CHAPTER 14

Plan progressive delivery

 

14 Plan progressive delivery

Figure 14.1 illustrates the plan progressive delivery process within the MSP framework.

Images

Figure 14.1 Plan progressive delivery process within the MSP framework

14.1 Purpose

The purpose of the plan progressive delivery process is to build on the programme design. The process plans the programme, structuring the projects and other work into tranches of delivery to achieve the required capabilities and realize the benefits. It also confirms the programme justification before deciding whether to proceed with programme delivery.

14.2 Objectives

The objectives of the plan progressive delivery process are to ensure that:

the projects and other work involved to deliver the programme are planned

the tranches of delivery and intermediate landing points are defined

the delivery approach and ways of working are defined

the path to realizing benefits is planned

the approach to acquiring and managing the resources (needed to deliver the programme) is defined

the pace of delivery is aligned with the rate of change that operational areas can support.

14.3 Context

Planning progressive delivery is about understanding how the outcomes of benefit will be achieved through delivery of the programme’s projects and other work. This process ensures that the programme will deliver capability at an appropriate pace, maintaining an acceptable balance between delivery, transition, realization of benefits, and affordability.

Table 14.1 shows the inputs, activities, and outputs for the process.

Table 14.1 Inputs, activities, and outputs for plan progressive delivery

Inputs to the process

Activities

Outputs from the process

Approval to proceed

Vision statement

Target operating model

Benefit profiles

Benefits map

Programme strategy (latest version)

Risk register

Issue register

Decision register

Business case (latest version)

Programme plans (latest versions)

Validate required resources

Complete the programme strategy

Continue to develop and validate the programme plans:

delivery plan

benefits realization plan

stakeholder engagement and communications plan

assurance plan

financial plan

Confirm the business case

Prepare for the next process

Agree to proceed (or close)

Programme strategy (completed and approved)

Programme plans (completed and approved)

Business case (completed and approved)

Risk register

Issue register

Decision register

14.4 Activities

14.4.1 Validate required resources

The resources required during the plan progressive delivery process need to be confirmed, acquired, and established. As with the design the outcomes process, resources may include infrastructure, tools, equipment, and the team needed to carry out the required activities. Specialist skills may be needed for planning the programme and finalizing the business case. Where appropriate skills are unavailable in-house, they may be supplemented by external specialists.

14.4.2 Complete the programme strategy

The programme strategy aligns with existing organizational processes and governance. This enables effective decision-making and efficient communication flows among members of the programme team and stakeholders. Aspects of the programme strategy will have been developed in the previous processes (identify the programme, design the outcomes), but this activity validates, confirms, and finalizes the overall programme strategy, including the approaches to:

governance

stakeholder engagement

design

funding

delivery

resourcing

knowledge and learning

information

assurance

decision-making

issue resolution

risk response.

14.4.3 Continue to develop and validate the programme plans

The vision statement, target operating model, benefit profiles, and benefits map provide the basis for designing the projects and other work required to deliver new capabilities. Different options may be available for achieving improvements which need to be explored in terms of their timing, content, and associated risks and benefits. Some projects and other work may already be ongoing, and they will be adopted into the programme, while others will be new initiatives that the programme will deliver.

The following aspects of the programme need to be planned:

Delivery of new capabilities The programme’s projects and other work will need to be sequenced into tranches of delivery, showing their relative timescales and key dependencies. Detailed plans for the next tranche are required.

Benefits realization The timeframes for measuring benefits.

Stakeholder engagement and communications Activities for identifying, analysing, and engaging with stakeholders.

Assurance Programme monitoring and control, and independent assurance activities.

Finances Budgeting, monitoring, and measurement of cost and benefit.

These plans may be consolidated into a single overall document or maintained as separate stand-alone items. The programme plans cover the delivery of the entire programme; however, they are likely to contain more detailed information for the first (or next) tranche of delivery and less detail for subsequent tranches. Plans for each incremental progression will be refined every time this process is undertaken.

14.4.4 Confirm the business case

The business case will have started to emerge in the identify the programme process (as part of the programme brief) and been further developed in the design the outcomes process. The business case is finalized here as the arrangements for programme management and delivery are developed. When the information about the programme’s costs, benefits, timings, and risks are understood, the viability of the programme can be assessed and confirmed.

14.4.5 Prepare for the next process

The programme can now prepare for the first tranche of delivery. Planning for the next process may involve preparing to establish governance and specifying any physical equipment or infrastructure requirements. Subsequent tranches may require similar preparations.

According to the assurance plan, the programme documentation may be subject to an independent assurance review in order to gain objective confirmation that the business case is viable, the programme delivery is achievable, and the stated outcomes and benefits are realistic. This assurance needs to be completed before the decision is made to proceed with delivery.

14.4.6 Agree to proceed (or close)

Formal approval to proceed means that:

the SRO approves the programme business case and other documentation

the sponsoring group authorizes and commits to resource the first tranche of delivery

delivery of the programme can commence

if formal approval cannot be given, the programme will close.

14.5 Responsibilities

Table 14.2 shows a RACI chart for the activities in the process, split between the core MSP governance boards, supporting offices, and individual roles.

Table 14.2 RACI chart for plan progressive delivery

Img

14.6 Application of the themes in this process

Table 14.3 shows how the themes apply to the plan progressive delivery process.

Table 14.3 Application of the themes to the plan progressive delivery process

Theme

Application to plan progressive delivery process

Organization

Finalize programme and project structures

Confirm the governance approach

Confirm the stakeholder engagement approach

Develop the stakeholder engagement and communications plan

Design

Update the target operating model, if required

Refine and validate benefits

Justification

Finalize the business case

Develop the financial plan

Structure

Confirm the delivery approach

Identify projects and tranches of delivery

Develop the delivery plan, including the next tranche in detail

Develop the benefits realization plan

Knowledge

Confirm the approach to managing information and knowledge

Incorporate learnings into programme plans, and share more widely within the organization(s)

Assurance

Confirm the assurance approach

Develop the assurance plan

Decisions

Confirm the approach to decision-making and escalation paths

..................Content has been hidden....................

You can't read the all page of ebook, please click here login for view all page.
Reset
3.140.198.12