Name | Position | Signature | Date |
---|---|---|---|
Author | Well Test Engineer | ||
Review | Logistics Superintendent | ||
Approval | Drilling Department Manager |
Name | Position | Type | Hard Copies Qty |
---|---|---|---|
Name 1 | Drilling Department Manager | Hard & Soft | 1 copy |
Name 2 | Logistics Superintendent | Hard & Soft | 1 copy |
Name 3 | Well Test Engineer | Hard & Soft | 1 copy |
Name 4 | Offshore Drilling Supervisor | Soft | |
Name 5 | Well Test Contractor Focal Points | Soft | |
File | Document Control | Soft |
This document details logistics planning specific to well test operations and should be read in conjunction with any existing Resource Company logistics plan for this campaign.
The logistics superintendent based in the company head office has overall authority for managing logistics for this operation. A shore base supervisor and a wellsite logistics supervisor both report to the logistics superintendent.
Logistics personnel structure is as follows
Name | Position | Phone | |
---|---|---|---|
Name 1 | Logistics Superintendent | Head office phone | Name1@email |
Name 2 | Shore base Supervisor | Shore base phone | Name2@email |
Name 3 | Wellsite Logistics Supervisor | Wellsite phone | Name3@email |
The Logistics Superintendent is the sole focal point responsible for authorising any equipment movements to or from the Resource Company shore base. All equipment and materials must comply with the following requirements.
The movement of equipment to or from the wellsite shall be the responsibility of the wellsite logistics supervisor. The wellsite logistics supervisor will liaise with the resource company drilling supervisor and the well test engineer to plan equipment movements to and from the wellsite. Requirements for any such movements are the same as 1.3.
Personnel travel to or from the wellsite shall be the responsibility of the wellsite logistics supervisor, who will forward check in and itinerary's to each contractor focal point for distribution to contractor personnel.
Personnel will travel from the airport to the offshore facility via helicopter. The helicopter check in is located inside the airport terminal and is clearly marked.
The offshore drilling facility is located 100 kms from the airport, in order to manage POB, and to prioritise personnel according to operations, the wellsite logistics supervisor will liaise with the resource company drilling supervisor and the well test engineer to plan personnel movements to or from the wellsite.
Unless by prior arrangement, the airport shall be designated point of origin for all contractor personnel. Contractor personnel are responsible for arranging their own travel to and from the airport.
Personnel travelling to or from an offshore facility must comply with the following
3.14.80.45