and finish dates are adjusted based on resource constraints with the goal of balancing resource demand with available supply.

[Planning]

18 QUESTION

What are the nine sections typically included in the Schedule Management Plan?

ANSWER

  • Project schedule model development
  • Level of accuracy
  • Units of measure
  • Organizational procedure links
  • Project schedule model maintenance
  • Control thresholds
  • Rules of performance measurements
  • Reporting formats
  • Process descriptions

[Planning]

19 QUESTION

What is the purpose of estimate activity resources?

ANSWER

Determine and identify the types and quantities of material, personnel, equipment, or supplies needed to complete each activity.

[Planning]

20 QUESTION

What does the following formula calculate?

[Optimistic + (4 × Most Likely) + Pessimistic] ÷ 6

ANSWER

An expected activity duration using a weighted average of three estimates. It is the method used in the PERT (Program Evaluation and Review Technique).

[Planning]

21 QUESTION

List four resource categories found in a Resource Breakdown Structure.

ANSWER

  • Labor
  • Material
  • Equipment
  • Supplies

[Planning]

22 QUESTION

What are three organizational process assets used in sequence activities?

ANSWER

  • Project files describing scheduling methodologies
  • Activity related policies, procedures, and guidelines such as the scheduling methodology
  • Templates

[Planning]

23 QUESTION

What is slack or float? Is it different from lag?

ANSWER

The amount of time that a particular schedule activity can be delayed without delaying the project.

Yes. Lag is waiting time between activities in a network.

[Planning]

24 QUESTION

What is a time-constrained schedule?

ANSWER

A project schedule that is fixed and cannot change. The unavailability of required resources for any activity is indicated by negative float.

[Planning]

25 QUESTION

Describe the four types of dependencies or precedence relationships in PDM. Of these, which one is the most commonly used dependency? Which one is the least commonly used?

ANSWER

  • Finish-to-start—The successor activity cannot start until the predecessor activity finishes
  • Finish-to-finish—The successor activity cannot finish until the predecessor activity finishes
  • Start-to-start—The successor activity cannot start until the predecessor activity starts
  • Start-to-finish—The successor activity cannot finish until the predecessor activity starts

Finish-to-start

Start-to-finish

[Planning]

26 QUESTION

What is the resource-constrained critical path called?

ANSWER

The critical chain.

[Planning]

27 QUESTION

What is crashing? What is its likely result?

ANSWER

A technique used to shorten the schedule for the least incremental cost by adding resources.

Crashing generally increases costs and results in increased risks.

[Planning]

28 QUESTION

What is the advantage of using a bar (Gantt) chart?

ANSWER

It is an effective progress-reporting tool, easily understood by most project stakeholders.

[Planning]

29 QUESTION

What is the schedule baseline?

ANSWER

The approved version of a schedule model that can only be changed through formal change control procedures and is used as a basis for comparison to actual results.

[Planning]

30 QUESTION

What is the project buffer?

ANSWER

An amount of time placed at the end of the critical chain to protect the target finish date from slippage along its path.

[Planning]

31 QUESTION

What are feeding buffers?

ANSWER

The amount of time placed at each point that a chain of dependent tasks not on the critical chain feeds into the critical chain. By doing so, the critical chain is protected from slippage along the feeding chains.

[Planning]

32 QUESTION

What are the disadvantages of using a bar (Gantt) chart?

ANSWER

  • It is a weak planning tool.
  • It does not show logical relationships between or among all project activities.

[Planning]

33 QUESTION

What is a resource breakdown structure? When is it prepared?

ANSWER

A hierarchical structure of the identified resources by resource category and resource type.

As an output from estimate activity resources.

[Planning]

34 QUESTION

What is estimate activity durations? Who should do the estimating?

ANSWER

Developing an approximation of the number of work periods needed to complete individual activities with estimated resources.

That person or persons most familiar with the work that needs to be performed.

[Planning]

35 QUESTION

What type of network logic diagram method was used to create the figure below?

image

ANSWER

PDM

[Planning]

36 QUESTION

How is work performance data used in control schedule?

ANSWER

To provide project progress information such as which activities have started, finished, or are in progress.

[Monitoring and Controlling]

37 QUESTION

What is the difference between a milestone chart and a bar chart as it relates to develop schedule?

ANSWER

The milestone chart identifies significant events such as a scheduled start of an activity, completion of a major deliverable, or approval to proceed by a higher authority. A bar chart graphically depicts an activity’s start and end dates, including its estimated duration.

[Planning]

38 QUESTION

How does PERT differ from CPM?

ANSWER

PERT uses the expected value (instead of the most likely estimate used in CPM) by using three time estimates per activity: pessimistic, most likely, and optimistic.

[Planning]

39 QUESTION

What are five tools and techniques used in estimate activity resources?

ANSWER

  • Expert judgment
  • Alternatives analysis
  • Published estimating data
  • Project management software
  • Bottom-up estimating

[Planning]

40 QUESTION

What PDM relationship is shown in the figure below?

image

ANSWER

Finish-to-finish.

[Planning]

41 QUESTION

What is fast-tracking? What is its likely result? What is a form of fast-tracking?

ANSWER

Performing activities in parallel that normally would be performed in sequence.

It often results in rework and usually increases risk.

Concurrent engineering

[Planning]

42 QUESTION

What is the focus of the critical chain network analysis technique?

ANSWER

To modify the project schedule to account for limited resources. Instead of managing the network paths’ total float, it manages the remaining buffer durations against the remaining durations of task chains.

[Planning]

43 QUESTION

What is analogous estimating?

ANSWER

Often called “top-down” estimating, it uses the actual duration of a previous, similar activity as the basis to estimate the duration of a future activity. It is a form of expert judgment. It is most reliable when the previous activities are similar in fact, not just in appearance, and when individuals preparing the estimate have the needed expertise.

[Planning]

44 QUESTION

What are two performance measurements used to assess the magnitude of variation to the original schedule baseline?

ANSWER

  • Schedule variance (SV)
  • Schedule performance index (SPI)

[Monitoring and Controlling]

45 QUESTION

What is the purpose of the schedule management plan?

ANSWER

It establishes the criteria and activities for developing, monitoring, and controlling the schedule.

[Planning]

46 QUESTION

Describe the concept of a “range of results” in activity duration estimating.

ANSWER

A quantitative assessment of the likely number of work periods required to complete an activity. Example: 2 weeks plus or minus 2 days—the activity will take at least 8 days and no more than 12 days.

[Planning]

47 QUESTION

What is develop schedule?

ANSWER

Analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.

[Planning]

48 QUESTION

When is the schedule baseline updated?

ANSWER

Immediately after approval is granted for change requests that impact project scope, activity resources, or activity duration estimates.

[Monitoring and Controlling]

49 QUESTION

What is the difference between a project calendar and a resource calendar?

ANSWER

A project calendar affects all resources. A resource calendar affects a specific resource or category of resources.

[Planning]

50 QUESTION

What are three examples of assumptions in estimate activity durations?

ANSWER

  • Existing conditions
  • Availability of information
  • Length of the reporting periods

[Planning]

51 QUESTION

What is the difference between lead and lag?

ANSWER

Lead is a modification of a logical relationship that allows an acceleration of the successor task. Lag is a modification of a logical relationship that directs a delay in the successor task.

[Planning]

52 QUESTION

How is simulation used in develop schedule? What technique is the most common?

ANSWER

To calculate multiple project durations with different sets of activity assumptions.

Monte Carlo Analysis.

[Planning]

53 QUESTION

How is reserve analysis used in estimate activity durations? How is the schedule contingency reserve determined?

ANSWER

To incorporate additional time into the project schedule as a reflection of schedule risk.

Contingency reserve can be a percentage of the estimated activity or project duration, a fixed and agreed-to number of work periods, or can be developed by using other quantitative methods.

[Planning]

54 QUESTION

How is the scope baseline used in define activities?

ANSWER

As an input to the process.

The WBS, deliverables, constraints, and assumptions documented in the scope baseline are considered as activities are defined.

[Planning]

55 QUESTION

What estimating problem is addressed through the critical chain method?

ANSWER

The tendency by those persons responsible for executing activities to be too conservative in their duration estimating, resulting in extended project durations and overestimation of required production resources such as staff specialists or unique equipment.

[Planning]

56 QUESTION

What should always be included as part of the supporting detail for the project schedule?

ANSWER

  • Detailed resource requirements by time period
  • Alternative schedules, such as best and worst case, not-resource-leveled, or resource-leveled dates
  • How contingency reserves are scheduled

[Planning]

57 QUESTION

How are performance reviews used in Control Schedule when the critical chain method is being used?

ANSWER

To help determine schedule status one can compare the amount of buffer remaining to the amount of buffer needed to protect the delivery date. Corrective action may be appropriate depending on the difference between the buffer needed and the buffer remaining.

[Monitoring and Controlling]

58 QUESTION

What is an example of an internal dependency?

ANSWER

If the project team cannot test a machine until it is developed

[Planning]

59 QUESTION

How is what-if scenario analysis used in develop schedule?

ANSWER

To test whether the project’s schedule is realistic under adverse conditions, and to prepare back-up plans to mitigate the impact of unexpected situations.

[Planning]

60 QUESTION

What are three examples of organizational process assets that may be updated as a result of control schedule?

ANSWER

  • Causes of variances
  • Corrective actions chosen and the reasons
  • Other types of lessons learned from project schedule control

[Monitoring and Controlling]

..................Content has been hidden....................

You can't read the all page of ebook, please click here login for view all page.
Reset
3.133.144.59