What is the RIBA Plan of Work?
Why is a major update of the RIBA Plan of Work necessary?
What are the main changes to the RIBA Plan of Work?
How does the RIBA Plan of Work 2013 respond to the issues raised?
How does the RIBA Plan of Work 2013 differ from the 2007 Plan?
The RIBA Plan of Work 2013 Overview publication, available from www.ribaplanofwork.com, explains the rationale behind the eight project stages and eight task bars as well as explaining the logic behind the defined terms and newly introduced aspects of the RIBA Plan of Work 2013.
In addition to providing further details on these subjects, this Guide to Using the RIBA Plan of Work 2013:
It is a valuable document for any party involved in a building project during the briefing, design, construction or in-use stages, including clients, contractors and design team members. As well as providing an insight into the thinking behind the RIBA Plan of Work 2013, this guide also allows those who embrace the new RIBA Plan of Work to utilise it more effectively by understanding the reasoning behind the many issues that have been addressed during its development.
The importance of considering and successfully assembling the project team is covered in Chapter 3 but the themes are dealt with in greater detail in the RIBA publication Assembling a Collaborative Project Team, which has been developed in parallel with this guide.
Since its conception in 1963, the RIBA Plan of Work has been the definitive model for building design and construction processes in the UK, and has also exerted significant influence internationally. The RIBA Plan of Work framework has served both the architects’ profession and the wider construction industry well.
The initial Plan of Work was conceived as a ‘Plan of Work for Design Team Operations’ and consisted of 12 stages and three columns that set out ‘the purpose of work and decisions to be reached at each stage’, ‘tasks to be done’ and ‘the people directly involved’. This Plan of Work was updated in 1967 and again in 1973. In 1998 a major revamp was undertaken. The 12 stages were reduced to 11 by the deletion of the ‘Completion’ stage and, although the general thrust of each stage remained the same, only two stages retained their original titles. The 1998 RIBA Outline Plan of Work defined ‘the work stages into which the process of designing building projects and administrating building contracts may be divided’. This Plan acknowledged that some variations to the work stages apply to design and build procurement, although it did not set out what these variations might be. This Plan was updated in 2007, with five stages renamed and additional descriptions of the key tasks added along with the Office of Government Commerce (OGC) Gateways, which were the old Government ‘checkpoints’, now renamed ‘UK Government Information Exchanges’. More importantly, guidance was added on how the Plan might be adapted to different forms of procurement, although the Outline Plan of Work continued to relate to traditional procurement.
This brief synopsis of the Plan of Work’s history underlines its continual evolution in response to changing trends. The RIBA Plan of Work 2013 represents the next significant evolutionary stage of the RIBA Plan of Work.
This Guide to Using the RIBA Plan of Work 2013 sets out the reasons behind the fundamental changes, clarifies the amendments to the project stages, details changes to the key tasks to be undertaken and provides additional narrative on the core subjects that must be considered in relation to the RIBA Plan of Work 2013. More importantly, this guide sets out how the RIBA Plan of Work 2013 can be used to assemble an effective project team. This shift in emphasis from the design team to the project team is, in itself, one of the major cultural changes that the RIBA Plan of Work 2013 acknowledges and reinforces.
The principal purpose of the RIBA Plan of Work 2013, in line with its predecessors, is explaining to clients the circular processes involved in a building project, although these are expanded and adjusted to relate to the briefing, design, construction, maintenance, operational and in-use processes involved in a building project. Within this explanatory framework the stages continue to set particular and specific boundaries for those involved in the process. While the RIBA Plan of Work is devised by the RIBA, it is intended for use by all the parties involved in a project.
The RIBA Plan of Work has continued to evolve in response to changing processes within the broader construction industry. For example, the RIBA Plan of Work 1998 acknowledged the reduced use of bills of quantities by amending Stage G to Tender Documentation and redefining the nature of Stage E. In a similar vein, the RIBA Plan of Work 2013 has been created in response to a number of drivers. The eight most important factors necessitating a major review of the RIBA Plan of Work are considered below:
The RIBA Plan of Work is not a contractual document. Schedules of services and other contractual documents are used for contractual purposes.
On first sight, the RIBA Plan of Work 2013 appears to be a radical shift from the RIBA Outline Plan of Work 2007 (see the fold-out template at the back of this book). This is not the case. The RIBA Plan of Work 2013 maintains the tradition of explaining to clients how the briefing, design, construction, maintenance, operation and in-use processes work by mapping key activities against project stages. It still specifies the core activities undertaken at each stage. While the concept is the same, four key points need to be digested in order to understand the changes to the RIBA Plan of Work, before considering how it responds to the issues that have been highlighted:
Use of the Riba Plan of Work 2013
In this guide, capitalised terms indicate those terms defined under each stage and in the Glossary in the RIBA Plan of Work 2013 Overview (see Chapter 10 for a list of these terms).
In response to the points raised above on the necessity for redrafting, the RIBA Plan of Work 2013:
New Schedules of Services for the RIBA suite of appointment documents have been produced in parallel with the RIBA Plan of Work 2013. These, along with this guide and the new RIBA publication Assembling a Collaborative Project Team, provide the tools necessary to successfully build a project team during Stage 1.
While the RIBA Plan of Work 2013 is the second major evolutionary change to the RIBA Plan of Work, it is important realise that it is not a fundamental shift from the RIBA Outline Plan of Work 2007. To emphasise this point, the transition from the 2007 stages to the 2013 stages is mapped out in the new stage definitions on pages 20 to 35, and the defined terms that have been introduced to bring greater clarity to a number of core subjects are listed in Chapter 10. The rationale behind the new task descriptions, now referred to as task bars, is set out on pages 10 to 18. This section also defines how the variable elements of the task bars can be harnessed to generate a bespoke practice- or project-specific Plan of Work.
When considering fee proposals, the areas that have the most significant impact are the integration of tendering activities within each project stage and the additional coordination work required during Stage 3.
Before considering the eight task bars and eight stages (see Chapter 2) it is important to consider that the RIBA Plan of Work 2013 represents merely the tip of the iceberg. The process outlined in Chapter 3 for assembling a successful project team is not prescriptive but it does offer the opportunity to reinvigorate the documentation necessary to support a project and the processes of briefing, designing, constructing, maintaining, operating and using a building.
‘Is it possible for the RIBA Plan of Work 2013 to be “all things to all people” and useable on small and large projects alike?’
The consultation process undertaken by the RIBA during summer 2012 suggested that traditional procurement processes are used on most smaller projects. The RIBA Plan of Work 2013 allows a practice-specific Plan of Work to be generated, based on traditional or non-traditional procurement methods but derived from the same template format, facilitating flexibility within a consistent overall framework.
3.149.229.253