CHAPTER 18

Close the programme

 

18 Close the programme

Figure 18.1 illustrates the close the programme process within the MSP framework.

Images

Figure 18.1 Close the programme process within the MSP framework

18.1 Purpose

The purpose of the close the programme process is to end the programme in a controlled way, extracting as much value from the programme regardless of the reason for closing it. This includes ensuring that the investing organization(s) is ready to maximize the benefits to be realized from the completed programme work by continuing to measure the benefits and taking steps in BAU to minimize benefit erosion.

18.2 Objectives

The objectives of the close the programme process are to ensure that:

a final assessment of the programme is conducted to capture its achievements relative to those expected and any gaps

other governance structures assume accountabilities for residual benefits realization, risk management, and capability development activities

the impact of closure on stakeholders is understood and managed well

capabilities are fully integrated into BAU

the programme office and the supporting processes are decommissioned

resources are decommissioned (e.g. contractors, staff, or secondees)

evidence that supports future assurance activities is retained (e.g. external audit)

knowledge acquired during the programme is retained and lessons learned are put in place for subsequent programmes.

18.3 Context

Programmes are closed when the value of continuing is no longer justified by the sponsoring group because:

the work has been completed as planned

the outcome expectations are deemed to have been sufficiently achieved, leading to the mandate being fulfilled

other organizations (e.g. vendors, programmes, projects, or BAU) are deemed to be better suited to delivering the outcomes or objectives of the programme, leading to the mandate being substantially changed

programme resources are deemed to be better used elsewhere, leading to the mandate being withdrawn early.

Withdrawal of the programme mandate might happen either when new corporate strategies or priorities emerge, corporate funding for programmes has been reduced, the programme is lacking achievements, or the likelihood of significant achievement in the future is very low.

Table 18.1 shows the inputs, activities, and outputs for the process.

Table 18.1 Inputs, activities, and outputs for close the programme

Inputs to this process

Activities

Outputs from this process

End-of-tranche report

Risk register

Issue register

Decision register

Prepare for closure

Hand over residual work

Finalize programme information

Disband the programme organization and close

Confirmation of closure

Updated knowledge

18.4 Activities

18.4.1 Prepare for closure

To prepare for closure, the programme manager:

confirms that the programme is about to close (triggered by the formal approval to close)

ensures that stakeholders are notified (this will be in the stakeholder engagement and communications plan if the closure is planned)

evaluates programme performance to identify lessons to be learned (drawing from the end-of-tranche report).

18.4.2 Hand over residual work

The programme manager:

assesses delivery of the target operating model

hands over residual capability delivery to other programmes (if relevant)

hands over responsibility for ongoing benefits realization and associated risks and issues.

18.4.3 Finalize programme information

This activity is to ensure that programme information is up to date and stored or archived.

18.4.4 Disband the programme organization and close

Formal closure means that the SRO disbands the programme organization and agrees with the sponsoring group to close the programme.

18.5 Responsibilities

Table 18.2 shows a RACI chart for the activities in the process, split between the core MSP governance boards, supporting offices, and individual roles.

Table 18.2 RACI chart for close the programme

Img

18.6 Application of the themes in this process

Table 18.3 shows how the themes apply to the close the programme process.

Table 18.3 Application of the themes in the close the programme process

Theme

Application to close the programme process

Organization

Disband the programme organization

Design

Confirm the status of the operating model

Justification

Confirm the status of the business case (all costs and benefits accrued to date)

Structure

Close all projects and other work that were part of the programme, and hand over residual work

Knowledge

Ensure that the knowledge gained by the programme team is captured and made explicit as far as possible

Identify specific lessons for the organization to learn

Update all programme information

Assurance

Provide any assurance activities that are required by the sponsoring group before final closure of the programme

Decisions

Close issues and risks, and confirm the status of other decisions

Hand over any residual issues or risks as applicable

..................Content has been hidden....................

You can't read the all page of ebook, please click here login for view all page.
Reset
3.138.124.143