Section 4

Project Cost Management

1 QUESTION

Define Project Cost Management.

ANSWER

Processes involved in planning, estimating, budgeting, and controlling costs so the project can be completed within the approved budget

[Planning and Monitoring and Controlling]

2 QUESTION

What is the key benefit of Plan Cost Management?

ANSWER

To provide guidance and direction on how the project costs will be managed throughout the project

[Planning]

3 QUESTION

Identify four organizational process assets used in estimate costs.

ANSWER

  • Cost estimating policies
  • Cost estimating templates
  • Historical information
  • Lessons learned

[Planning]

4 QUESTION

List three general financial management techniques when predictions and analyses are included in Project Cost Management.

ANSWER

  • Return on investment
  • Discounted cash flow
  • Investment payback analysis

[Planning]

5 QUESTION

What is the BAC? What question does it answer?

ANSWER

Budget at completion. It is the total Planned Value for the project and constitutes the cost performance baseline.

What is the total job supposed to cost?

[Planning and Monitoring and Controlling]

6 QUESTION

What is the payback period?

ANSWER

The number of time periods up to the point at which cumulative revenues exceed cumulative costs and, therefore, the project has “turned a profit.”

[Planning]

7 QUESTION

How is the WBS used in determine budget?

ANSWER

As an input the process.

The WBS provides the relationships among all project deliverables and their various components.

[Planning]

8 QUESTION

What is the internal rate of return (IRR)?

ANSWER

The percentage rate that makes the present value of costs equal to the present value of benefits.

[Planning]

9 QUESTION

What is the AC? What question does it answer?

ANSWER

AC means actual costs or the actual cost incurred in accomplishing work on a WBS activity component or on the total project.

How much did the completed work cost?

[Monitoring and Controlling]

10 QUESTION

What is PV? What question does it answer?

ANSWER

Planned value.

It is the authorized budget assigned to the work scheduled to be accomplished for an activity or WBS component.

How much work should be done?

[Monitoring and Controlling]

11 QUESTION

List two enterprise environmental factors that can be used in estimate costs.

ANSWER

  • Marketplace conditions
  • Published commercial information

[Planning]

12 QUESTION

When do activity duration estimates affect project cost estimates?

ANSWER

  • When “cost of financing” project activities is a reality
  • When costs are based on the number of units of time estimated
  • When costs are sensitive to time such as union labor rates increasing on a certain date

[Planning]

13 QUESTION

What is the EAC? What question does it answer?

ANSWER

Estimate at completion—the expected total cost of a schedule activity, a WBS component, or the project at completion.

What do we now expect the total job to cost?

[Monitoring and Controlling]

14 QUESTION

What is ETC? What question does it answer?

ANSWER

Estimate to complete the expected cost to complete a schedule activity, a WBS component, or the project.

What do we need to spend to complete the remaining work?

[Monitoring and Controlling]

15 QUESTION

What is EV? What question does it answer?

ANSWER

Earned value—the value of the work performed expressed in terms of the approved budget assigned to that work for a schedule activity or WBS component.

How much work is done?

[Monitoring and Controlling]

16 QUESTION

What is the “50-50” rule of progress reporting? What assumption underlies this rule?

ANSWER

When beginning a task, charge 50 percent of its PV to its account; when the task is completed, charge the remaining 50 percent to its account.

All tasks generally are of the same size.

[Monitoring and Controlling]

17 QUESTION

Identify ten estimate cost tools and techniques

ANSWER

  • Expert judgment
  • Analogous or top-down estimating
  • Parametric estimating
  • Bottom-up estimating
  • Three-point estimating
  • Reserve analysis
  • Cost of quality
  • Project management estimating software
  • Vendor bid analysis
  • Group decision-making techniques

[Planning]

18 QUESTION

How is schedule variance (SV) calculated?

ANSWER

SV = EV – PV

[Monitoring and Controlling]

19 QUESTION

If you are using the payback period to compare projects A and B, and project A has the shortest payback period, what does this mean?

ANSWER

Project A becomes profitable more quickly.

[Planning]

20 QUESTION

What are direct costs?

ANSWER

Costs incurred directly by a specific project.

[Planning]

21 QUESTION

Analogous estimating is most reliable when two conditions are met. Describe them.

ANSWER

  • When the previous projects have similar characteristics as the current project
  • When the person(s) preparing the estimates has the required expertise

[Planning]

22 QUESTION

What is parametric cost estimating, and how can it provide higher levels of accuracy?

ANSWER

It uses a statistical relationship between relevant historical data and other variables to calculate a cost estimate for the project work. Higher levels of accuracy are achieved based on the sophistication of the data in the model.

[Planning]

23 QUESTION

Describe bottom-up estimating.

ANSWER

Estimating and then summarizing or rolling up the cost of individual activities or work packages to get a project total.

[Planning]

24 QUESTION

What are management reserves? Are they in the cost baseline?

ANSWER

An amount of the total budget withheld for management purposes for unforeseen work or for “unknown unknowns”

They are not part of the cost baseline but are part of the overall project budget and funding requirements.

[Planning]

25 QUESTION

What are variable costs?

ANSWER

Costs that rise or fall directly with the size of the project.

[Planning]

26 QUESTION

List the five recommended types of supporting detail for activity cost estimates.

ANSWER

  • The basis for the estimate
  • The assumptions made
  • The constraints
  • An indication of the range of results (e.g., $5,000 ± 10%)
  • An indication of the confidence level of the final estimate

[Planning]

27 QUESTION

How is the cost performance index (CPI) calculated?

ANSWER

CPI = EV / AC

[Monitoring and Controlling]

28 QUESTION

List nine items to be part of the cost management plan.

ANSWER

  • Units of measure
  • Level of precision
  • Level of accuracy
  • Organizational procedures link
  • Control thresholds
  • Rules of performance measurement
  • Reporting formats
  • Process descriptions
  • Additional details

[Planning]

29 QUESTION

What does the cost management plan describe?

ANSWER

How the project costs will be planned, structured, and controlled

[Planning]

30 QUESTION

What is the variance at completion (VAC)? How is it calculated?

ANSWER

The difference between the total amount the job was supposed to cost (BAC), and the amount the job is now expected to cost (EAC).

VAC = BAC – EAC

[Monitoring and Controlling]

31 QUESTION

What is the status of this project?

image

ANSWER

Over budget (AC is higher than PV) and behind schedule (EV is less than PV).

[Planning]

32 QUESTION

What is determine budget?

ANSWER

Aggregating the estimated costs of all individual activities or work packages in the WBS to establish an authorized cost baseline.

[Planning]

33 QUESTION

What are fixed costs? Are they recurring or nonrecurring costs?

ANSWER

Costs that do not change based on the number of units.

Nonrecurring.

[Planning]

34 QUESTION

What is a rough order-of-magnitude estimate? When is it performed? What is its accuracy range?

ANSWER

An approximation without detailed data.

Often done early in a project when you need a “ballpark estimate.”

±50 percent.

[Planning]

35 QUESTION

What are the nine inputs to determine budget?

ANSWER

  • Cost management plan
  • Scope baseline
  • Activity cost estimates
  • Basis of estimates
  • Project schedule
  • Resource calendars
  • Risk register
  • Agreements
  • Organizational process assets

[Planning]

36 QUESTION

What are indirect costs?

ANSWER

Costs that are part of the overall organization’s cost of doing business and are shared among (allocated to) all the projects that are under way.

[Planning]

37 QUESTION

How is a definitive estimate prepared? Give an example of one. What is its accuracy range?

ANSWER

From well-defined, detailed data.

A bottom-up estimate.

-5 to +10 percent.

[Planning]

38 QUESTION

What is the cost baseline?

ANSWER

Authorized version of the time-phased budget, excluding management reserve, which can only be changed through formal change control processes and is used for comparison to actual results.

[Planning]

39 QUESTION

How is the SPI calculated?

What does it tell us?

What does an SPI less than 1.0 mean?

ANSWER

SPI = EV / PV

As a progress measure it tells us how much work has been achieved compared to the plan.

Less work was completed than planned.

[Monitoring and Controlling]

40 QUESTION

How is CPI calculated?

What does it tell us?

What does a CPI greater than 1.0 mean?

ANSWER

CPI = EV / AC

Measure of work value completed compared to actual cost of completed work.

Cost under-run.

[Monitoring and Controlling]

41 QUESTION

What are the four organizational process assets used for the plan cost management process?

ANSWER

  • Financial control procedures
  • Historical information and lessons learned knowledge bases
  • Financial databases
  • Existing cost estimating and budgeting-related policies, procedures, and guidelines

[Planning]

42 QUESTION

What are the four inputs to the control costs process?

ANSWER

  • Project management plan
  • Project funding requirements
  • Work performance data
  • Organizational process assets

[Monitoring and Controlling]

43 QUESTION

What is present value (PrV)? How is it calculated?

ANSWER

The value today of future cash flows based on the concept that payment today is worth more than payment tomorrow.

PrV=Mt(1+r)t

Mt = amount of payment t years from now

r = interest rate (or discount rate)

t = time period

[Planning]

44 QUESTION

When is rebaselining required?

ANSWER

When the cost variances are so severe that a complete revision of the project budget is needed to provide a realistic measure of performance.

[Monitoring and Controlling]

45 QUESTION

How are group decision-making techniques used in estimating costs?

ANSWER

To improve accuracy and commitment to the emerging estimates

[Planning]

46 QUESTION

List four ways to calculate EAC.

ANSWER

  • EAC = BAC/CPI
  • EAC = AC + BAC – EV
  • EAC = AC + BottomupETC
  • EAC = AC + [(BAC – EV)/(CPI × SPI)]

[Monitoring and Controlling]

47 QUESTION

What is the basis for a budget estimate?

When is it used?

What is its accuracy range?

ANSWER

This type of estimate is based on data that are more detailed than those used for an order-of-magnitude estimate.

Used to establish initial funding and to gain project approval.

-10 to +25 percent.

[Planning]

48 QUESTION

What is the to-complete-performance index (TCPI)?

What does it tell us?

Is it based on BAC or EAC?

ANSWER

  • The ratio of the “remaining work” to the “funds remaining.”
  • Tells us the cost performance that must be achieved on the remaining work to meet a specific goal.
  • It can be based on either BAC or EAC. If BAC is viable, equation is:

BAC = (BAC – EV) / (BAC – AC)

If BAC is not viable, equation is:

EAC = (BAC – EV) / (EAC – AC)

[Monitoring and Controlling]

49 QUESTION

Why is the management reserve added to cost baseline?

ANSWER

To produce the project budget.

[Planning]

50 QUESTION

What is value analysis?

ANSWER

A cost-reduction tool that involves careful analysis of a design or item to identify all the functions and the cost of each one. It considers whether the function is necessary and whether it can be provided at a lower cost without degrading performance or quality.

[Planning]

51 QUESTION

How is cost variance (CV) calculated?

ANSWER

CV = EV – AC

[Monitoring and Controlling]

52 QUESTION

Which sections of the project management plan are used in the control cost process?

ANSWER

Cost management plan

Cost baseline

[Monitoring and Controlling]

53 QUESTION

When should EAC be calculated by: BAC/CPI?

ANSWER

If the CPI is expected to be the same for the remainder of the project.

[Monitoring and Controlling]

54 QUESTION

When should EAC be calculated by: AC + BAC – EV?

ANSWER

If future work will be accomplished at the planned rate

[Monitoring and Controlling]

55 QUESTION

When should EAC be calculated by: AC + Bottomup ETC?

ANSWER

If the initial plan is no longer valid

[Monitoring and Controlling]

56 QUESTION

What is the difference between variance analysis and trend analysis in project cost management?

ANSWER

Variance analysis is a technique that compares actuals to planned data to determine degree of variation to cost baseline.

Trend analysis looks at data over a specified time period to see if performance is improving or deteriorating.

[Monitoring and Controlling]

57 QUESTION

What drives the cost and accuracy of bottom-up estimating?

ANSWER

The size and complexity of the individual activity or work package.

[Planning]

58 QUESTION

Define control costs.

ANSWER

The process of monitoring project status to update the project costs and manage changes to the cost baseline

[Monitoring and Controlling]

59 QUESTION

What does the benefit–cost ratio not tell you?

ANSWER

The absolute value of the benefit or cost.

[Planning]

60 QUESTION

When should EAC be calculated by:

EAC = AC + [(BAC – EV)/(CPI × SPI)]?

ANSWER

If both the CPI and SPI influence the remaining work

[Monitoring and Controlling]

..................Content has been hidden....................

You can't read the all page of ebook, please click here login for view all page.
Reset
18.220.125.100