Appendix A: Key Concepts

Chapter 1 : Introductions

  • Critical Chain can be used to help deliver projects faster and more reliably.
  • Theory of Constraints (TOC) is a set of general problem-solving tools that can be used to look at an organization as a whole, identify areas to focus on, and drive overall improvements. It can be used help focus teams on any improvement effort from Critical Chain, Scrum, Agile, new technology deployments, and so on.

Chapter 2 : High-Level Critical Chain Overview

Critical Chain is a Theory of Constraints solution that addresses the common problems found in project management so you can better plan, manage, and be more successful with projects.
Theory of Constraints (TOC) is a general problem-solving model that can be applied to a variety of environments, but it has one fundamental concept. In looking at any kind of system such as project management, manufacturing, or distribution, you can find one constraint that is limiting the overall system. If you focus improvement efforts on this constraint, the whole system will benefit and the bottom line of the organization will improve.
Common project-management issues Critical Chain can help address:
  • Projects miss critical deadlines and market opportunities [crt 25]
  • You cut too many key features to make deadlines [crt 19]
  • Your products are not competitive enough (due to slow project turnaround, missing deadlines, and cutting key features) [crt 23]
  • There is too much resource burn-out and turnover [crt 14]
  • You go over budget due to project overruns and do not make expected revenues our product lines [crt 26]
  • There are internal projects fights over shared resources [crt 18]
Possible Critical Chain benefits :
  • On-time delivery of products significantly improves [frt 8]
  • You are able to complete projects much faster [frt 8]
  • Hidden or misused resource capacity is surfaced [frt 12]
  • The company and its products are more competitive [frt 14]
  • The company is more profitable [frt 20]
For sample results, see these web sites for the latest results:
Key Critical Chain components that help you get results are:
  • Project buffers to better manage task variability [frt 1]
  • Reducing bad multi-tasking to find hidden and misused resource capacity [frt 1]
  • Building schedules (back-to-front) and challenging assumptions [frt 1]
  • Organizational analysis (TOC TP) to better understand our overall project environment (creating the CRT and FRT)
You can mix project-management methodologies (Critical Chain, Scrum, Agile, etc.), but you really need to have a solid grounding in each of the methodologies you are trying to mix. If you want to learn more about combining Lean, Six Sigma, and TOC, you can look at the TOC book Velocity .

Chapter 3 : Factors for Success

Successful implementations ideally have:
  • A certified Critical Chain implementation expert who really understands the mechanics of the Critical Chain solution, including how to use it to improve the organization’s throughput and how to successfully implement it in an organization.
  • Someone who has Critical Chain software tool experience.
  • For complicated and political environments, someone who is certified Theory of Constraints Thinking Process background who can complete an organizational analysis.
  • An organization with a compelling need and desire to change.
  • Metrics that encourage desired behaviors.
Some of the environmental issues to consider can include the following:
  • Does the organization’s project team take ownership of the Critical Chain solution?
  • Is senior management on board with the solution? The other way of looking at it is your organization independent and isolated enough that you can set up and manage schedules how you want, without senior management involvement as long as you deliver products successfully?
  • How complex is your project environment? Single project? Matrixed multi-project?
  • Does the organization have good or poor project-management practices?
The better the organization understands Critical Chain and the characteristics and factors mentioned, the better you can help move the implementation along as well as make sure the person you have helping implement it in your organization is covering everything needed.

Chapter 4 : Concepts

Key CCPM benefits that help you get results are:
  • Project and feeding buffers to better manage variability
  • Reducing bad multi-tasking to find hidden or misused resource capacity
  • Building schedules back-to-front challenging assumptions
  • Organizational Analysis (TOC TP) to better understand your environment
The Organizational Analysis (TOC TP) can help you:
  • Understand the organizational environment and constraints that limit your success
  • Understand the issues, how they interconnect, and what the core drivers are
  • Understand how Critical Chain can help you address these issues
  • Understand what outside of Critical Chain is needed to ensure your success

Chapter 5 : Championing Ideas

  • Just having a good idea by itself does not make things happen; you often need someone who can help champion the idea through the organization. This person needs to meet with key stakeholders to identify the benefits for their area, identify the concerns they have for their area, and work to minimize these concerns. The champion also needs to understand the organization’s approval process and drive the idea through this process in the most efficient way possible.
  • In addition to having external Critical Chain expertise to help you implement the Critical Chain solution, it is advisable to have an internal Critical Chain champion to help drive the implementation, work on key stakeholder concerns and issues, and navigate the organization’s adoption process.
  • The TOC Cloud tool can be helpful in looking at conflicts to find unique ways to resolve them.
    • For day-to-day conflicts, the clouds from the Management Skills Workshop (MSW) can be helpful.
    • For organizational conflicts in complex environments, it is important to look at the TOC Thinking Process in addition to the cloud to fully develop solutions and implementation plans.
  • The TOC cloud is composed of the following pieces:
    • The common goal both sides share (A)
    • The needs each side has (B, C)
    • The wants each side is verbalizing that are being driven by the wants (D, D’)
  • The assumptions you should commonly challenge on the cloud are:
    • The true conflict between both sides’ wants (DD’)
    • Each side’s connection between the need and want (BD, CD’)

Chapter 6 : Implementation Steps

Phoenix Setup :
  • When looking at moving an organization onto Critical Chain ideally, you should try to move the whole organization. If time is an issue then you can look at staggering the implementation and pick one or two high-impact projects to focus on. They need to have a bottom-line impact as well and cannot be side projects since the effort needed and results created would not be taken seriously.
  • If necessary, it is possible to intercept a project already in process and simply build the new Critical Chain schedule from where the project is currently at to the end.
  • To really make a culture change in an organization, you need three things:
    • Top management buy-in and agreement to lead the charge
    • Determine key measurement changes that will incentivize the desired behaviors of the new culture
    • Education for all involved, including the new measurements.
Phoenix Network Build :
  • As part of the network build, it is important that the managers and the team learn the key Critical Chain concepts [Chapters 2 and 4 items].
  • You want to be sure to build the project to throughput (where you generate income or further the goals of the organization).
  • When you build the schedule, you look at the project’s goal and build backward using the phrasing in order to.. we must.. and add in any dependencies.
  • When you need to compress and tighten a schedule up, look at BORA: B reak a link, O verlap tasks, R educe scope or duration, or A dd a resource.
Phoenix Execution :
  • As you execute the schedule, the team should have regular, typically weekly, schedule updates. As part of these updates, the project manager and the team should review the fever chart for the different project and endpoint/milestone buffers. The fever chart measures how much buffer you have consumed compared to how much of the project you have completed. Green means you are on track, yellow means you are falling behind and need to look at ways to recover, and red means that you are putting the project deadline at risk and need to act to add time back into the buffer.
  • To add time back into the buffer, review BORA: B reak a link, O verlap tasks, R educe scope or duration, or A dd a resource.
  • As you execute the project, there are several behaviors you’ll want to be sure to maintain. These were covered in Chapters 2 and 4 . Some of these behaviors include:
    • Roadrunner: You encourage people to work as quickly as they can.
    • Relay race: You encourage people to cleanly hand off work to the next resource (dependency) as quickly as possible.
    • Reduce bad multi-tasking: You want to avoid any multi-tasking that stretches out work and delays hand-offs.
    • Management does not beat up resources for missing focused times, the focus times are aggressive by design so you should expect that several will be missed. You’ll want to manage the overall project buffer and overall deadline, not micro-manage resources.
Phoenix Post-Mortem Plan :
1.
POOGI stands for the Process Of OnGoing Improvement. Once you have set up a new process, you need to maintain and continue to improve upon it.
 
Micky’s Urgent Requests :
1.
Even when you set up Critical Chain, it is not foolproof. If you let too much work into the system, you will flood it. So you must have good discipline and manage a good change control process.
 
2.
If you know you will always have changes at key points in the schedule, you should try to minimize these changes (i.e., change control) as well as proactively reserve capacity for these changes.
 

Chapter 7 : Ambitious Targets

  • When people put together a plan for a project, they often focus on the tasks involved. For example, the QA tests that need to be identified and run. The ambitious target tool can help you look broader. You can clarify the goals of the overall project and identify issues and concerns that the team has in general based on past experience as well as in trying to meet the project’s goal.
  • The Ambitious target tool allows you to successfully use an individual’s innate ability to complain in a constructive way to find ways to address concerns and make the project more successful.
  • Key steps in creating an Ambitious target include:
    1.
    Define a goal that is clear, concise, and measurable.
     
    2.
    Have the team identify issues and concerns in trying to reach the specific goal, leveraging past experience when possible.
     
    3.
    Develop suggestions (sometimes called intermediate objectives ) to address each issue. Make sure that the team feels confident that the suggestions can successfully help them reach the goal. If not, review the additional issues and develop additional suggestions.
     
    4.
    Sequence the suggestions into a tangible plan that is regularly tracked.
     
    5.
    When reading ambitious targets, use in order to (above item) we must (below item). For example, in order to reach the goal of shipping a product that meets the QA customer release criteria, we must detail out the QA customer release criteria .
     

Chapter 8 : Individual Buy-In

  • The six layers of resistance give you a systematic framework on how you can organize your analysis (CRT, FRT, etc.).
  • The buy-in process is how you conversationally walk through someone through your analysis and the layers of resistance to get their understanding and potential acceptance.
The six layers of resistance:
  • Layer 1: Lack of consensus on the problem.
  • Layer 2: People do not agree on the direction of the solution.
  • Layer 3: Arguing the proposed solution cannot yield the desired outcome.
  • Layer 4: Yes, but . Concerns about potential negative side-effects from proposed solution.
  • Layer 5: Obstacles that stand in the way of implementing solution into the environment.
  • Layer 6: Raising doubts, wait and see, unverbalized fears.
How to approach each layer:
  • Layer 1: Lack of consensus on the problem.
    • Pre-work : Build out the CRT for the organization to understand the issues, how they interconnect, and the core problem driving the issues.
    • Buy-in : Pick a few key issues that resonate with that person’s area and the organization as a whole and work to quantify their impact. Then verbally walk through how they are interconnected.
      • Don’t show the CRT or FRT to people (at least not the first meeting). It tends to overwhelm and frustrate people not familiar with TOC. It’s just like showing a page of calculus formulas to someone who doesn’t know calculus and saying, “isn’t this great”!
  • Layer 2: People do not agree on the direction of the solution.
    • Pre-work : Focus on the core conflict and the key injection(s) necessary to break it.
    • Buy-in: Review the cloud by showing or verbally walking through the conflict. Then work with the person to realize (better) or reveal to them the key injection. Then promptly move onto Layer 3 to justify why the injection addresses the issues of the organization.
  • Layer 3: Arguing the proposed solution cannot yield the desired outcome.
    • Pre-work : Build out the organization’s FRT.
    • Buy-in : Start with the key injection and verbally walk through and show how the key injection leads to and is connected to several of the key benefits of the FRT. Cover just the key benefits that the person you are talking will find of value; there is no need or value to cover them all.
  • Layer 4: Yes, but. Concerns about potential side-effects from proposed solution.
    • Pre-work : If possible, try to anticipate negative effects from your suggested direction. Then try to come up with recommendations that negate these issues if they come up. The negative branch (NBR) TOC tool is typically used for these issues.
    • Buy-in : Be patient and be ready to address any concerns raised.
  • Layer 5: Obstacles that stand in the way of implementing solution into the environment.
    • Pre-work : If possible, try to anticipate any potential obstacles and how they could be overcome.
    • Buy-in : Be patient and ready to address any concerns raised.
  • Layer 6: Raising doubts, wait and see, unverbalized fears.
    • Pre-work : Be aware of this challenge and look for ways to address it.
    • Buy-in : As you get buy-in, work to get commitments and timelines for people to act.
      • If you find some people are holding back, try to see what their concerns are. Work to surface any “yes, but” concerns and obstacles then work to address them.
      • If people seem to be holding back and it seems more driven by fear and doubt, work with them to see the pain with the current process and the value in moving to the new process.
  • Be sure to focus blame on the system. Avoid finger pointing and focus on the system and how the way it operates is holding the company back.
  • Be sure to close the deal. For an initial or exec meeting, layers 1-3 are good. Always be sure to close the deal and get some commitment at the end of the meeting (otherwise, why did you hold the meeting in the first place?). Address the remaining layers (yes..but, obstacles, etc.) as they come up or in subsequent meetings.

Chapter 9 : Almost

  • Randal and Tim Prep :
    • Once you have created the CRT, FRT, and your plan to address the six layers of resistance, you are ready to start working with people to get their buy-in. You just have to tailor what you present based on your audience by highlighting and focusing on the issues that relate to that specific person’s area of interest. You can start the conversation with issues or with the cloud. It depends on which one you think will better resonate with the person you are talking to.
  • Next Steps:
    • Even when you have everything ready for the buy-in, some people may be more open to suggestions (like Grant) and others will be less open or will have their own and potentially competing suggestions (like Micky). There are no guarantees.

Chapter 10 : Exec Review

  • It is important to have executive buy-in, otherwise your implementation of Critical Chain could be blocked or hampered.
  • Once you have single project Critical Chain implemented, the next step to consider is to look at Critical Chain multi-project to help manage multiple parallel projects effectively.

Chapter Questions

Chapter 1 : Introductions

LivingTV :
1.
What happened to LivingTV?
 
Tim and Randal Reconnect:
1.
What is Critical Chain useful for?
 
2.
What is TOC useful for?
 

Chapter 2 : High-Level Critical Chain Overview

What Is TOC and Critical Chain:
1.
What is Critical Chain?
 
2.
What is TOC?
 
Critical Chain Issues, Benefits, and Sample Results:
1.
What are some of the common project-management issues Critical Chain can help address?
 
2.
What are some of the Critical Chain benefits?
 
Key Parts of Critical Chain:
1.
What are some of the key Critical Chain components that help us get results?
 
Project Buffers:
1.
What do project buffers do?
 
2.
What are some of the issues that can cause project variability?
 
Multi-Tasking:
1.
What does reducing bad multi-tasking give you?
 
2.
Is all multi-tasking bad?
 
Building Schedules:
1.
What does building schedules back-to-front give you?
 
Organizational Analysis:
1.
What is the benefit of an organizational analysis?
 
Multiple Methodologies:
1.
What can influence the success of implementing a new project-management process even if it is a proven process?
 
2.
Can you mix other project-management methodologies with Critical Chain?
 
CRT and FRT:
1.
What does Tim’s CRT/FRT flowcharts help with?
 
2.
Is this something that should be shared with everyone?
 

Chapter 3 : Factors for Success

Introductions:
1.
What was Gary’s feeling on how good the Critical Chain methodology was?
 
2.
What was Tim’s thinking on why Gary did not get very good results?
 
Key Characteristics of Successful Implementations :
1.
Which areas are important for successful implementations? What is the benefit of each area?
 
2.
If your company is already using Critical Chain, how well do you address the above areas for successful implementations?
 
Environmental Factors:
1.
What four organizational issues can be important for successful implementations? For extra credit, explain why.
 
2.
What other areas beyond this list do you see as critical for a successful implementation or a potential major issue that could de-rail an implementation?
 
3.
If your company is already using Critical Chain, how well do you address the above organizational issues? Are there other issues that are a concern?
 

Chapter 4 : How Does the Critical Chain Solution Work

Key Critical Chain Benefits:
1.
What are the key Critical Chain benefits?
 
Project and Feeding Buffers, Padding Dates:
1.
What does it mean to pad dates? Why can it be problematic?
 
2.
What is the management and engineering poker game over?
 
Project and Feeding Buffers, Project Buffers:
1.
What is the value of a project buffer? How is it different than management adding padding (additional time) to the team’s deadline?
 
2.
What are some of the behaviors that Critical Chain tries to implement to improve project performance? Briefly describe them.
 
Project and Feeding Buffers, Feeding Buffers:
1.
What is the value of feeding buffers?
 
Project and Feeding Buffers, Safety Time:
1.
What is safety time?
 
Project and Feeding Buffers, Managing Project Variability:
1.
What does Critical Chain try to do in regard to variability? How?
 
Reducing Bad Multi-Tasking:
1.
What does bad multi-tasking do to your deadlines, resource capacity, and responsiveness?
 
Defining the Project Goal and Building Schedules Back-to-Front:
1.
What is the first step in building a schedule back-to-front?
 
2.
What does the phrase in order to (previous task) we must (successive task) first help you with?
 
3.
What does in order to (goal) we must (and list out the key tasks in the schedule) allow you to do?
 
4.
Overall, how does building the schedule back-to-front help you?
 
Organizational Analysis:
1.
How does Critical Chain and the organizational analysis work together to provide a more complete solution?
 
2.
How does the organizational analysis help?
 

Chapter 5 : Championing Ideas

LivingTV Interactive’s Dilemma:
1.
What was LivingTV’s dilemma? What choice was it struggling with?
 
2.
Why was LivingTV stuck?
 
LivingTV Interactive’s Conflict Cloud:
1.
What is the common goal that both sides share?
 
2.
What are the wants of each side?
 
3.
What are the needs driving the wants of each side?
 
Looking for Possible Resolutions:
1.
Of the AB,BD,AC,CD’, DD’ connections, which three connections in the cloud does Tim try to challenge? Why those three specifically?
 
Spark of an Idea:
1.
What link (AB, AC, BD, CD’, DD’ ) did Tim challenge?
 
2.
What assumption did he identify that he was able to challenge?
 
3.
How did breaking this assumption create a win-win solution for the company?
 
Initial Manager Meeting:
1.
What was Tim trying to prevent by meeting with each of the directors before the Exec review?
 
Lobbying in Preparation for the Exec Review:
1.
What did John, Mike, Bill, and Jim like about the pre-show concept?
 
2.
What were John, Mike, Bill, and Jim’s reservations about the pre-show concept?
 
3.
How did their responses relate to each of their respective departments?
 
4.
When pitching an idea, how would your approach change based on your audience?
 
The Exec Review:
1.
How did Tim and Lori’s work help in the Exec review?
 

Chapter 6 : Single Project Implementation Steps

Phoenix Setup :
1.
What are two ways to implement Critical Chain into an organization? Which one is more ideal than the other?
 
2.
Is it possible to intercept a project that is already in flight with Critical Chain?
 
3.
To really make a culture change in an organization, what three things do you need?
 
Phoenix Network Build:
1.
As part of the network build, does all of the team need to know the Critical Chain concepts?
 
2.
What defines the end of the project?
 
3.
What phrasing can you use when building out the schedule and checking dependencies?
 
4.
What is BORA and what is it used for?
 
5.
What are some of the issues that Tim, Gary, and Jeremy ran into when building out the Phoenix schedule?
 
Phoenix Execution:
1.
How often should the team update the schedule?
 
2.
What does the fever chart measure?
 
3.
What do the different colors of the fever chart mean?
 
4.
How can you recover time?
 
5.
What are some of the key behaviors you want during project execution? See Chapters 2 and 4 for more details.
 
Phoenix Post-Mortem Plan:
1.
What is POOGI and what is it for?
 
Micky’s Urgent Requests:
1.
What is the value of a change control process?
 
2.
If you know you will always have changes at key points in the schedule, what are some of the possible options?
 

Chapter 7 : Ambitious Targets

Background and QA Issues:
1.
What is the challenge faced by the QA team?
 
Define Your Goal:
1.
What criteria makes up a clear goal?
 
List Out Clear Issues and Their Impact:
1.
What issues are impacting QA?
 
Define Intermediate Objects (IOs):
1.
Who should be first to make suggestions to address an issue raised? Why?
 
2.
What are “flying pig” suggestions and why are they useful?
 
3.
At the end, Tim checks the suggestions that Nir and Anthony came up with against the goal. Why?
 
Sequence the Intermediate Objectives (IOs):
1.
What three things is Tim looking for from each suggestion?
 
2.
What does Ambitious Targets allow us to do over a task oriented schedule?
 
3.
What are the high-level steps in building an ambitious target?
 

Chapter 8 : Individual Buy-In

Meeting with Sales and Marketing:
1.
What does Tim learn in talking with Ashley?
 
Meeting with Human Resources:
1.
What does Tim learn in talking with Herb?
 
Randal and Tim Prep for the Meeting with Grant:
1.
What are the six layers of resistance used for?
 
2.
What are the six layers of resistance?
 
3.
What TOC tools are used for the first four layers?
 
4.
Why is it bad to show the CRT/FRT and use TOC terminology when trying to get buy-in from someone not familiar with TOC?
 
5.
Why is it important to blame the system?
 
6.
Why bother with the organizational analysis, CRT, FRT, and getting all of the execs’ to buy-in? Wouldn’t it just be simpler to build the Critical Chain schedules, add the buffers, and implement it in engineering without the rest of the organization’s involvement?
 
7.
Why is it so important to close the deal?
 
Meeting with Grant:
1.
What major stages does Tim go through in talking with Grant?
 
2.
What areas does Tim go through when he walks through the vision (Layer 2) with Grant?
 
3.
What does Tim learn in talking to Grant?
 

Chapter 9 : Almost

Randal and Tim Prep :
1.
What does Tim choose to focus on for his meeting with Micky compared to his meeting with Grant?
 
Tim Meets with Micky:
1.
What three steps does Tim go through when presenting to Micky?
 
2.
Would you have done anything different in meeting with Micky?
 
Next Steps:
1.
What are some of the benefits Randal and Gary are seeing from implementing Critical Chain on the Phoenix project?
 

Chapter 10 : Exec Meeting

Gary and Randal Present:
  • What are the pros and cons of Gary and Randal’s Critical Chain proposal?
  • Did Grant follow through on his commitment to help Gary and Randal in the Exec meeting (Chapter 8 discussion)? If so, how?
Micky Presents:
  • What are the pros and cons of Micky’s outsourcing solution?
Epilog:
  • Who won at the board meeting? Micky? Gary and Randal?
  • What does Tim want to implement next and why?

Basic Answers to Chapter Questions

Chapter 1 : Introductions

LivingTV :
1.
What happened to LivingTV?
a.
They could not develop the market fast enough. They could not get the new technology out soon enough. They were unable to grow the revenues as quickly as they had expanded the company and counter the resulting growth in expenses.
 
 
Tim and Randal Reconnect:
1.
What is Critical Chain useful for?
a.
To help deliver projects faster and more reliably.
 
 
2.
What is TOC useful for?
a.
It is a great set of general problem-solving tools that can be used to look at an organization as a whole, identify areas to focus on, and drive overall improvements.
 
b.
It can be used help focus teams on any improvement effort from Critical Chain, Scrum, Agile, new technology deployments, and so on.
 
 

Chapter 2 : High-Level Critical Chain Overview

What Is TOC and Critical Chain :
1.
What is Critical Chain?
a.
Critical Chain is a Theory of Constraints solution that addresses the common problems found in project management so you can better plan, manage, and be more successful with projects.
 
 
2.
What is TOC?
a.
The Theory of Constraints (TOC for short) is a general problem-solving model that can be applied to a variety of environments, but it has one fundamental concept. It focuses on identifying the one constraint that is limiting the system overall. So if you focus improvement efforts on this one area, the whole system will benefit and the bottom line of the organization will improve.
 
 
Critical Chain Issues, Benefits, and Sample Results:
1.
What are some of the common project-management issues Critical Chain can help address?
a.
Your projects miss critical deadlines and market opportunities.
 
b.
You cut too many key features to make deadlines.
 
c.
Your products are not competitive enough (due to slow project turnaround, missing deadlines, cutting key features, etc.).
 
d.
There is too much resource burn-out and turnover.
 
e.
You go over budget (due to project overruns).
 
f.
There are internal projects fights over shared resources.
 
 
What are some of the Critical Chain benefits?
a.
On-time delivery of products significantly improves.
 
b.
You are able to complete projects much faster.
 
c.
Hidden or misused resource capacity is surfaced.
 
d.
Your company and products are more competitive.
 
e.
Your company is more profitable.
 
Key Parts of Critical Chain:
1.
What are some of the key Critical Chain components that help you get results?
  • Project buffers to better manage task variability [frt 1]
  • Reducing bad multi-tasking to find hidden and misused resource capacity [frt 1]
  • Building schedules (back-to-front) and challenging assumptions [frt 1]
  • Organizational analysis (TOC TP) to better understand the overall project environment (creating the CRT and FRT)
 
Project Buffers :
1.
What do project buffers do?
a.
Help to better manage the variability in all projects.
 
 
2.
What are some of the issues that can cause project variability?
a.
There is more work involved than originally expected, additional scope and requirements are added, resources are not available, tasks take longer than expected, and project disasters happen that might sink a project.
 
 
Multi-Tasking:
1.
What does reducing bad multi-tasking give you?
a.
It provides clear priorities, focuses resources on key projects versus spreading them out, and encourages quick hand-offs.
 
 
2.
Is all multi-tasking bad?
a.
No, if you are working on one task and get blocked, working on a second task is fine. If you are juggling multiple tasks and going back and forth between them is slowing you down, then it is bad.
 
 
Building Schedules:
1.
What does building schedules back-to-front give you?
a.
A better way to call out true dependencies that can also be creatively challenged.
 
 
Organizational Analysis :
1.
What is the benefit of an organizational analysis?
a.
It provides a way to do a root cause analysis of your organizations issues. From there, you can see which issues the Critical Chain general solution can help you address. But as important, you can also see what other areas you will need to work on. This enables you to develop a complete and overall solution that will significantly improve your organization.
 
 
Multiple Methodologies :
1.
What can influence the success of implementing a new project-management process even if it is a proven process?
a.
How well the culture supports and adopts the solution
 
b.
How well the process addresses the organization’s problems
 
 
2.
Can you mix other project-management methodologies with Critical Chain?
a.
You can certainly mix project-management methodologies, but you need to have a solid grounding in the methodologies you are trying to mix. It is really important to first focus on getting your Critical Chain experience then you can look at adding other methods into it.
 
 
CRT and FRT:
1.
What does Tim’s CRT/FRT flowcharts help with?
a.
Tim’s chart helps visually map out several of the key components and connections between them for both the current situation as well as the desired situation.
 
 
2.
Is this something that should be shared with everyone?
a.
Tim’s charts can be shared with some key people, but in general they are often too detailed and technical to share with everyone. In these cases you may want to leverage the information from the flowcharts for discussions but not share them directly.
 
 

Chapter 3 : Factors for Success

Introductions:
1.
What was Gary’s feeling on how good the Critical Chain methodology was?
a.
The methodology did not seem to work well when they had tried to implement it on their own.
 
 
2.
What was Tim’s thinking on why Gary did not get very good results?
a.
No one was certified in Critical Chain and had no one had prior experience implementing Critical Chain.
 
 
Key Characteristics of Successful Implementations :
1.
What areas are important for successful implementations? What is the benefit of each area?
a.
A Critical Chain implementation expert who really understands the mechanics of the Critical Chain solution, how to use it correctly to help organizations increase throughput, and how to successfully implement it in an organization.
 
b.
Someone who has Critical Chain software tool experience.
 
c.
For complicated and political environments, I personally like to see someone who has a Theory of Constraints Thinking Process background who can do an organizational analysis.
 
d.
The organization has a compelling need and desire to change.
 
e.
Setting up the correct metrics.
 
 
2.
If your company is already using Critical Chain, how well do you address the above areas for successful implementations?
a.
Optional student exercise. Answers vary.
 
 
Environmental Factors :
1.
What four organizational issues can be important for successful implementations?
a.
Does the organization’s project team take ownership of the Critical Chain solution?
 
b.
Is senior management brought into the solution?
 
c.
How complex is your project environment?
 
d.
Existence of poor project-management practices.
 
 
2.
What other areas beyond this list do you see as critical for a successful implementation or a potential major issue that could de-rail an implementation?
a.
Optional student exercise. Items can include how well a team understands its customers, how well they know the market, how well can they define the product’s requirements, etc.
 
 
3.
If your company is already using Critical Chain, how well do you address the above organizational issues? Are there other issues that are a concern?
a.
Optional student exercise. Answers vary.
 
 

Chapter 4 : How Does the Critical Chain Solution Work

Key Critical Chain Benefits :
1.
What are the key Critical Chain benefits?
a.
Project and feeding buffers to better manage variability
 
b.
Reducing bad multi-tasking to find hidden or misused resource capacity
 
c.
Building schedules back-to-front and challenging assumptions
 
d.
Organizational Analysis (TOC Thinking Process) to better understand the environment
 
 
Project and Feeding Buffers , Padding Dates :
1.
What does it mean to pad dates? Why can it be problematic?
a.
Padding dates is the practice of adding additional time on top of an engineering deadline. It can be problematic since it can extend the overall project’s length and if it is too long this time can get cut by management.
 
 
2.
What is the management and engineering poker game over?
a.
How much time engineers can get management to add to the schedule to ensure features and quality versus how much time managers can cut from the engineers’ estimates to manage costs and hit key market windows.
 
 
Project and Feeding Buffers, Project Buffers :
1.
What is the value of a project buffer? How is it different than management adding padding (additional time) to the team’s deadline?
a.
It provides strategic use of safety time to more effectively protect the overall project’s deadline. In doing this, it can help shorten the overall project duration versus padding that just adds additional time.
 
b.
The project buffer consumption can also be used to trigger planning and response plans if the project starts encountering too many delays.
 
 
2.
What are some of the behaviors Critical Chain tries to implement to improve project performance? Briefly describe them.
a.
Roadrunner refers to the fact that you want resources to start working on a task as soon as it is assigned to them. Relay race is that as soon as a task is finished you want them to hand off to the next resource so they can start right away. Bad multi-tasking is when resources work on several tasks at once. Student syndrome is the temptation to put work off to the last minute.
 
 
Project and Feeding Buffers, Feeding Buffers
1.
What is the value of feeding buffers?
a.
To minimize overall project delays from feeding task issues and delays.
 
 
Project and Feeding Buffers, Safety Time:
1.
What is safety time?
a.
The extra time (padding) engineers add to a task to protect against delays and paranoia.
 
 
Project and Feeding Buffers, Managing Project Variability:
1.
What does Critical Chain try to do in regard to variability? How?
a.
Critical Chain sets up ways to manage the variability of a project so companies are less impacted by delays. The feeding buffers minimize delays from feeding paths. Moving safety time out of the tasks and into a project buffer allows you to better protect the project’s deadline from delays without adding time. The project behaviors are to help you move as quickly forward in executing the project as you can.
 
 
Reducing Bad Multi-Tasking :
1.
What does bad multi-tasking do to your deadlines, resource capacity, and responsiveness?
a.
Bad multi-tasking causes deadlines to get stretched out, resource capacity to be wasted, and your responsiveness to be wasted.
 
 
Defining the Project Goal and Building Schedules Back-to-Front :
1.
What is the first step in building a schedule back-to-front ?
a.
The first step is to be sure that you have a clearly defined project goal.
 
 
2.
What does the phrase in order to (previous task) we must (successive task) first help you with?
a.
It allows you to make sure you have captured all of the necessary tasks and dependencies.
 
 
3.
What does in order to (goal) we must (and list out the key tasks in the schedule) allow you to do?
a.
Make sure that you have captured all of the key requirements in the schedule.
 
 
4.
Overall, how does building the schedule back-to-front help you?
a.
It allows you to make sure you capture key dependencies and tasks that might be overlooked by just listing requirements, it helps you make sure you clearly define the project goal, and it helps you make sure the key tasks you are doing are sufficient to reach that goal.
 
 
Organizational Analysis :
1.
How does Critical Chain and the organizational analysis work together to provide a more complete solution?
a.
Critical Chain helps address the common project-management issues. The organizational analysis helps you identify organizational issues that could significantly limit the results of your Critical Chain implementation as well as helps you see what needs to help improve the organization as a whole.
 
 
2.
How does the organizational analysis help?
a.
The organizational analysis helps in getting the organizational buy-in on what problems need to be addressed, how, and why Critical Chain and some other key improvements are necessary.
 
 

Chapter 5 : Championing Ideas

LivingTV Interactive ’s Dilemma:
1.
What was LivingTV’s dilemma? What choice is it struggling with?
a.
In order to expand, LivingTV needed to decide if it wanted to first expand into a nationwide service or expand the number of programs and games it offered.
 
 
2.
Why was LivingTV stuck?
a.
LivingTV was stuck because it only had the funding to either go nationwide or expand programming; it could not do both.
 
 
LivingTV Interactive’s Conflict Cloud :
1.
What is the common goal that both sides share?
a.
Everyone wanted LivingTV to grow and be successful.
 
 
2.
What are the wants of each side?
a.
One side wanted LivingTV to go nationwide.
 
b.
One side wanted LivingTV to expand its programming.
 
 
3.
What are the needs driving the wants of each side?
a.
One side needed to have a market large enough to attract advertising revenue.
 
b.
One side needed to have enough programming to develop subscriber revenue.
 
 
Looking for Possible Resolutions :
1.
Of the AB,BD,AC,CD’, DD’ connections, which three connections in the cloud does Tim try to challenge? Why those three specifically?
a.
DD’ to challenge the assumptions behind the conflict itself.
 
b.
BD and CD’ to challenge the assumptions between each side’s need and each side’s want.
 
 
Spark of an Idea:
1.
What link (AB, AC, BD, CD’, DD’ ) did Tim challenge?
a.
CD’
 
 
2.
What assumption did he identify that he was able to challenge?
a.
There was no way to get additional programming without paying additional royalties.
 
 
3.
How did breaking this assumption create a win-win solution for the company?
a.
The “go deep” subscriber/programming side benefited since there were now able to increase the number of programs supported without significant expense by not having to pay royalties to get pre-distribution access to shows.
 
b.
The side that wanted to “go broad” benefited since they will now have the money and resources to expand.
 
c.
With the pre-show, both sides were able to protect and move forward with their needs.
 
 
Initial Manager Meeting :
1.
What was Tim trying to prevent by meeting each of the directors before the Exec review?
a.
His idea failing by getting stalled by the company’s approval process. In addition, Tim could educate each decision maker about the idea as well as have a chance to address their concerns in advance.
 
 
Lobbying in Preparation for the Exec Review :
1.
What did John, Mike, Bill, and Jim like about the pre-show concept?
a.
John liked how it supported his goals to expand the number of shows LivingTV supported, the idea’s ability to support any show, and the concept gave his team a full week to develop each week’s script.
 
b.
Mike liked that the idea was not technically challenging to implement.
 
c.
Jim liked that it gave the opportunity to produce any and as many shows as LivingTV wanted without the high cost of royalties.
 
 
2.
What were John, Mike, Bill, and Jim’s reservations about the pre-show concept?
a.
Everyone had concerns around the legality of the developing LivingTV content based on TV shows that have been broadcast.
 
b.
Mike wanted Tim to review the idea with Peter in case there were additional technical concerns.
 
c.
Jim had concerns around legal and maintaining the company’s relationship with broadcasters.
 
 
3.
How did their responses relate to each of their respective departments?
a.
John focused on programming operations questions, Mike on engineering and technical questions, and Jim on executive and strategic relationship questions.
 
 
4.
When pitching an idea, how would your approach change based on your audience?
a.
Everyone needs a general idea of the solution, but each person’s interest and questions often focus on where they are in the organization (i.e., John in operations, Mike in technical, and Jim in strategic).
 
 
The Exec Review :
1.
How did Tim and Lori’s work help in the Exec review?
a.
At the start of the meeting, everyone already understood the concept and Tim and Lori had been able to understand and help address the majority of concerns. This streamlined the meeting.
 
 

Chapter 6 : Single Project Implementation Steps

Phoenix Setup:
1.
What are two ways to implement Critical Chain into an organization? Which one is more ideal than the other?
  • When looking at moving an organization onto Critical Chain ideally, you should try to move the whole organization. If time is an issue, then you can look at staggering the implementation and pick one or two high-impact projects to focus on. They need to have a bottom-line impact as well and cannot be side projects since the effort needed and results created would not be taken seriously.
 
2.
Is it possible to intercept a project that is already in flight with Critical Chain?
  • If necessary it is possible to intercept a project already in process and simply build the new Critical Chain schedule from where the project is currently at to the end.
 
3.
To really make a culture change in an organization, what three things do you need?
  • Top management buy-in and agreement to lead the charge.
  • Determination of key measurement changes that will incentivize the desired behaviors of the new culture.
  • Education for all involved, including the new measurements. (Bibliography 1)
 
Phoenix Network Build:
1.
As part of the network build, does all of the team need to know the Critical Chain concepts?
  • As part of the network build, it is important that the managers and the team learns the key Critical Chain concepts [Chapters 2 and 4 items]
 
2.
What defines the end of the project?
  • You want to be sure to build the project to throughput (where you generate income).
 
3.
What phrasing can you use when building out the schedule and checking dependencies?
  • You look at the project’s goal and build backward using the phrasing in order to.. we must.. and add in any dependencies.
 
4.
What is BORA and what is it used for?
  • When you need to compress and tighten a schedule up, you can look at BORA: B reak a link, O verlap tasks, R educe scope or duration, or A dd a resource.
 
5.
What are some of the issues Tim, Gary, and Jeremy run into when building out the Phoenix schedule?
  • Jeremy wants to be sure Gary has signed off on replanning the Phoenix schedule using a new methodology.
  • They need to build the schedule to throughput, so when the customer actually approves the features and revenues are generated.
  • Critical Chain is staggering the tasks based on resource availability.
  • Tasks are assigned to the manager’s name as opposed to the resource’s name.
  • Jeremy added padding back into some of the focus times for some of the tasks.
  • The schedule is too long and the team needs to use BORA to tighten it up.
 
Phoenix Execution:
1.
How often should the team update the schedule?
a.
The team should have regular, typically weekly, schedule updates.
 
 
2.
What does the fever chart measure?
a.
The fever chart measures how much buffer you have consumed compared to how much of the project you have completed.
 
 
3.
What do the different colors of the fever chart mean?
a.
Green means you are on track, yellow means you are falling behind and need to look at ways to recover, and red means that you are putting the project deadline at risk and need to act to add time back into the buffer.
 
 
4.
How can you recover time?
a.
To recover time, review BORA: B reak a link, O verlap tasks, R educe scope or duration, or A dd a resource.
 
 
5.
What are some of the key behaviors that you want during project execution? See Chapters 2 and 4 for more details.
a.
Roadrunner: You encourage people to work as quickly as they can.
 
b.
Relay race: You encourage people to hand off work to the next resource (dependency) as quickly as possible.
 
c.
Reduce bad multi-tasking: You want to avoid any multi-tasking that stretches out work and delays hand-offs.
 
d.
Do not beat up resources for missing focused times; they are aggressive by design so you should expect that several will be missed. You’ll want to manage the overall project buffer and overall deadline, not micro-manage resources.
 
 
Phoenix Post-Mortem Plan:
1.
What is POOGI and what is it for?
  • POOGI stands for the Process Of OnGoing Improvement. Once you have set up a new process, you need to maintain and continue to improve upon it.
 
Micky’s Urgent Requests:
1.
What is the value of a change control process?
  • Even when you set up Critical Chain (or any system) it is not foolproof. If you let too much work into the system, you will flood it. So you must have good discipline and manage a good change control process.
 
2.
If you know you will always have changes at key points in the schedule, what are some of the possible options?
  • Look at trying to minimize these changes (i.e. change control) as well as proactively reserve capacity for these changes.
 

Chapter 7 : Ambitious Targets

Background and QA Issues :
1.
What is the challenge faced by the QA team?
a.
The engineering schedule ran late and the overall project deadline held so the QA timeframe was severely compressed with the expectation that the team would hold to the original quality and testing guidelines.
 
 
Define Your Goal :
1.
What criteria makes up a clear goal?
a.
It’s clear, measurable, and has specific criteria and dates.
 
 
List Out Clear Issues and Their Impact:
1.
What issues are impacting QA?
a.
Software is often late, software’s delays reduces the time left for QA, software going into test is of poor quality, QA is blamed for software’s low quality, and software engineers change requirements without informing QA.
 
 
Define Intermediate Objects (IOs) :
1.
Who should be first to make suggestions to address an issue raised? Why?
a.
The person who first raised the issue should have the first opportunity to make a suggestion. Afterward, others can add their own suggestions as it makes sense.
 
 
2.
What are “flying pig” suggestions and why are they useful?
a.
Flying pig suggestions are “way out there” suggestions that initially seem impossible, such as we can breathe under water, we can land on the moon, we all become rich, etc. They are useful in that they give you a direction as long as you can eventually come back and convert the flying pig idea back into something realistic and implementable.
 
 
3.
At the end, Tim checks the suggestions that Nir and Anthony came up with against the goal. Why?
a.
Tim is doing a quick check to make sure that there were not any other major issues that would prevent the team from reaching the goal that had not been discussed.
 
 
Sequence the Intermediate Objectives (IOs) :
1.
What three things is Tim looking for from each suggestion?
a.
Sequencing, owner, timeline.
i.
Sequencing: Can this be done in parallel with other tasks or is it dependent on another task finishing first?
 
ii.
Owner: Who owns completing this task?
 
iii.
Timeline: When do you expect them to finish the task? Will you have several status checkpoints to review progress?
 
 
 
2.
What do ambitious targets allow you to do over a task-oriented schedule?
a.
Focus on putting together an overall plan that includes not only the traditional tasks needed to complete a schedule, but also a plan that captures the issues you are concerned about and your plans on how to overcome these concerns.
 
 
3.
What are the high-level steps in building an Ambitious Target?
a.
Develop a goal
 
b.
Identify issues
 
c.
Develop suggestions
 
d.
Sequence the suggestions
 
 

Chapter 8 : Individual Buy-In

Meeting with Sales and Marketing :
1.
What does Tim learn in talking with Ashley?
a.
Missed dates and features have caused the company to incur penalties, get less desirable contract terms, and lose future contracts.
 
b.
The company is missing revenue targets.
 
c.
Several of the execs have lost trust in engineering’s ability to deliver.
 
d.
Micky has once looked into adding additional product lines [crt 30].
 
e.
Competitors are catching up and getting contracts the company once had.
 
 
Meeting with Human Resources :
1.
What does Tim learn in talking with Herb?
a.
The company has lost several good people due to tight deadlines, priorities switching, and unrealistic schedules.
 
b.
Competitors are ramping up and picking up some of the people who left and that in turn has lead to poaching of additional employees.
 
c.
Micky had asked the execs to look at a potential 10% resource cut across the company, but is unlikely to follow through on it since it would have long-term consequences.
 
 
Randal and Tim Prep for the Meeting with Grant :
1.
What are the six layers of resistance used for?
a.
To help get buy-in in an effective and systematic way, help address people’s concerns, and help them understand and ideally agree to your proposal.
 
 
2.
What are the six layers of resistance?
a.
Layer 1: Lack of consensus on the problem.
 
b.
Layer 2: People do not agree on the direction of the solution.
 
c.
Layer 3: Arguing the proposed solution cannot yield the desired outcome.
 
d.
Layer 4: Yes, but. Concerns about potential negative side-effects from proposed solution.
 
e.
Layer 5: Obstacles that stand in the way of implementing solution into the environment.
 
f.
Layer 6: Raising doubts, wait and see, unverbalized fears.
 
 
3.
What TOC tools are used for the first four layers?
a.
Layer 1: Lack of consensus on the problem. CRT tool.
 
b.
Layer 2: People do not agree on the direction of the solution. Cloud and Injection tool.
 
c.
Layer 3: Arguing the proposed solution cannot yield the desired outcome. FRT tool.
 
d.
Layer 4: Yes, but. Concerns about potential side-effects from proposed solution. Negative Branch (NBR) tool.
 
 
4.
Why is it bad to show the CRT/ FRT and use TOC terminology when trying to get buy-in from someone not familiar with TOC?
a.
When you start showing CRTs and FRTs and start using TOC lingo on people who are not familiar with TOC, instead of them being amazed by your insights, they in fact will be turned off by the complexity and your arrogance in assuming they would understand something so new and different instantly.
 
 
5.
Why is it important to blame the system?
a.
You want to focus attention on the system, not go around finger pointing and blaming people.
 
b.
It is not that any one person or group is trying to undermine the company. The system, the way you operate, is holding you back. The CRT outlines this system and how it is interconnected. Companies need to focus their efforts on understanding, blaming, and changing the system.
 
 
6.
Why bother with the organizational analysis, CRT, FRT, and getting all of the execs’ to buy-in? Wouldn’t it just be simpler to build the Critical Chain schedules, add the buffers, and implement it in engineering without the rest of the organization’s involvement?
a.
It could work briefly. But in the long run it would likely fall apart. As noted in the factors for success [Chapter 3 ], the organizational buy-in is needed. If management is not brought in and understand the project buffers they will just cut them and that will undermine Critical Chain’s success. With the cut project buffers, you are more likely to miss deadlines and in turn management will push even more to switch to some other methodology du jour. The same is true with the buffer management and project behaviors. Without management support, they will not work and in turn the Critical Chain solution will not work.
 
 
7.
Why is it so important to close the deal?
a.
You are holding a meeting for a reason. If you present everything, but do not close it with a confirmed call to action, then people are informed but nothing changes. You need the call to action to get ensure that you get some level of commitment and cause change.
 
 
Meeting with Grant :
1.
What major stages does Tim go through in talking with Grant?
a.
Quantify the issues (Layer 1)
 
b.
Explain the core conflict and key injection (Layer 2)
 
c.
Walk through the vision/FRT (Layer 3)
 
d.
Close the deal
 
 
2.
What areas does Tim go through when he walks through the vision (Layer 2) with Grant?
a.
Throughput
 
b.
Project buffers and behaviors
 
c.
Organizational analysis
 
d.
Summarize the vision
 
 
3.
What does Tim learn in talking to Grant?
a.
About 40% of the projects have some delays.
 
b.
He and Gary have to juggle project priorities between proprietary features and infrastructure versus general features and infrastructure.
 
c.
Micky states the revenues from contracts are down 30%.
 
 

Chapter 9 : Almost

Randal and Tim Prep :
1.
What does Tim choose to focus on for his meeting with Micky compared to his meeting with Grant?
a.
Tim is catering to the audience. Grant lives a lot of the engineering issues, so it made sense to start the discussion there. Micky is the CEO and sees and lives the company’s struggles so starting with the cloud of the company’s conflict should work well for him.
 
 
Tim Meets with Micky :
1.
What three steps does Tim go through when presenting to Micky?
a.
Show the cloud
 
b.
Blame the system and highlight key issues from the CRT
 
c.
Introduce the key injection and vision
 
 
2.
Would you have done anything different in meeting with Micky?
a.
Optional student exercise. Answers vary.
 
 
Next Steps:
1.
What are some of the benefits Randal and Gary are seeing from implementing Critical Chain on the Phoenix project?
a.
They hit a number of issues and consumed some of the project buffer, but are still on track to hit their deliverables.
 
b.
The development team feels more confident that the schedule is realistic and they actually have a chance to succeed.
 
c.
Randal has been working with Gary to talk with the customers to better enable a clean feature check-out. The customers appreciate the attention and Gary feels it will help them get payments a month early if the schedules continue to hold up.
 
 

Chapter 10 : Exec Meeting

Gary and Randal Present:
1.
What are the pros and cons of Gary and Randal’s Critical Chain proposal?
 
Pros:
  • Phoenix is on track to generate better revenues than with past projects (no excessive overtime, no customer penalties for incomplete features).
  • Phoenix is on track to generate revenues earlier than with past projects.
  • The techniques used can be carried over to other projects and, in turn, help them bring in better revenues sooner.
  • Keeping development in internal will protect their intellectual property.
Cons:
  • Engineering has a long history of missing deadlines.
  • Engineering has a long history of promising to improve with limited success.
  • Engineering needs time to fully implement this new process across the company’s various projects.
2.
Did Grant follow through on his commitment to help Gary and Randal in the Exec meeting (Chapter 8 discussion)? If so, how?
  • Yes, Grant followed through on his commitment. Grant shared his belief that Critical Chain would help the organization move forward and would help them turn things around.
 
Micky Presents:
  • What are the pros and cons of Micky’s outsourcing solution?
Pros:
  • Development can be done at a fraction of the cost.
  • They can use freed up funds to aggressively market and expand product offerings.
  • Development can be done by a company with a history of delivering on time.
  • They can transition to the outsourcing company quickly (in theory).
  • They can add development capacity by expanding their contract.
Cons:
  • How quickly the outsourcing company can actually ramp up needs further investigation.
  • They are entrusting their intellectual property to an outside organization.
  • They lay off a significant number of their existing staff.
  • They assume the outsourcing company can innovate as well as the existing teams that have had years to ramp up.
  • They assume the outsourcing company will not significantly increase its fees.
Epilog:
1.
Who won at the board meeting? Micky? Gary and Randal?
  • The company won overall by getting a solution that would help it succeed. Gary and Randal were able to preserve the local development team based on the early success they were able to get using Critical Chain on the Phoenix project as well as set the development team up for continued success. Micky was able to cement his leadership role as the new co-CEO.
 
2.
What does Tim want to implement next and why?
  • After implementing single project Critical Chain to help each project do well, he wants to look at Critical Chain multi-project to help the organization manage multiple parallel projects effectively.
 

TOC Resources

To learn the latest information and more about TOC, TOC solutions including Critical Chain, and TOC conferences, results, and testimonials, consider the following:
  • The Goldratt Institute ( www.goldratt.com ); the birthplace of TOC
  • The Theory of Constraints International Certification Organization ( www.tocico.org ); TOC Training and Certification Organization
  • Googling your favorite topic

Bibliography

Chapter 2 : High-Level Critical Chain Overview

Chapter 4 : How Does the Critical Chain Solution Work?

  • Goldratt, Eliyahu M. Critical Chain, North River Press, 2002.
  • Wikipedia. “Critical Chain.” [Online]. Available at www.en.wikipedia.org/wiki/Critical_chain_project_management , December 23, 2014.
  • Avraham Y Goldratt Institute. “A White Paper: Theory of Constraints Project Management—A Brief Introduction to the Basics.” Available from AGI December 13, 2010.

Chapter 5 : Championing Ideas

Chapter 6 : Implementation Steps

  • Bibliography 1 interview with Suzan Bergland, January, 2016.
  • Bibliography 2 interview with Tina Merry, October, 2006.

Chapter 7 : Ambitious Targets

  • Avraham Y Goldratt Institute, “Management Skills Course: Ambitious Targets,” 1993.

Chapter 8 : Individual Buy-In

  • Interview with Suzan Bergland, January, 2016

Basic Answers to Chapter Questions

Chapter 2

Index
A
Ambitious targets
background and QA issues
key steps
questions
Avraham Goldratt Institute (AGI)
B
Bad multi-tasking
reduces
tasks and projects
Bibliography
Board room meeting
epilog
exec meeting
exec review
Gray approaches
Micky presentation
Randal presentaion
review
Building schedules
Building schedules back-to-front
C, D
Clear
definition
issues and impacts
Concise definition
Critical Chain
AGI
answers
benefits
building schedules back-to-front
CCPM benefits
common project management issues
components
Goldratt’s marketing group
high level mechanics
issues
managing variability
multiple project management methodologies
problem-solving model
ProChain
project and feeding buffers
bad multi-tasking
feeding buffer
highway analogy
padding dates
project buffers
project variability management
safety time
project buffers
aggressive task estimates
bad multi-tasking
building schedules (back to front)
focused time
manage variability
organizational analysis
safety time
project management issues
questions
realization
resources
results
TOC solution
velocity
web sites
wrapping up
Current Reality Tree (CRT)
LivingTV Interactive
cloud captures
core confilct
CRT diagram
meeting peoples
Phoenix project
E
Environmental factors
organizational issues
overview
Randal implementation
roles and responsibilities
solution and implementation
F
Feeding buffers
Future Reality Tree (FRT)
board room meeting
Critical Chain
Intermediate Objectives (IOs)
LivingTV Interactive
meeting peoples
Phoenix project
successful implementations
G
Gary
presentation
questions
Grant
approaches
core conflict and key injection
FRT
organizational analysis
project buffers and behaviors
synopsis
Throughput
issue
review
H
High-level implementation
Micky, requests
Phoenix
execution
network build
Post-Mortem plan
setup
questions
Human resources (HR)
I, J, K
Individual buy-in
approaches
key steps
layers
questions
Intermediate Objectives (IOs)
concatenation
definition
results
L
LivingTV Interactive
answers
assumptions
background
conflict cloud
Critical Chain
dilemma
direct conflict
exec review
history
idea
initial manager meeting
Peter meeting
questions
Randal reconnection
realtime ideas
resolutions
stuck
Tim and Randal
Tim reconnection
TOC
M
Measurable goal definition
Meeting peoples
CRT/FRT issues
Grant
See also(Grant)
human resources
layers
meeting preparation
Micky
cloud
CRT issues
injection and vision
steps
sales and marketing
TOC tools
Methodologies
Micky
cloud
CRT issues
injection and vision
presentation
requests
steps
N
Negative branch (NBR)
O
Organizational analysis
P, Q
Padding dates
Phoenix project
execution
Micky
network build
post-mortem plan
setup
ProChain
Project buffers
Project implementation
R
Randal
and Tim preparation
and Tim presentation
Micky
presentation
questions
Relay race
Roadrunner
S
Sales and marketing director
Student syndrome
Successful implementations
characteristics
Critical Chain Implementation expert
environmental factors
environmental issues
experience
factors
See also(Environmental factors)
organization needs
compelling reason
Randal and Gary
Tim
TOC thinking processes
questions
software tool experience
metrics
TOC TP thinking process background
T, U, V, W, X, Y, Z
Theory of Constraints Thinking Process (TOC TP)
Theory of Constraints (TOC)
key concepts
resources
..................Content has been hidden....................

You can't read the all page of ebook, please click here login for view all page.
Reset
18.221.156.50