THE PMP® EXAM CONTENT FROM THE EXECUTING THE PROJECT PERFORMANCE DOMAIN COVERED IN THIS CHAPTER INCLUDES THE FOLLOWING:
Executing is the third process group of the five project management process groups. The processes in this group are responsible for executing the work outlined in the project management plan, managing the project resources, and performing the work of the project. Within this process group, you will also see approved changes and actions implemented as well as re-planning and re-baselining as a result of implemented changes.
Executing also involves keeping the project in line with the original plan. The majority of the project budget and time will be spent in this process group, and the majority of conflicts will relate to the schedule. In addition, the product description will be finalized and contain more detail than it did in the Planning processes®” must be placed as shown here. Please do not adjust it through the editing process. AU"?>.
The Executing process group accounts for 30 percent of the questions on the Project Management Professional (PMP)® exam.
As mentioned previously, the Executing process group involves executing the project work. Naturally, this cannot be accomplished without first acquiring the resources needed to perform the project work. Obtaining resources occurs through the Acquire Resources process, which is part of the Project Resource Management Knowledge Area, and the Conduct Procurements process, which is a part of the Project Procurement Management Knowledge Area. The resource and procurement management plans play an important role in carrying out these processes because they outline how resources will be acquired, managed, and released throughout the project life cycle.
The Acquire Resources process involves acquiring and assigning resources, both internal and external, to the project. It is the project manager’s responsibility to ensure that human resources are available and skilled in the project activities to which they’re assigned. In addition to human resources, this process addresses acquiring physical resources, such as facilities, equipment, materials, supplies, and other physical resources needed to perform the work at hand. This process considers the following factors:
Figure 7.1 shows the inputs, tools and techniques, and outputs of the Acquire Resources process.
Know the following inputs for the Acquire Resources process:
Project Management Plan The project management plan is essential to this process. The following are utilized from within this plan:
The project management plan should detail how resources will be acquired.
Project Documents Several project documents inform this process and can include, but are not limited to, the following:
Enterprise Environmental Factors The enterprise environmental factors used in this process involve taking the following information into account before making assignments:
Organizational Process Assets The organizational process assets input refers to the standard processes, policies, procedures, and guidelines that the organization has in place. This includes policies around acquiring external resources. In particular, procurement practices should be taken into account.
Be familiar with the following tools and techniques for the Acquire Resources process:
Decision Making Decision-making techniques used in this process include, but are not limited to, multi-criteria decision analysis. Multi-criteria decision analysis involves the use of selection criteria to make decisions on whether potential project team members are a fit. Criteria are typically assigned a weight based on their level of importance, and candidates are then rated against the criteria. Some examples of criteria used are availability, experience, ability, and cost.
Interpersonal and Team Skills When working with shared resources, the use of interpersonal and team skills, specifically negotiation, is key. Project managers may use negotiation techniques when dealing with functional managers and other organizational department managers—and sometimes with a vendor to get some of their best people—for project resources and for the timing of those resources.
The following items are typically negotiated:
Pre-assignment Pre-assignment may take place when the project is put out for bid and specific team members or physical resources are promised as part of the proposal or when internal project team members are promised and assigned as a condition of the project. Pre-assignments are documented within the project charter.
Virtual Teams According to the PMBOK® Guide, virtual teams are defined as groups of people with a shared goal who fulfill their roles with little or no time spent meeting face-to-face. The use of virtual teams makes it possible to draw in resources that wouldn’t otherwise be available. It also reduces travel expenses by allowing teams to work from home. Virtual teams typically connect using technology tools, such as the Internet, email, and videoconferencing.
Communication becomes essential when functioning in a virtual structure. All team members should be made aware of the protocols for communicating in a virtual team environment, understand the expectations, and be clear on the decision-making processes.
Know the following eight outputs of the Acquire Resources process:
Physical Resource Assignments Physical resource assignments need to be documented, and the supplies, locations, material, and equipment should be recorded.
Project Team Assignments Project team assignments are based on the results of negotiating and determining elements such as the roles and responsibilities and reviewing recruitment practices. This output also results in a published project team directory, which lists the names of all project team members and stakeholders.
Resource Calendars Resource calendars show the team members’ availability and the times they are scheduled to work on the project. A composite resource calendar includes availability information for potential resources as well as their capabilities and skills.
Change Requests As a result of performing the Acquire Resources process, adjustments or preventative or corrective actions need to be documented in a change request. Change requests are then reviewed and disposed of through the Perform Integrated Change Control process.
Project Management Plan Updates As a result of performing the Acquire Resources process, updates will be made to the resource management plan and the cost baseline.
Project Documents Updates The Acquire Resources process will result in updates to the lessons learned register, resource breakdown structure, risk register, stakeholder register, project schedule, and resource requirements. There may also be other documents that will need to be updated depending upon the scope and nature of the project being performed.
Enterprise Environmental Factors Updates The resource availability within the organization and the amount of consumable resources used are elements of enterprise environmental factors that may be updated through this process.
Organizational Process Assets Updates At a minimum, documentation related to acquiring, assigning, and allocating resources may be updated through the Acquire Resources process.
In some cases, resources will need to be procured externally. The Conduct Procurements process is concerned with obtaining responses to bids and proposals from potential vendors, selecting a vendor, and awarding the contract. This process is used only when goods or services are obtained from outside of the project’s organization. After this process is conducted, sellers will have been selected, contracts awarded, and project documents updated to reflect the selected vendors.
Figure 7.2 shows the inputs, tools and techniques, and outputs of the Conduct Procurements process.
There are six inputs of the Conduct Procurements process that you should know:
Project Management Plan The project management plan elements used to guide the Conduct Procurement process may include, but are not limited to, the scope management plan, requirements management plan, communications management plan, risk management plan, procurement management plan, configuration management plan, and cost baseline.
Project Documents Project documents typically used as an input to this process include the lessons learned register, project schedule, requirements documentation, risk register, and stakeholder register.
Procurement Documentation The following procurement documents are typically utilized:
Seller Proposals Seller proposals are literally the proposals submitted by sellers in response to a procurement document package. These proposals will be evaluated as part of this process.
Enterprise Environmental Factors There are many enterprise environmental factors that could shape the Conduct Procurements process including, but not limited to, the following:
Organizational Process Assets Organizational process assets may contain information on sellers used, including a list of preferred sellers, organizational policies that influence seller selection, and relevant financial policies and procurements.
Know the following tools and techniques of the Conduct Procurements process:
Expert Judgment Expert judgment may include experts from all areas of the organization when evaluating proposals and selecting vendors.
Advertising Advertising lets potential vendors know that an RFP is available. It can be used as a way of expanding the pool of potential vendors, or it may be a requirement, such as in the case of government projects. Here are some examples of where advertising may appear:
Bidder Conferences Bidder conferences, also known as vendor conferences, prebid conferences, and contractor conferences, are meetings with prospective vendors or sellers that occur prior to the completion of their response proposal. Bidder conferences have the following characteristics:
Data Analysis There are several techniques that can be used to evaluate proposals. The types of goods and services you’re trying to procure will dictate how detailed your evaluation criteria are. Depending on the complexity of the procurements, you may use one or more of the following techniques to evaluate and rate sellers:
After utilizing the necessary techniques, compare each proposal against the criteria, and rate or score each proposal for its ability to meet or fulfill these criteria. This can serve as your first step in eliminating vendors that don’t match your criteria. The next step is to apply the tools and techniques of this process to further evaluate the remaining potential vendors.
Using a weighting system, you can assign numerical weights to evaluation criteria and then multiply them by the weights of each criteria factor to come up with total scores for each vendor. Screening systems and seller rating systems are also sometimes used.
Interpersonal and Team Skills The primary interpersonal and team skill used for this process is negotiation. In procurement negotiations, both parties come to an agreement regarding the contract terms. At a minimum, deal points that may need negotiation in a contract should include the following items:
Once agreement is reached and the negotiations are finished, the contract is signed by both buyer and seller and is executed.
The Conduct Procurements process contains the following six outputs:
Selected Sellers Selected sellers are vendors that have been chosen to provide the goods or services requested by the buyer.
Agreements A procurement agreement is a legally binding agreement between two or more parties, typically used to acquire goods or services. Agreements have several names:
The type of contract awarded depends on the product or services being procured and on the organizational policies.
A contract’s life cycle consists of four stages: requirement, requisition, solicitation, and award. In the requirement stage, the project and contract needs are established and requirements are defined within the statement of work (SOW). The requisition stage focuses on refining and confirming the project objectives and generating solicitation materials, such as the request for proposals (RFP), request for information (RFI), and request for quotations (RFQ). The solicitation stage is where vendors are asked to compete and respond to the solicitation materials. And last, the award stage is where the vendors are chosen and contracts awarded.
The contract should clearly address the following:
Change Requests Change requests may include changes to the project management plan and its subsidiary plans and components. These changes are submitted to the change control board for review.
Project Management Plan Updates The following elements of the project management plan may need to be updated as a result of this process:
Project Documents Updates The following documents may need to be updated as a result of this process:
Organizational Process Assets Updates The following organizational process assets may need to be updated as a result of this process:
Maximizing team performance involves leading, mentoring, training, and motivating team members. The project manager leads these efforts with the guidance of the documented resource management plan. The processes used to achieve maximum team performance include Develop Team and Manage Team, which are both a part of the Project Resource Management Knowledge Area.
To be successful, project managers will need to be familiar with several leadership theories, the stages of team development, motivational theories, and leadership styles. Being familiar with and understanding conflict resolution techniques and types of power are also important when managing teams.
The Develop Team process is concerned with creating a positive environment for team members; developing the team into an effective, functioning, coordinated group; and increasing the team’s competency levels. The proper development of the team is critical to a successful project. Since teams are made up of individuals, individual development becomes a critical factor to project success.
Figure 7.3 shows the inputs, tools and techniques, and outputs of the Develop Team process.
The Develop Team process includes the following inputs:
Project Management Plan The project management plan, and specifically the resource management plan, provides guidance on providing the project team members with rewards, feedback, additional training, and disciplinary actions.
Project Documents Project documents that serve as inputs to the Develop Team process include, but are not limited to, the lessons learned register, project schedule, resource calendars, project team assignments, and team charter.
Enterprise Environmental Factors The Develop Team process is informed by the following enterprise environmental factors (among others):
Organizational Process Assets Historical information and the lessons learned repository are the key organizational process assets that inform the Develop Team process.
Before we review the tools and techniques of the Develop Team process, it is helpful to understand some key concepts and theories about leadership, management, and motivation.
Project managers need to use the traits of both leaders and managers at different times during a project. Therefore, it’s important to understand the difference between the two.
Leaders display the following characteristics:
Managers display the following characteristics:
There are four particularly notable theories regarding leadership and management:
Theory X & Y Douglas McGregor defined two models of worker behavior, Theory X and Theory Y, that attempt to explain how different managers deal with their team members. Theory X managers believe the following statements to be true:
As a result, Theory X managers are like dictators and impose very rigid controls over their employees. They believe people are motivated only by punishment, money, or position.
Theory Y managers have the following characteristics:
Theory Y managers believe people are creative and committed to the project goals, that they like responsibility and seek it out, and that they are able to perform the functions of their positions with limited supervision.
Theory Z Theory Z was developed by William Ouchi. This theory is concerned with increasing employee loyalty to their organization and results in increased productivity. Theory Z has the following characteristics:
Theory Z develops employee loyalty through group decision making, which also results in a sense of being valued and respected.
Figure 7.4 highlights the differences between a Theory X manager, a Theory Y manager, and a Theory Z manager.
Contingency Theory The Contingency theory builds on a combination of Theory Y behaviors and the Hygiene theory. (The Hygiene theory is discussed shortly, in the section “Motivational Theories.”) The Contingency theory says that people are motivated to achieve levels of competency and will continue to be motivated by this need even after competency is reached.
Situational Theory Paul Hersey and Ken Blanchard developed the Situational Leadership theory during the mid-1970s. This theory’s main premise is that the leadership style you use depends on the situation. Both Hersey and Blanchard went on to develop their own situational leadership models. Blanchard’s model, Situational Leadership II, describes four styles of leadership that depend on the situation: directing, coaching, supporting, and delegating.
There are various leadership styles that a project manager may use, and in many cases, the appropriate leadership style is based on the situation. The following are examples of leadership styles:
Autocratic All decisions are made by the leader.
Laissez-faire The leader uses a hands-off approach and allows the team to drive the decisions.
Democratic Leaders gather all facts and receive input from the team before reaching a decision.
Situational Based on the Blanchard theory of situational leadership that uses four styles: directing, coaching, supporting, and delegating.
Transactional and Transformational Developed by Bernard Bass. He described transactional leaders as activity-focused and autonomous; they use contingent reward systems and manage by exception. Transformational leaders are described as focusing on relationships rather than activities.
Leaders, managers, and project managers use power to convince others to do tasks a specific way. The kind of power they use to accomplish this depends on their personality, their personal values, and the company culture. Here are five forms of power leaders may use:
There are many theories on motivation, and as a project manager, you should understand and tailor the recognition and rewards programs around the project team. The following are some important motivational theories to note:
Maslow’s Hierarchy of Needs Abraham Maslow theorized that humans have five basic sets of needs arranged in hierarchical order. The idea is that each set of needs must be met before a person can move to the next level of needs in the hierarchy. Once that need is met, they progress to the next level, and so on. Maslow’s hierarchy of needs theory suggests that once a lower-level need has been met, it no longer serves as a motivator, and the next-higher level becomes the driving motivator in a person’s life. Maslow theorized that humans are always in one state of need or another and they can move up and down the pyramid throughout their lives. The following is a brief review of the needs, as shown in Figure 7.5, starting with the highest level and ending with the lowest:
Hygiene Theory Frederick Herzberg came up with the Hygiene theory, also known as the Motivation-Hygiene theory. He postulated that two factors contribute to motivation:
Expectancy Theory The Expectancy theory, first proposed by Victor Vroom, says that the expectation of a positive outcome drives motivation. People will behave in certain ways if they think there will be good rewards for doing so and if they themselves value the reward. Also note that this theory says the strength of the expectancy drives the behavior. This means the expectation or likelihood of the reward is linked to the behavior. This theory also says that people become what you expect of them.
Achievement Theory The Achievement theory, attributed to David McClelland, says that people are motivated by the need for three things:
You should know the following tools and techniques of the Develop Team process:
Colocation Colocation refers to basing team members out of the same physical location. Colocation enables teams to function more effectively than if they’re spread out among different localities. One way to achieve colocation might be to set aside a common meeting room, sometimes called a war room, for team members who are located in different buildings or across town to meet and exchange information.
Virtual Teams Through the use of technology, teams create online work environments that allow shared file storage, use of conversation threads or tools to communicate, and use of a team calendar.
Communication Technology Communication technology helps in the Develop Team process for both collocated and virtual teams. Examples of this technology include video- and audioconferencing tools, use of a shared portal, and email/chat tools.
Interpersonal and Team Skills Interpersonal skills, often referred to as soft skills, include things such as these:
By possessing these skills, the project management team can reduce issues within the project team and better manage the team overall.
Team-Building Activities Team-building activities are also important. Part of the project manager’s job is to bring the team together, get its members headed in the right direction, and provide motivation, reward, and recognition. This is done using a variety of team-building techniques and exercises. Team building involves getting a diverse group of people to work together in the most efficient and effective manner possible.
Important to team-building activities are the theories behind team development. Authors Bruce Tuckman and Mary Ann Jensen developed a model that describes how teams develop and mature. According to Tuckman and Jensen, all newly formed teams go through the following five stages of development:
Figure 7.6 shows the stages of a team’s development.
Recognition and Rewards Recognition and rewards are an important part of team motivation. They are formal ways of recognizing and promoting desirable behavior and are most effective when carried out by the management team and the project manager. Criteria for rewards should be developed and documented, and rewards should be given to team members who go above and beyond the call of duty.
Motivation can be extrinsic or intrinsic:
The recognition and rewards tool of this process is an example of an extrinsic motivator.
Training Training is a matter of assessing the team members’ skills and abilities, assessing the project needs, and providing the training necessary for the team members to carry out their assigned activities. Training can sometimes be a reward as well. Training needs may be incorporated into the staffing management plan or scheduled as they are assessed.
Individual and Team Assessments Personnel and team assessment tools capture feedback obtained on the project team’s level of effectiveness. The intention is to increase the probability of the team’s success in achieving the project objectives through the increase of performance. Team performance is often measured against the following:
Meetings In the Develop Team process, meetings are used for, but not limited to, project orientation, team building, and team development.
The following six outputs result from the Develop Team process:
Team Performance Assessments Team performance assessments involve determining the project team’s effectiveness. Assessing these characteristics helps to determine where (or whether) the project team needs improvements. The following indicators are among those assessed:
Change Requests In the Develop Team process, change requests may be necessary if recommended corrective or preventive actions affect any of the components of the project management plan or project documents.
Project Management Plan Updates The resource management plan is one of the components of the project management plan that may be updated in this process.
Project Documents Updates This process may include updates to multiple project documents including, but not limited to, the following:
Enterprise Environmental Factors Updates Updates to the enterprise environmental factors typically include updates to team records regarding training and skill assessment and any personnel administration updates that resulted from carrying out this process.
Organizational Process Assets Updates Updates to the organizational process assets include updates to the training requirements and personnel assessments.
The Manage Team process is concerned with tracking and reporting on the performance of individual team members. During this process, performance appraisals are prepared and conducted, issues are identified and resolved, and feedback is given to the team members. This process involves management skills that promote teamwork and result in high-performance teams.
Figure 7.7 shows the inputs, tools and techniques, and outputs of the Manage Team process.
There are six inputs to the Manage Team process:
Project Management Plan The primary, but not sole, input to the Manage Team process from the project management plan is the resource management plan. The resource management plan provides the following information that is utilized in this process:
Project Documents Project documents that provide inputs into this process include, but are not limited to, the following:
Work Performance Reports Work performance reports document the status of the project compared to the forecasts. For additional information on performance reports, see the outputs of the Monitor and Control Project Work process in Chapter 8, “Monitoring and Controlling the Project,” in this book.
Team Performance Assessments Team performance assessments, which are an output of the Develop Team process, provide necessary information and insight into the performance and issues of the project team. This information is necessary for managing the group and taking action to resolve any issues and to foster improvement.
Enterprise Environmental Factors The primary enterprise environmental factors that can influence the Manage Team process are human resource management policies.
Organizational Process Assets Organizational process assets used within this process include any existing organizational perks and forms of recognition.
Know the following tools and techniques of the Manage Team process:
Interpersonal and Team Skills There are five types of interpersonal and team skills used most often in this process:
Of all these skills, conflict management deserves some specific focus. Conflict exists when the desires, needs, or goals of one party are incompatible with the desires, needs, or goals of another party (or parties). Conflict is the incompatibility of goals, which often leads to one party resisting or blocking the other party from attaining their goals. Conflict management is how an individual deals with these types of scenarios or issues.
The following six methods of conflict management are also shown in Figure 7.8
The following should also be noted about conflict and conflict resolution:
Project Management Information System Scheduling or resource management software can be used for the management and coordination of team members.
The Manage Team process includes the following outputs:
Change Requests Change requests may result from a change in staffing. Also included within change requests are corrective actions that may result from disciplinary actions or training needs and preventive actions, which may be needed to reduce potential issues among the project team.
Project Management Plan Updates Project management plan updates may include changes that occurred in the resource management plan, schedule baseline, and cost baseline.
Project Documents Updates The following project documents are typically updated as a result of carrying out this process:
Enterprise Environmental Factors Updates There are two components of the enterprise environmental factors that may need updating as a result of this process:
Executing the project management plan is carried out through the Direct and Manage Project Work process, which is a process that belongs to the Project Integration Management Knowledge Area. This is where the project work is carried out, according to the plan, as a way of producing the deliverables on time and on budget. The Direct and Manage Project Work process is also responsible for implementing changes that have been approved by the change control board. Typically, approved changes are implemented according to the change management plan as a way of meeting project requirements.
When implementing the plan, the project manager will need to be proactive in managing project communications. This includes distributing relevant project information in an efficient and effective manner. Managing stakeholder engagement is also important at this stage. Both of these objectives can be accomplished by carrying out the Manage Communications and Manage Stakeholder Engagement processes in accordance with the communications management plan and stakeholder engagement plan.
The Direct and Manage Project Work process is responsible for carrying out the project management plan. The project manager oversees the actual work, staying on top of issues and problems and keeping the work lined up with the plan. Coordinating and integrating all the elements of the project are among the most challenging aspects of this process.
According to the PMBOK® Guide, this process also requires implementing corrective actions to bring the work of the project back into alignment with the project management plan, preventive actions to reduce the probability of negative consequences, and repairs to correct product defects discovered during the quality management processes.
Figure 7.9 shows the inputs, tools and techniques, and outputs of the Direct and Manage Project Work process.
Know the following inputs for the Direct and Manage Project Work process:
Project Management Plan The project management plan documents the collection of outputs of the planning processes and describes and defines the work to be carried out and how the project should be executed, monitored, controlled, and closed.
Project Documents The following project documents are typically considered as inputs for this process:
Approved Change Requests Approved change requests come about as a result of the change request status updates output of the Perform Integrated Change Control process. Approved change requests are then submitted as inputs to the Direct and Manage Project Work process for implementation. Implementation of approved changes may also include the implementation of workarounds, which are unplanned responses to negative risks that have occurred.
Enterprise Environmental Factors The following enterprise environmental factors are considered when performing the Direct and Manage Project Work process:
Organizational Process Assets The following organizational process assets are utilized within the Direct and Manage Project Work process:
You should be familiar with the following tools and techniques of the Direct and Manage Project Work process:
Expert Judgment Expert judgment is provided by the project manager and project team members as well as by the following sources:
Project Management Information System As used in the Direct and Manage Project Work process, the project management information system (PMIS) provides the ability to connect to automated tools, such as scheduling software and configuration management systems, that can be utilized during project execution.
Meetings Meetings are a key tool in managing the work of the project. According to the PMBOK® Guide, there are three types of meetings: information exchange, working sessions such as brainstorming and design, and decision making.
These seven outputs result from carrying out the Direct and Manage Project Work process:
Deliverables According to the PMBOK® Guide, a deliverable (see Figure 7.10) is defined as any unique and verifiable product, result, or capability to perform a service that is required to be produced to complete a process, phase, or project.
During the Direct and Manage Project Work process, the following information regarding the outcomes of the work is gathered and recorded:
Work Performance Data Work performance data involves gathering, documenting, and recording the status of project work. Here are types of information that may be gathered during this process:
Issue log All project issues are recorded and tracked in a document known as the issue log. The following elements may be included on the issue log:
Change Requests Changes can come about from several sources, including stakeholder requests, external sources, and technological advances. Change requests may encompass changes to the following:
Implementation of change requests may incorporate the following actions:
Project Management Plan Updates The following project management plan updates may occur as a result of the Direct and Manage Project Work process:
Project Documents Updates The following project documents may undergo updates as a result of the Direct and Manage Project Work process:
Organizational Process Assets Updates It is possible that any organizational process asset could be updated as a result of the Direct and Manage Project Work process.
The Manage Communications process is responsible for getting information about the project to stakeholders in a timely manner. It describes how reports, and other information, are collected, stored, retrieved, and distributed and to whom. Executing the communications management plan also occurs during this process.
Figure 7.11 shows the inputs, tools and techniques, and outputs of the Manage Communications process.
Know the following inputs of the Manage Communications process:
Project Management Plan The communications management plan, resource management plan, and stakeholder engagement plan are the primary components of the project management plan. The plan is put into action during this process.
Project Documents The following project documents are typically considered as inputs for this process:
Work Performance Reports Work performance reports are utilized to distribute performance and status information to the appropriate individuals.
Enterprise Environmental Factors Enterprise environmental factors used through this process include the organizational culture and structure, any government- or industry-related standards, and the project management information system.
Organizational Process Assets For this process, organizational process assets refer to any policies, procedures, and guidelines that the organization already has in place for distributing information and any existing documents and information that are relevant to the process.
The tools and techniques of the Manage Communications process include the following seven items:
Communication Technology Technology is often used to disseminate information to stakeholders as appropriate and as described within the communications management plan.
Communication Methods Choosing the appropriate communication methods will allow the message to be catered to the events and audience who need to receive the information.
Communication Skills There are a variety of communication techniques that are used in the Manage Communications process, which include but are not limited to the following:
Project Management Information System The following information distribution tools are used to get the project information to the project team or stakeholders:
Project Reporting Project reporting refers to the actual collection and distribution of information, typically through the form of a project status report. This may include a diverse set of reports, from basic reporting to detailed and complex analysis of the project team’s performance. Project reporting may also be communicated via progress metrics and forecasts.
Interpersonal and Team Skills There are a number of interpersonal and team skills that can be used in the Manage Communications process. These include but are not limited to the following:
Meetings The communication model selected for managing communications should be based on the communication needs of the project.
Manage Communications results in four outputs that you should know: project communications, updates to the project management plan, updates to project documents, and updates to the organizational process assets.
Project Communications Project communications refers to the actual communication produced, often by the project manager. Examples of project communications presented by the PMBOK® Guide include performance reports, deliverable status, schedule progress, and actual costs to date.
Project Management Plan Updates Typical updates produced to the project management plan as a result of this process includes updates to the communications management plan, stakeholder management plan, and project baselines.
Project Documents Updates Project documents updated as a result of carrying out this process often includes updates made to the issue log, schedule, and project funding requirements.
Organizational Process Assets Updates There can be several updates to the organizational process assets as a result of carrying out this process. These updates are listed and described in Table 7.1.
TABLE 7.1 Organizational process assets updates
Update Item | Description |
Stakeholder notifications | Notifications sent to stakeholders when solutions and approved changes have been implemented, the project status has been updated, issues have been resolved, and so on. |
Project reports | The project status reports and minutes from project meetings, lessons learned, closure reports, and other documents from all the process outputs throughout the project. |
Project presentations | Project information presented to the stakeholders and other appropriate parties when necessary. |
Project records | Memos, correspondence, and other documents concerning the project. |
Feedback from stakeholders | Feedback that can improve future performance on this project or future projects. The feedback should be captured and documented. |
Lessons learned documentation | Information that is gathered and documented throughout the course of the project and can be used to benefit the current project, future projects, or other projects being performed by the organization. |
The Manage Stakeholder Engagement process is responsible for satisfying the needs of the stakeholders by managing communications with them, resolving issues, improving project performance by implementing requested changes, and managing concerns in anticipation of potential problems.
Figure 7.12 shows the inputs, tools and techniques, and outputs of the Manage Stakeholder Engagement process.
Know the following inputs of the Manage Stakeholder Engagement process:
Project Management Plan The project management plan document contains several components useful in managing stakeholder expectations within the project. This includes, but is not limited to, the following components:
Project Documents Project documents such as the change log, issue log, and lessons learned register can be inputs to the Manage Stakeholder Engagement process.
Enterprise Environmental Factors Enterprise environmental factors used through this process include the organizational culture and structure, industry- or government-related standards, and the project management information system.
Organizational Process Assets The following organizational process assets influence this process:
Be familiar with the following six tools and techniques of the Manage Stakeholder Engagement process, and how they are used in this process:
Expert Judgment Expert judgment may include input from experts or those with specialized knowledge on the following topics:
Inspection Project documentation and reports will need be inspected to enforce stakeholder engagement activities as originally designed or to make adjustments as needed.
Communication Skills With guidance from the communications management plan, the project team uses feedback to assist in understanding stakeholder reaction to activities and decisions during the course of the project.
Interpersonal and Team Skills Interpersonal and team skills were introduced in the Develop Team process. To manage stakeholder expectations and engagement, the project manager utilizes soft skills, such as building trust, conflict management, negotiation, establishing relationships, and listening.
Ground Rules Defined in the team charter, ground rules set the behavioral expectations for team members and stakeholders.
Meetings In the Management Stakeholder Engagement process, meetings provide a forum to discuss or address any issue or concern for communicating with stakeholders. This might include but is not limited to the following types of meetings:
The Manage Stakeholder Engagement process results in the following outputs:
Change Requests The following change requests may emerge as a result of this process:
Project Management Plan Updates Updates to the project management plan as a result of carrying out this process often involve updating the communications management plan and the stakeholder engagement plan.
Project Documents Updates The stakeholder register, change log, lessons learned register, and issue log may all need updates as a result of carrying out this process.
As described in the previous section, the need for changes will emerge as the project work is executed. All change requests created to deal with this need must first be approved by the change control board before they can be implemented. This occurs through the Perform Integrated Change Control process, which is discussed in Chapter 8, “Monitoring and Controlling the Project,” and must be managed according to the change management plan.
It’s also important to keep in mind that the moment the work enters into the executing stage of the project, monitoring and controlling activities begin and continue concurrently as the work is progressing. Monitoring and controlling activities also identify the need for corrective and preventive actions as well as defect repairs. Once change requests are approved, they are implemented through the Direct and Manage Project Work process, discussed previously.
Implementing the quality management plan occurs throughout the Executing and Monitoring and Controlling process groups. During Executing, quality assurance activities take place. Quality assurance is responsible for auditing quality control activities and the effectiveness of the project management processes. These activities are carried out through the Manage Quality process.
The Manage Quality process involves performing systematic quality activities and uses quality audits to determine which processes should be used to achieve the project requirements and to ensure that they are performed efficiently and effectively. This process also brings about continuous process improvement through improved process performance and eliminating unnecessary actions. This is done by assessing whether the processes are efficient and whether they can be improved.
Figure 7.13 shows the inputs, tools and techniques, and outputs of the Manage Quality process.
Know the following three inputs of the Manage Quality process:
Project Management Plan The quality management plan is the primary, but not the only, component of the project management plan that can provide guidance for carrying out quality assurance activities through this process.
Project Documents The following project documents are typically considered as inputs for this process:
Organizational Process Assets The following organizational process assets influence this process:
You should be familiar with the following tools and techniques of the Manage Quality process:
Data Gathering Checklists are a primary data-gathering technique used for this process. Checklists are structured tools that guide the specific steps to be performed to ensure that requirements are met.
Data Analysis The following data analysis techniques can be used for this process:
Decision Making The primary, but not sole, decision-making technique used for this process is multicriteria decision analysis. When this technique is used, several criteria are considered while evaluating alternatives that impact project or product quality.
Data Representation The Manage Quality process utilizes tools and techniques also used during the Plan Quality Management and Control Quality processes. Examples of tools used include, but aren’t limited to, the following:
Audits Audits are independent reviews performed by trained auditors or third-party reviewers, either on a regular schedule or at random. The purpose of an audit is to identify ineffective and inefficient activities or processes used on the project.
Quality improvements come about as a result of the audits, as shown in Figure 7.14 .
Quality improvements are implemented by submitting change requests, which may entail taking corrective action.
Design for X When inventing a specific product to meet a specific design aspect, design for X brings a set of technical guidelines to the product.
Problem Solving Problem solving is the technique of searching for solutions for various issues or challenges. Using this tool effectively is a core piece of quality assurance and quality improvement.
Quality Improvement Methods The Manage Quality process utilizes methods to improve quality based upon findings and recommendations from quality control processes, such as Plan-Do-Check-Act or Six Sigma.
The Manage Quality process results in the following five outputs:
Quality Reports Graphical, numerical, or qualitative reports can be used to direct corrective actions needed to fulfill the project quality expectations. These become an input to the Control Quality process.
Test and Evaluation Documents Based upon organizational templates or industry needs, test and evaluation documents are used to evaluate the achievement of quality objectives. Dedicated checklists and detailed requirements traceability matrices are examples of these documents.
Change Requests During this process, any recommended corrective actions, whether they are a result of a quality audit or process analysis, should be acted upon immediately. Change requests may involve corrective action, preventive action, or defect repair.
Project Management Plan Updates As a result of this process, the quality management plan may need to be updated. The following documents may also require changes within the project management plan:
Project Documents Updates Updates may include changes to the following project documents:
As the work of the project is executed, predefined risk triggers may occur and some risks will be realized, calling for the execution of risk response plans, contingency plans, and fallback plans. These responses are defined within the risk register and should be managed according to the risk management plan. The risk management plan is important in reducing the impact of negative risks on the project.
The risk responses documented within the risk register are executed as part of the Implement Risk Responses process, which is the only process within the Project Risk Management Knowledge Area that falls within the Executing process group.
The Implement Risk Responses process is responsible for implementing agreed-upon response plans so that overall risk exposure is managed and to minimize unique project threats and maximize opportunities. While listed in the Executing process group, managing risk responses can occur throughout the entire project.
Figure 7.15 shows the inputs, tools and techniques, and outputs of the Implement Risk Responses process.
Know the following inputs of the Implement Risk Responses process:
Project Management Plan The primary, but not sole, component of the project management plan used in the Implement Risk Responses process is the risk management plan. The risk management plan helps to pair identified risks with an owner by listing the risk-related roles and responsibilities of the team. Additionally, this plan sets the precision, or level of detail, to be used for the risk management methodology. The risk management plan also lists risk thresholds for the project as defined by the stakeholders’ risk appetite.
Project Documents The following project documents are typically considered as inputs for this process:
Organizational Process Assets The lessons learned repository is the primary (but not only) organizational process asset that is used as an input to this process. Comparing risk responses from prior and similar projects can help guide the effectiveness of responses to risks.
Be familiar with the following three tools and techniques of the Implement Risk Response process. Know how they are used in this process:
Expert Judgment Expert judgment may include employing subject matter experts or those with specialized knowledge to validate or adjust risk responses.
Interpersonal and Team Skills The primary interpersonal skill and team skill used is influencing. Projects often have external stakeholders who can have demands that compete with the goals of the project team.
Project Management Information System The project management information system has cost, resource, and schedule information attached to agreed-upon risk response plans and their activities.
The Implement Risk Responses process results in the following two outputs:
Change Requests During this process, risk responses can have an impact on schedule and cost baselines and need to be processed as change requests through the Perform Integrated Change Control process.
Project Documents Updates Updates may include, but are not limited to, changes to the following project documents:
Let’s briefly review the processes that were covered in this chapter and, more important, how these processes work together. You may recall that the primary objective of the Executing process group is to complete the work defined in the project management plan. In addition to this, we also coordinate and manage resources, implement approved changes, and manage communications.
As we went through the processes covered in this chapter, you may have noticed an ongoing theme: human resources. Whether these resources were internal to the organization or external, we covered a lot of information that dealt with the project team, including obtaining the resources and managing them. We also covered the management of stakeholder expectations and their engagement.
Figure 7.16 shows how people-centric the Executing Process Group really is. Within the realms of this figure, we see the following take place:
Clearly, a lot of behind-the-scenes effort goes into the executing stage. For example, the project team must be assembled and managed.
Altogether, we covered eight processes within this chapter, which make up the Executing process group. These processes spanned the following Knowledge Areas:
Next, we will review the process interactions that occur within each Knowledge Area during the Executing process group.
During the Executing process group, the Project Integration Management Knowledge Area covers the implementation of the project management plan through a single process known as the Direct and Manage Project Work process. As Figure 7.17 shows, the project management plan and the approved changes (which occur after the work has already been executed) are carried out through this process. As a result, deliverables and information on the work performance during the project are generated.
The Manage Quality process is the only quality-related process that falls within the Executing process group. As you may recall, this is where auditing takes place, which ultimately leads to implemented changes and continuous process improvement. The following items are among those that are audited:
Figure 7.18 provides a glimpse into the information needed to perform the quality audits. Quality metrics, which were defined in the Planning process group, provide work performance data and quality measurements. These quality measurements are gathered while the project’s quality is being monitored and controlled. You can see the level of interaction between the three quality processes throughout the life cycle of the project. The processes are iterative.
Three of the six processes related to resources occur within the Executing process group. Remember that this process group involves coordinating and managing people, and you cannot implement the project work without a project team. Additionally, this process manages the physical assets needed for the project. Figure 7.19 shows, step-by-step, how the project team comes together so that the project work can be rolled out.
Here is an overview of these steps:
As the project work is executed, communication becomes more important than ever. All of the planning behind how communication will take place within the project goes into effect. This is where knowing the communication needs and requirements of your stakeholders becomes particularly important. Be sure you place a great level of importance on knowing your stakeholders.
There is one communications-related process within the Executing process group, which makes project information available to stakeholders. As you can see in Figure 7.20, the stakeholder communication requirements must be developed before you can manage communications. After all, you cannot meet your team’s communication needs if you do not know what they are. These communication needs and requirements are determined in the Initiating and Planning process groups.
Figure 7.20 also shows how the management of the project stakeholder communications fits in with the communication processes. This step involves addressing any existing issues and recommending changes to resolve conflicts. It also involves the management of stakeholder engagement with the idea of unifying the project goals.
Throughout the project, risk management becomes an important set of activities that project managers must be actively monitoring and engaging with. Beyond just the Executing process group, risks triggers will occur and risks will materialize. This means that risk response plans will need to be implemented.
The Project Risk Management Knowledge Area has only a single process that falls within the Executing process group, and that is the Implement Risk Responses process. It’s through this process that the risk responses logged in the risk register are put into motion. Figure 7.21 provides a glimpse of the Implement Risk Responses process.
During the Executing process group, vendors are selected for work that will be handled externally. Conducting procurements is part of obtaining and hiring the resources needed to complete the project work. As you can see, much of project execution involves hiring and managing people resources—internal and external to the organization.
Figure 7.22 shows how the single procurement process that takes place during project execution results in the selection of the project’s sellers and the issuance of procurement contracts. To arrive at this outcome, you will use several planned procurement items:
Stakeholder management is critical to the success of the project, particularly when the project team is actively executing the project work. During the Executing process group, the project manager actively engages with stakeholders to ensure that their needs and expectations are met.
Figure 7.23 shows how the Manage Stakeholder Engagement process interacts with other processes.
As you reflect on the Executing process group, always remember that the key purpose is to complete the project work.
Jon is gearing up for his upcoming project, which involves programming a complex system that will allow two programs to talk to each other. The project kicks off in one week, and he had been specifically requested by the customer. As a software architect, this assignment will be his most challenging project yet, and he has been looking forward to the assignment for months. Which of the following options best describes Jon’s upcoming project role?
All of the following are benefits of virtual teams except:
At which stage of team development do employees compete for control?
Sally, a junior project manager for Project Red, is in the process of holding a status meeting for the project manager, who stepped out to deal with a procurement issue. The tension in the room has been high as a result of two critical resources who suddenly quit. John and Rick, both team members, have been arguing for five minutes over who will take over the tasks. Sally has tried to interject multiple times with no success. The side conversations don’t make managing the meeting any easier. What is the most likely cause of the inefficient meeting?
Which of the following levels within Maslow’s hierarchy of needs describes the need to belong?
Which of the following conflict management techniques is said to be the best strategy?
Meetings, email, videoconferences, and conference calls are all examples of which of the following options?
The project team of a new housing expansion project is in a state of frenzy because of a surprise quality audit that is being conducted today on the project. In three days, a major deliverable is due. The project manager explains to the team that the quality audit is important. What reasoning is the project manager likely to give the team for explaining why the quality audits are needed in a project?
Who is responsible for defining Theory X & Y?
The following are tools and techniques of the Manage Stakeholder Engagement process except:
Beans by the Dozen is a company that ships pre-cooked beans to restaurants in the western United States. Recently, the company has decided to expand their operation to the northern regions of the country. The project manager assigned to the project has just instituted a war room to bring project team members together and concluded a team-building session after collocating the team. What process is the project manager carrying out?
Through which process group is the majority of the project budget consumed?
Polly is a project manager tasked with leading a project that will establish business continuity management practices for a major retail coffee chain. She has just concluded planning efforts on the project and is gearing up to begin executing the work of the project. What is she likely to do first?
Which of the following tools and techniques provides an opportunity for prospective vendors to ask sellers questions about an RFP?
A deliverable can best be described as:
A project manager has just gathered the status of project activities and calculated resource consumption to date. What process is the project manager carrying out?
The issue log is first created as a result of which process?
The following represent the results generated from carrying out the Direct and Manage Project Work process except:
The following are inputs used to carry out the Manage Quality process except:
Polly is a project manager tasked with leading a project that will establish business continuity management practices for a major retail coffee chain. By facilitating quality audits, the project team recently discovered corrective action needed to bring the project into compliance with quality requirements. How will Polly process the corrective action?
18.118.140.108