Notification of agreed extension to period for reply |
13.5 |
Notification |
Project Manager
|
Instruction to change Scope or a Key Date |
14.3 |
Instruction D/M |
Project Manager
|
Notification of ‘cost/time/quality’ early warning matters |
15.1 |
Notification M |
PM/Contractor
|
Notification of other early warning matter |
15.1 |
Notification D |
PM/Contractor
|
Instruction to attend early warning meeting |
15.2 |
Instruction D |
PM/Contractor
|
Revise Early Warning Register to record early warning meeting |
15.4 |
Record |
Project Manager
|
Notification of an ambiguity or inconsistency |
17.1 |
Notification |
Project Manager
|
Instruction to resolve the ambiguity or inconsistency |
17.1 |
Instruction M |
Project Manager
|
Notification of illegal or impossible requirements |
17.2 |
Notification |
PM/Contractor
|
Instruction as to how to deal with prevention event |
19.1 |
Instruction |
Project Manager
|
Instruction to remove an employee |
24.2 |
Instruction |
Project Manager
|
Acceptance of Subcontractor |
26.2 |
Acceptance |
Project Manager
|
Acceptance of Subcontract |
26.3 |
Acceptance |
Project Manager
|
Completion Certificate |
30.2 |
Certificate |
Project Manager
|
Acceptance of programme |
31.3 |
Acceptance |
Project Manager
|
Notification of non-acceptance of programme |
31.3 |
Notification |
Project Manager
|
Instruction to stop or not to start work |
34.1 |
Instruction |
Project Manager
|
Take over Certificate |
35.4 |
Certificate |
Project Manager
|
Instruction to submit quotation for acceleration |
36.1 |
Instruction |
Project Manager
|
Instruction to search for defects |
43.1 |
Instruction |
Supervisor
|
Notification of defects |
43.2 |
Notification |
Supervisor/Contractor
|
Defects Certificate |
44.3 |
Certificate |
Supervisor
|
Notification of extension to defects correction period |
44.4 |
Notification |
Project Manager
|
Acceptance of quotation to accommodate defect |
45.2 |
Acceptance |
Project Manager
|
Instruction to change Scope, Prices and Completion Date |
45.2 |
Instruction |
Project Manager
|
Assessment of amount of money due |
50.1 |
Assessment |
Project Manager
|
Payment Certificate |
51.1 |
Certificate |
Project Manager
|
Notification of compensation event |
61.1 |
Notification |
Project Manager
|
Instruction to submit quotation for compensation event |
61.2 |
Instruction |
Project Manager
|
Notification of failure to give early warning |
61.5 |
Notification |
Project Manager
|
Notification of correcting compensation event effect |
61.6 |
Notification |
Project Manager
|
Instruction to submit alternative quotations |
62.1 |
Instruction |
Project Manager
|
Acceptance of a quotation |
62.3 |
Acceptance |
Project Manager
|
Instruction to submit a revised quotation |
62.3 |
Instruction |
Project Manager
|
Notification of PM’s own assessment |
62.3 |
Notification |
Project Manager
|
Notification of extension of quotation period |
62.5 |
Notification |
Project Manager
|
Notification of PM’s assessment of compensation event |
64.3 |
Notification |
Project Manager
|
Instruction to deal with objects of value/historic interest |
73.1 |
Instruction |
Project Manager
|
Acceptance of insurance details |
84.1 |
Acceptance |
Project Manager
|
Termination Certificate |
90.1 |
Certificate |
Project Manager
|
Notification of default |
91.2 |
Notification |
Project Manager
|