Chapter 9
Closing the Project

THE PMP® EXAM CONTENT FROM THE CLOSING THE PROJECT PERFORMANCE DOMAIN COVERED IN THIS CHAPTER INCLUDES THE FOLLOWING:

  • images Obtain final acceptance of the project deliverables from relevant stakeholders in order to confirm that project scope and deliverables were achieved.
  • images Transfer the ownership of deliverables to the assigned stakeholders in accordance with the project plan in order to facilitate project closure.
  • images Obtain financial, legal, and administrative closure using generally accepted practices and policies in order to communicate formal project closure and ensure transfer of liability.
  • images Prepare and share the final project report according to the communications management plan in order to document and convey project performance and assist in project evaluation.
  • images Collate lessons learned that were documented throughout the project and conduct a comprehensive project review in order to update the organization’s knowledge base.
  • images Archive project documents and materials using generally accepted practices in order to comply with statutory requirements and for potential use in future projects and internal/external audits.
  • images Obtain feedback from relevant stakeholders using appropriate tools and techniques and based on the stakeholder management plan in order to evaluate their satisfaction.

imagesClosing is the final process group of the five project management process groups and accounts for 7 percent of the questions on the PMP® exam. The primary purpose of Closing is to formally complete the project, phase, or contractual obligations. Finalizing all of the activities across the project management process groups accomplishes this.

By the end of the process that makes up the Closing process group, the completion of the defined processes across all of the process groups will have been verified. Don’t forget that the closeout preparations begin early in the project with the clear and well-defined success criteria of the project.

Obtaining Final Acceptance

All projects must be formally closed out regardless of the reasons for closure (such as successful completion or early termination). According to the PMBOK® Guide, the following typically occurs during formal closing of the project or project phase:

  • Ensuring that exit criteria are met
  • Obtaining formal acceptance by the customer or sponsor
  • Closing out procurement contracts
  • Conducting phase-end or post-project reviews
  • Updating the organizational process assets, which includes documenting lessons learned and archiving project documents in the project management information system (PMIS)
  • Recording the impacts of tailoring to any process
  • Performing assessments of the project team members
  • Transferring the project’s product, service, or results to the next phase or to operations
  • Measuring stakeholder satisfaction

These activities are carried out through a single process called Close Project or Phase.

Close Project or Phase

The Close Project or Phase process is concerned with finalizing activities necessary to complete a project, phase, or contract; this includes gathering project records and disseminating information to formalize the acceptance of the product, service, or result. The process belongs to the Project Integration Management Knowledge Area. Here are additional notes about the process you should know:

  • It involves analyzing the project management processes to determine their effectiveness.
  • It documents lessons learned concerning the project processes.
  • It closes out procurement activities.
  • It archives all project documents for historical reference. You can probably guess that Close Project or Phase belongs to the Project Integration Management Knowledge Area since this process touches so many areas of the project.
  • It investigates and documents reasons for a project or phase being terminated prior to its completion.

According to the PMBOK® Guide, every project requires closure, and the completion of each project phase requires project closure as well. The Close Project or Phase process is performed at the close of each project phase and at the close of the project.

Figure 9.1 shows the inputs, tools and techniques, and outputs of the Close Project or Phase process.

Image described by caption and surrounding text.

FIGURE 9.1 Close Project or Phase process

Inputs of Close Project or Phase

For the exam, know the eight inputs of the Close Project or Phase process:

Project Charter The project charter contains the success criteria and other approval requirements necessary to close out a phase or project.

Project Management Plan For a project to be considered closed, the project management plan will be reviewed by the project manager to ensure completion of the deliverables and that all objectives of the project have been met.

Project Documents Several project documents can be referenced to validate that closure requirements have been met. According to the PMBOK® Guide, the following are examples of documents that may be referenced:

  • Assumptions log: Contains assumptions and constraints
  • Basis of estimates: Contains details behind estimates produced
  • Change log: Details status of all change requests
  • Issue log: Contains status of all open issues
  • Lessons learned register: Includes lessons learned from the phase or project to be finalized
  • Milestone list: Contains final dates on which milestones are to be accomplished
  • Project communications: Includes all communications created to date
  • Quality control measurements: Contains results of quality control activities to determine compliance against requirements
  • Quality reports: Includes quality assurance issues, recommendations for improvement, and summary of quality control findings
  • Requirements documentation: Used to demonstrate compliance against the project scope
  • Risk register: Provides details about risks captured
  • Risk report: Provides summary of information on risk status

Accepted Deliverables Accepted deliverables are an output of the Validate Scope process. This input is necessary to determine whether all deliverables have been successfully completed.

Business Documents Business documents typically referenced include the business case, which contains the cost benefit analysis and business need being satisfied, and the benefits management plan, which notes when benefits are expected to be achieved.

Agreements Agreements become a necessary input to the process, since it’s through this process that procurement activities are finalized. Agreements contain the terms and conditions related to contract closure.

Procurement Documentation According to the PMBOK® Guide, procurement documentation is collected, indexed, and filed through the Close Project or Phase process. Procurement documentation typically includes the following:

  • Contract schedule
  • Scope
  • Quality
  • Cost performance
  • Contract change documentation
  • Payment records
  • Inspection results

Organizational Process Assets The following organizational process assets are typically used in this process:

  • Guidelines for closing out the project or project phase
  • Historical information and lessons learned
  • Project closure reports
  • Configuration management knowledge base

Tools and Techniques of Close Project or Phase

The Close Project or Phase process has three tools and techniques: expert judgment, data analysis, and meetings.

Expert Judgment Subject matter experts can help ensure that the process is performed according to the organization’s standard and to project management standards. Experts typically include other project managers, the project management office, and organizations such as PMI® or other technical organizations that publish standards and resources.

Data Analysis Analytical techniques may be used to ensure that closure activities are ready to be performed and are performed correctly. Regression analysis and trend analysis are two examples of techniques provided by the PMBOK® Guide, as well as document analysis and variance analysis. These data analysis techniques help teams gather lessons learned to improve the performance on projects taken on in the future.

Meetings Meetings are often used as a means of bringing experts together to validate that deliverables have been accepted. Other uses of meetings at this stage include transferring knowledge, capturing lessons learned, and celebrating successful closure of a phase or project. Meetings may occur in a variety of formats, such as in person or virtual.

Outputs of Close Project or Phase

The four outputs that result from carrying out the Close Project or Phase process are as follows:

Final Product, Service, or Result Transition Final product, service, or result transition refers to the acceptance of the product and the turnover to the customer or into operations. This is where information is distributed that formalizes project completion.

Final Report The project’s final report includes an overall summary of how the project has performed. According to the PMBOK® Guide, it may include things such as these:

  • Summary description of project or phase
  • Objectives and criteria used to evaluate the following metrics:
    • Scope
    • Quality
    • Schedule
    • Cost
  • Summary of how the final result achieved the targeted benefits and business needs
  • Summary of risks

Project Documents Updates Any and all project documents may be updated as a result of carrying out this process. One document, in particular, that is important is the lessons learned register.

Organizational Process Assets Updates The following organizational process assets are typically updated as a result of the Close Project or Phase process:

  • Project files, such as the project planning documents, change records and logs, and issue logs
  • Project or phase closure documents, which include documentation showing that the project or phase is completed and that the transfer of the product of the project to the organization has occurred
  • Project closure reports
  • Historical information, which is used to document the successes and failures of the project
  • Operational or supporting documents
  • Procurement file, which includes all of the procurement records and supporting documents
  • Deliverable acceptance, which is a formal written notice from the buyer that the deliverables either are acceptable and satisfactory or have been rejected
  • Lessons learned documentation

Transferring Ownership

The acceptance and turnover of the product to the customer or into operations typically involves a formal sign-off indicating that those signing accept the product of the project. This occurs as a result of carrying out the Close Project or Phase process, which was discussed earlier in this chapter.

Obtaining Financial, Legal, and Administrative Closure

Aside from the Closing process, there are a few additional items to note about the Closing process group and finalizing project closure. To start, project or phase closure is carried out in a formal manner and requires that financial, legal, and administrative closure be obtained. This is important to communicating formal closure and to ensuring that no further liability exists after the project has been completed.

It’s important to note that a project can move into the Closing process group for several reasons:

  • It’s completed successfully.
  • It’s canceled or killed prior to completion.
  • It evolves into ongoing operations and no longer exists as a project.

Formal Project Endings

Aside from these common reasons that result in a project moving into the Closing process, there are four formal types of project endings that you should be familiar with: addition, starvation, integration, and extinction.

Addition A project that evolves into ongoing operations is considered a project that ends because of addition, moving into its own ongoing business unit. Once it experiences this transition, it no longer meets the definition of a project.

Starvation Starvation occurs when resources are cut off from a project prior to the completion of all the requirements. This results in an unfinished project. Starvation often occurs as a result of shifting priorities, a customer’s cancellation of an order or request, the project budget being reduced, or key resources quitting.

Integration Integration occurs when the resources of a project (such as people, equipment, property, and supplies) are distributed to other areas in the organization or are assigned to other projects. In other words, resources have been reassigned or redeployed, causing an end to the project.

Extinction Extinction occurs when a project has completed and stakeholders have accepted the end result. This is the best type of ending because the project team has completed what they set out to achieve.

In all cases, if a project ends early, it’s important to retain good documentation that describes why the project ended early. Performing a project review in these cases is important to retaining key details and specifics regarding why a project ended before all requirements were completed.

Trends

Another notable piece of information involves stakeholder influence and cost trends that occur during project closure. Stakeholders tend to have the least amount of influence during the Closing process, while project managers have the greatest amount of influence. Costs are significantly lower during the Closing process because the majority of the project work and spending has already occurred.

Administrative Closure

As part of administrative closure, resources will need to be released and the administrative closure procedures carried out.

Release Resources

Although releasing project team members is not an official process, you will release your project team members at the conclusion of the project, and they will go back to their functional managers or be assigned to a new project if you’re working in a matrix-type organization. The release of project resources is addressed within the resource management plan, which is created through the Plan Resource Management process.

As you learned in Chapter 5, “Planning Project Resource, Communication, Procurement, Change, and Risk Management,” the resource management plan includes a section called “project team resource management,” which includes details of how resources will be defined, staffed, managed, and released. The resource management plan is a subsidiary plan of the project management plan. It typically addresses the release of resources (not just at the end of the project, but in general at any point within the project), outlines the method for resource release, and defines when resources are to be released.

Once resources are released, the costs of the resources are no longer charged to the project. The resource management plan helps mitigate human resource risks that may occur during or at the conclusion of the project.

Perform Administrative Closure

Administrative closure procedures involve the following:

  • Collecting all the records associated with the project
  • Analyzing the project success (or failure)
  • Documenting and gathering lessons learned
  • Properly archiving project records
  • Documenting the project team members’ and stakeholders’ roles and responsibilities:
    • Approval requirements of the stakeholders for project deliverables and changes to deliverables
    • Confirmation that the project meets the requirements of the stakeholders, customers, and sponsor
    • Documented actions to verify that the deliverables have been accepted and exit criteria have been met

Figure 9.2 shows the elements of the administrative closure procedures.

Image described by caption and surrounding text.

FIGURE 9.2 Administrative closure procedures

Distributing the Final Project Report

As part of formally closing out a project, the project manager will need to create and distribute the final project report. As you saw in our review of the process outputs, this generally occurs as part of the Close Project or Phase process, where administrative details are addressed. The final project report should include all project closure–related details, project variances, and any issues. The project manager should ensure that final project status is distributed to the stakeholders.

Collating Lessons Learned

One of the recurring themes communicated across the PMBOK® Guide is the proactive nature of the project manager, expressed by their actions. An example of being proactive is documenting lessons learned as part of the organizational process assets and capturing them within the lessons learned register.

Documenting lessons learned, as mentioned previously, focuses on capturing what went well within the project, what didn’t go well, and what can be improved. Although lessons learned are recorded throughout the life of the project, holding a final review with the project team before the team is released at the end of the project is essential. This information can be captured through a comprehensive project review with stakeholders and then can be added to the organization’s knowledge base.

Documenting lessons learned occurs as part of the Close Project or Phase process, through the organizational process assets updates output.

Archiving Project Documents

As part of the Close Project or Phase process, project documents are archived. This occurs through the organizational process assets updates output, which makes the historical documents available for future reference and use. Archiving project documents provides the following benefits:

  • Retaining organizational knowledge
  • Ensuring that statutory requirements, if applicable, are adhered to
  • Making project data available for use in future projects
  • Making project data available for internal/external audits

Measuring Customer Satisfaction

According to the PMBOK® Guide, project success is measured by the following criteria:

  • Product and project quality
  • Timeliness
  • Budget compliance
  • Degree of customer satisfaction

Customer satisfaction is an important goal you’re striving for in any project. If your customer is satisfied, it means you’ve met their expectations and delivered the product or service as defined within the planning processes. Customer satisfaction can be measured through quality management, which in part is concerned with making sure that customer requirements are met. This is done through understanding, evaluating, defining, and managing customer and stakeholder expectations.

As Figure 9.3 illustrates, modern quality management achieves customer satisfaction in part by ensuring that the project accomplishes what it set out to do (conformance to requirements) and that it satisfies real needs (fitness for use).

Image described by caption and surrounding text.

FIGURE 9.3 Measuring customer satisfaction

Bringing the Processes Together

The Closing process group consists of a single process that works toward closing out the project or project phase. Before closing out the project, the project manager must first make sure that the project has met its objectives and accomplished what it set out to achieve. The Closing process group is also concerned with the following objectives:

  • Obtaining formal acceptance of the project’s completion
  • Releasing the project resources
  • Measuring customer satisfaction
  • Archiving the project information for later use

Figure 9.4 reflects the objectives of the Closing process group through several key questions that the project manager should ask before considering the project fully closed.

Diagram shows closure checklist having questions like deliverables verified?, stakeholders satisfied?, contracts closed?, resources released?, all loose ends tied?, et cetera.

FIGURE 9.4 Project closure checklist

Next, we’ll go through the Closing process reviewed in this chapter.

Project Integration Management Knowledge Area Review

A project closeout cannot occur without first finalizing all project or phase activities. The Close Project or Phase process from within the Project Integration Management Knowledge Area is responsible for making this happen. Figure 9.5 shows what occurs within this process. The accepted deliverables are used to verify that the project or the project phase has accomplished what it needed to.

Image described by caption and surrounding text.

FIGURE 9.5 Process interaction: integration

Keep in mind that all procurement contracts must be completed and closed out before the project itself can close. Any loose ends or work on the vendor’s end must be finalized as part of closing activities. You may recall that contract closure occurs through the Control Procurements process, part of the Monitoring and Controlling process group, and that all procurement activities are finalized through the Close Project or Phase process.

The Close Project or Phase process is also responsible for administrative closure of the project or project phase. The result is the transition to the customer of the final product, service, or result that the project created.

Before a project can be fully closed, all of the project documents must be archived within the organizational process assets. As you may recall, this includes all of the project files, any closing documents, and historical information. The historical information is archived within the lessons learned knowledge base, which will be a valuable asset to future projects.

Review Questions

  1. All of the following are inputs of the Close Project or Phase process except:

    1. Procurement documentation
    2. Project management plan
    3. Accepted deliverables
    4. Final product, service, or result transition
  2. A project manager of a travel excursion company is currently working on confirming that all project deliverables have been successfully completed to transfer the project to the customer. What process is the project currently in?

    1. Validate Scope
    2. Scope Closure
    3. Close Project or Phase
    4. Close Procurements
  3. When closing out a project or project phase, which of the following tools and techniques can be used to ensure that closure has been performed to the appropriate standards?

    1. Records management system
    2. Procurement audits
    3. Expert judgment
    4. Organizational process assets
  4. The Close Project or Phase process accomplishes all of the following except:

    1. Updating and archiving records for future reference
    2. Closing procurements
    3. Documenting and verifying project outcomes
    4. Transitioning the final product, service, or result to the organization
  5. While conducting project closure activities, a relatively new project manager of a whiteboard production company becomes confused as to how the organization verifies that the existing criteria have been met. The project manager has found that some of the procedures followed by the organization are different from the procedures used in previous companies she’s worked for. Where can the project manager go to clarify the procedures for verifying that the exit criteria have been met?

    1. Administrative closure procedures
    2. Close Project or Phase
    3. Control Procurements
    4. Expert judgment
  6. All of the following are tools and techniques of the Close Project or Phase process except:

    1. Claims administration
    2. Data analysis
    3. Meetings
    4. Regression analysis
  7. A project manager was in the midst of trying to resolve a dispute with one of the project’s largest vendors. The issue revolved around the responsibility of the vendor to comply with changes to the scope. Although this was addressed in the contract, the vendor felt that the scope changes were much larger than the scope of the contract itself. What would be the best way to resolve the dispute?

    1. Through the court system
    2. Using an alternative dispute resolution technique
    3. Terminating the contract
    4. Making changes to the contract
  8. Project managers have the greatest amount of influence during which stage of the project?

    1. Prior to the start of the project
    2. During the Planning processes
    3. During execution of the project work
    4. During the Closing processes
  9. Resource release criteria can best be found in which plan?

    1. Project management plan
    2. Staff release plan
    3. Project team resource management
    4. Resource management plan
  10. A major deliverable has just been signed off by the sponsor. What is the project manager likely to do next?

    1. Carry out the Close Project or Phase process
    2. Carry out the Validate Scope process
    3. Carry out the Control Quality process
    4. Carry out Integration activities
  11. Polly is a project manager tasked with leading a project that will establish business continuity management practices for a major retail coffee chain. The project’s sponsor has just informed Polly that due to a major health safety issue discovered, all resources will be pulled from her project for an indefinite amount of time. In this scenario, Polly’s project has just been terminated due to what type of project ending?

    1. Addition
    2. Starvation
    3. Integration
    4. Extinction
  12. Polly is a project manager tasked with leading a project that will establish business continuity management practices for a major retail coffee chain. The project’s sponsor has just informed Polly that due to a major health safety issue discovered, all resources will be pulled from her project for an indefinite amount of time. What is Polly likely to do next?

    1. Validate the health safety issue to ensure that resources are being used appropriately
    2. Archive all project documentation and release the resources immediately
    3. Perform closure activities by carrying out the Close Project or Phase process
    4. Refuse to cancel the project, since business continuity is critical to the success of the company
  13. The Close Project or Phase process belongs to which project management Knowledge Area?

    1. Project Procurement Management
    2. Project Integration Management
    3. Project Closure Management
    4. Project Scope Management
  14. Beans by the Dozen is a company that ships precooked beans to restaurants in the western United States. Recently, the company has decided to expand their operation to the northern regions of the country. Ben, the project manager, confirmed that the vendor has recently completed all deliverables outlined within the statement of work and passed a recent audit. He has just closed out the contract and completed the other major deliverables of the project. Which document is Ben likely to use as a guide to ensure that project success criteria have been met?

    1. Milestone list
    2. Project management plan
    3. Project charter
    4. Procurement management plan
  15. A project manager of a real-estate firm has just been notified that her project has come to an end as a result of resources redirected to work on other projects deemed to be of higher priority. In this scenario, the project has been terminated due to what type of project ending?

    1. Addition
    2. Starvation
    3. Integration
    4. Extinction
..................Content has been hidden....................

You can't read the all page of ebook, please click here login for view all page.
Reset
3.138.114.132