APPENDIX A.4: PROBLEM REPORT

Problem report
Project Health and safety rules re-training Date 12/02/2016 Version no. 01
Problem: Incomplete specification.
Cause: New legislation still being produced.
Consequences: Cannot finalise training material.
Options
Option 1: Close the specification with what is known today.
Impact: Possible fine. Incomplete training. Possible failure to fully meet new rules.
Option 2: Plan a second project to action new material after the start of this project.
Impact: £300. Unnecessary cost of starting a new project. Difficulty in planning team members’ future work.
Option 3: Continue to accept new rules throughout development and plan for last-minute changes.
Impact: No cost.
Recommendation: Option 3.
Decision   By   Signed  