THE PMP® EXAM CONTENT FROM THE CLOSING THE PROJECT PERFORMANCE DOMAIN COVERED IN THIS CHAPTER INCLUDES THE FOLLOWING:
Closing is the final process group of the five project management process groups and accounts for 7 percent of the questions on the PMP® exam. The primary purpose of Closing is to formally complete the project, phase, or contractual obligations. Finalizing all of the activities across the project management process groups accomplishes this.
By the end of the process that makes up the Closing process group, the completion of the defined processes across all of the process groups will have been verified. Don’t forget that the closeout preparations begin early in the project with the clear and well-defined success criteria of the project.
All projects must be formally closed out regardless of the reasons for closure (such as successful completion or early termination). According to the PMBOK® Guide, the following typically occurs during formal closing of the project or project phase:
These activities are carried out through a single process called Close Project or Phase.
The Close Project or Phase process is concerned with finalizing activities necessary to complete a project, phase, or contract; this includes gathering project records and disseminating information to formalize the acceptance of the product, service, or result. The process belongs to the Project Integration Management Knowledge Area. Here are additional notes about the process you should know:
According to the PMBOK® Guide, every project requires closure, and the completion of each project phase requires project closure as well. The Close Project or Phase process is performed at the close of each project phase and at the close of the project.
Figure 9.1 shows the inputs, tools and techniques, and outputs of the Close Project or Phase process.
For the exam, know the eight inputs of the Close Project or Phase process:
Project Charter The project charter contains the success criteria and other approval requirements necessary to close out a phase or project.
Project Management Plan For a project to be considered closed, the project management plan will be reviewed by the project manager to ensure completion of the deliverables and that all objectives of the project have been met.
Project Documents Several project documents can be referenced to validate that closure requirements have been met. According to the PMBOK® Guide, the following are examples of documents that may be referenced:
Accepted Deliverables Accepted deliverables are an output of the Validate Scope process. This input is necessary to determine whether all deliverables have been successfully completed.
Business Documents Business documents typically referenced include the business case, which contains the cost benefit analysis and business need being satisfied, and the benefits management plan, which notes when benefits are expected to be achieved.
Agreements Agreements become a necessary input to the process, since it’s through this process that procurement activities are finalized. Agreements contain the terms and conditions related to contract closure.
Procurement Documentation According to the PMBOK® Guide, procurement documentation is collected, indexed, and filed through the Close Project or Phase process. Procurement documentation typically includes the following:
Organizational Process Assets The following organizational process assets are typically used in this process:
The Close Project or Phase process has three tools and techniques: expert judgment, data analysis, and meetings.
Expert Judgment Subject matter experts can help ensure that the process is performed according to the organization’s standard and to project management standards. Experts typically include other project managers, the project management office, and organizations such as PMI® or other technical organizations that publish standards and resources.
Data Analysis Analytical techniques may be used to ensure that closure activities are ready to be performed and are performed correctly. Regression analysis and trend analysis are two examples of techniques provided by the PMBOK® Guide, as well as document analysis and variance analysis. These data analysis techniques help teams gather lessons learned to improve the performance on projects taken on in the future.
Meetings Meetings are often used as a means of bringing experts together to validate that deliverables have been accepted. Other uses of meetings at this stage include transferring knowledge, capturing lessons learned, and celebrating successful closure of a phase or project. Meetings may occur in a variety of formats, such as in person or virtual.
The four outputs that result from carrying out the Close Project or Phase process are as follows:
Final Product, Service, or Result Transition Final product, service, or result transition refers to the acceptance of the product and the turnover to the customer or into operations. This is where information is distributed that formalizes project completion.
Final Report The project’s final report includes an overall summary of how the project has performed. According to the PMBOK® Guide, it may include things such as these:
Project Documents Updates Any and all project documents may be updated as a result of carrying out this process. One document, in particular, that is important is the lessons learned register.
Organizational Process Assets Updates The following organizational process assets are typically updated as a result of the Close Project or Phase process:
The acceptance and turnover of the product to the customer or into operations typically involves a formal sign-off indicating that those signing accept the product of the project. This occurs as a result of carrying out the Close Project or Phase process, which was discussed earlier in this chapter.
Aside from the Closing process, there are a few additional items to note about the Closing process group and finalizing project closure. To start, project or phase closure is carried out in a formal manner and requires that financial, legal, and administrative closure be obtained. This is important to communicating formal closure and to ensuring that no further liability exists after the project has been completed.
It’s important to note that a project can move into the Closing process group for several reasons:
Aside from these common reasons that result in a project moving into the Closing process, there are four formal types of project endings that you should be familiar with: addition, starvation, integration, and extinction.
Addition A project that evolves into ongoing operations is considered a project that ends because of addition, moving into its own ongoing business unit. Once it experiences this transition, it no longer meets the definition of a project.
Starvation Starvation occurs when resources are cut off from a project prior to the completion of all the requirements. This results in an unfinished project. Starvation often occurs as a result of shifting priorities, a customer’s cancellation of an order or request, the project budget being reduced, or key resources quitting.
Integration Integration occurs when the resources of a project (such as people, equipment, property, and supplies) are distributed to other areas in the organization or are assigned to other projects. In other words, resources have been reassigned or redeployed, causing an end to the project.
Extinction Extinction occurs when a project has completed and stakeholders have accepted the end result. This is the best type of ending because the project team has completed what they set out to achieve.
In all cases, if a project ends early, it’s important to retain good documentation that describes why the project ended early. Performing a project review in these cases is important to retaining key details and specifics regarding why a project ended before all requirements were completed.
Another notable piece of information involves stakeholder influence and cost trends that occur during project closure. Stakeholders tend to have the least amount of influence during the Closing process, while project managers have the greatest amount of influence. Costs are significantly lower during the Closing process because the majority of the project work and spending has already occurred.
As part of administrative closure, resources will need to be released and the administrative closure procedures carried out.
Although releasing project team members is not an official process, you will release your project team members at the conclusion of the project, and they will go back to their functional managers or be assigned to a new project if you’re working in a matrix-type organization. The release of project resources is addressed within the resource management plan, which is created through the Plan Resource Management process.
As you learned in Chapter 5, “Planning Project Resource, Communication, Procurement, Change, and Risk Management,” the resource management plan includes a section called “project team resource management,” which includes details of how resources will be defined, staffed, managed, and released. The resource management plan is a subsidiary plan of the project management plan. It typically addresses the release of resources (not just at the end of the project, but in general at any point within the project), outlines the method for resource release, and defines when resources are to be released.
Once resources are released, the costs of the resources are no longer charged to the project. The resource management plan helps mitigate human resource risks that may occur during or at the conclusion of the project.
Administrative closure procedures involve the following:
Figure 9.2 shows the elements of the administrative closure procedures.
As part of formally closing out a project, the project manager will need to create and distribute the final project report. As you saw in our review of the process outputs, this generally occurs as part of the Close Project or Phase process, where administrative details are addressed. The final project report should include all project closure–related details, project variances, and any issues. The project manager should ensure that final project status is distributed to the stakeholders.
One of the recurring themes communicated across the PMBOK® Guide is the proactive nature of the project manager, expressed by their actions. An example of being proactive is documenting lessons learned as part of the organizational process assets and capturing them within the lessons learned register.
Documenting lessons learned, as mentioned previously, focuses on capturing what went well within the project, what didn’t go well, and what can be improved. Although lessons learned are recorded throughout the life of the project, holding a final review with the project team before the team is released at the end of the project is essential. This information can be captured through a comprehensive project review with stakeholders and then can be added to the organization’s knowledge base.
Documenting lessons learned occurs as part of the Close Project or Phase process, through the organizational process assets updates output.
As part of the Close Project or Phase process, project documents are archived. This occurs through the organizational process assets updates output, which makes the historical documents available for future reference and use. Archiving project documents provides the following benefits:
According to the PMBOK® Guide, project success is measured by the following criteria:
Customer satisfaction is an important goal you’re striving for in any project. If your customer is satisfied, it means you’ve met their expectations and delivered the product or service as defined within the planning processes. Customer satisfaction can be measured through quality management, which in part is concerned with making sure that customer requirements are met. This is done through understanding, evaluating, defining, and managing customer and stakeholder expectations.
As Figure 9.3 illustrates, modern quality management achieves customer satisfaction in part by ensuring that the project accomplishes what it set out to do (conformance to requirements) and that it satisfies real needs (fitness for use).
The Closing process group consists of a single process that works toward closing out the project or project phase. Before closing out the project, the project manager must first make sure that the project has met its objectives and accomplished what it set out to achieve. The Closing process group is also concerned with the following objectives:
Figure 9.4 reflects the objectives of the Closing process group through several key questions that the project manager should ask before considering the project fully closed.
Next, we’ll go through the Closing process reviewed in this chapter.
A project closeout cannot occur without first finalizing all project or phase activities. The Close Project or Phase process from within the Project Integration Management Knowledge Area is responsible for making this happen. Figure 9.5 shows what occurs within this process. The accepted deliverables are used to verify that the project or the project phase has accomplished what it needed to.
Keep in mind that all procurement contracts must be completed and closed out before the project itself can close. Any loose ends or work on the vendor’s end must be finalized as part of closing activities. You may recall that contract closure occurs through the Control Procurements process, part of the Monitoring and Controlling process group, and that all procurement activities are finalized through the Close Project or Phase process.
The Close Project or Phase process is also responsible for administrative closure of the project or project phase. The result is the transition to the customer of the final product, service, or result that the project created.
Before a project can be fully closed, all of the project documents must be archived within the organizational process assets. As you may recall, this includes all of the project files, any closing documents, and historical information. The historical information is archived within the lessons learned knowledge base, which will be a valuable asset to future projects.
All of the following are inputs of the Close Project or Phase process except:
A project manager of a travel excursion company is currently working on confirming that all project deliverables have been successfully completed to transfer the project to the customer. What process is the project currently in?
When closing out a project or project phase, which of the following tools and techniques can be used to ensure that closure has been performed to the appropriate standards?
The Close Project or Phase process accomplishes all of the following except:
While conducting project closure activities, a relatively new project manager of a whiteboard production company becomes confused as to how the organization verifies that the existing criteria have been met. The project manager has found that some of the procedures followed by the organization are different from the procedures used in previous companies she’s worked for. Where can the project manager go to clarify the procedures for verifying that the exit criteria have been met?
All of the following are tools and techniques of the Close Project or Phase process except:
A project manager was in the midst of trying to resolve a dispute with one of the project’s largest vendors. The issue revolved around the responsibility of the vendor to comply with changes to the scope. Although this was addressed in the contract, the vendor felt that the scope changes were much larger than the scope of the contract itself. What would be the best way to resolve the dispute?
Project managers have the greatest amount of influence during which stage of the project?
Resource release criteria can best be found in which plan?
A major deliverable has just been signed off by the sponsor. What is the project manager likely to do next?
Polly is a project manager tasked with leading a project that will establish business continuity management practices for a major retail coffee chain. The project’s sponsor has just informed Polly that due to a major health safety issue discovered, all resources will be pulled from her project for an indefinite amount of time. In this scenario, Polly’s project has just been terminated due to what type of project ending?
Polly is a project manager tasked with leading a project that will establish business continuity management practices for a major retail coffee chain. The project’s sponsor has just informed Polly that due to a major health safety issue discovered, all resources will be pulled from her project for an indefinite amount of time. What is Polly likely to do next?
The Close Project or Phase process belongs to which project management Knowledge Area?
Beans by the Dozen is a company that ships precooked beans to restaurants in the western United States. Recently, the company has decided to expand their operation to the northern regions of the country. Ben, the project manager, confirmed that the vendor has recently completed all deliverables outlined within the statement of work and passed a recent audit. He has just closed out the contract and completed the other major deliverables of the project. Which document is Ben likely to use as a guide to ensure that project success criteria have been met?
A project manager of a real-estate firm has just been notified that her project has come to an end as a result of resources redirected to work on other projects deemed to be of higher priority. In this scenario, the project has been terminated due to what type of project ending?
3.138.114.132