Practice Test 2225
61. Assume you are the portfolio manager for the leading toothpaste company.
As a major sporting event soon will be under way in which counties from
throughout the world will be participating, your company learned today that
some feel toothpaste may be used to conceal explosives. You want to ensure
your products are completely safe, and no tampering is possible so you
decide to add a component and announce it through a press release. This is
an example of a(n):
a. Structural risk
b. Execution risk
c. Unknown unknown
d. Need for a management reserve
62. Different stakeholders require involvement in governance activities at differ-
ent times in portfolio management. In your new camel milk portfolio, a new
venture for the dairy cooperative, phase- gate reviews should include repre-
sentatives from:
a. Engineering
b. Manufacturing
c. Research and development
d. Legal
63. Your portfolio stakeholders review a number of reports each month to moni-
tor the overall value of the value of the components to the business. One
report of interest shows the assigned resources to components and then
shows how much work is completed and how much is remaining with work
tracked in person days. Such a report is a:
a. Resource prioritization report
b. Funnel diagram
c. Histogram
d. Burn- down chart
64. You are working to ensure you identify how often the various stakeholder
groups require information about the status of the portfolio and how to best
provide it to them. You also decide to conduct a review of your analysis in
order to:
a. Ensure redundant information is not provided
b. Ensure consistent messages are delivered regardless of the frequency
c. Determine how the information will be stored and retrieved
d. Ensure all portfolio information is provided
226PfMP® Exam Practice Tests and Study Guide
65. Assume you are the portfolio manager for your natural gas distribution system
company. It is considering acquiring a transmission company in the same area
of the country, and this acquisition, once approved by regulatory authorities,
will broaden the portfolio enormously. You have organized the portfolio for
your company by categories, and this approach is benecial as it:
a. Enables appropriate balancing
b. Provides a way to use software easily in prioritization
c. Identies those components in greatest need of key subject matter
experts
d. Ensures components in each category have a common goal
66. As the portfolio manager, you and your team collect a variety of tangible
and intangible metrics to assess performance of the components in the portfo-
lio. Each component manager submits reports to the sponsor, who consolidates
them and sends them to you. You and your team then prepare a report for the
Portfolio Review Board. As portfolio management has evolved in your new prod-
uct development company in the past nine years, a metric now of interest is:
a. Internal rate of return
b. Net present value
c. Sustainability
d. Cycle time reduction
67. Having worked in the portfolio management eld for more than 10years,
you realize having an up- to- date roadmap is extremely useful as it promotes
portfolio management and shows the ‘to- be’ state in a way that is visually
appealing. The dependencies and integration of the components in the road-
map also inuence:
a. The portfolio organizational structure
b. The number of sub- portfolios in the organization
c. The portfolio processes to follow
d. The portfolio management plan
68. Previously, you were the portfolio manager for a consulting company, but
given the downturn in the economy and its decreased revenues, you applied
for and were offered the position of portfolio manager for a major pipeline
company. It has not implemented portfolio management before, and you
know a strategic plan is useful. You are nding its preparation to be more
difcult than when you did so at the consulting company because:
a. It is a completely new function
b. There are external environmental factors to consider
c. People require training in why portfolio management is needed
d. The company’s growth and ROI are strong
Practice Test 2227
69. Assume you are working to prepare your portfolio communications plan.
You have started the process of preparing your stakeholder analysis. You
found many stakeholders are unsure as to how their work ts into the over-
all portfolio and want information about it. This means:
a. You should set up a dashboard to portray the overall priorities in the
portfolio
b. A forecast of the portfolios direction would be helpful
c. The roadmap is useful to show the portfolios structure
d. An assessment of the value of the portfolio should be part of the plan
70. The dynamic nature of portfolio management makes it difcult to imple-
ment. If the organization has dened processes to follow and an engaged
Portfolio Review Board that meets regularly, components will be added to
the portfolio, and others will be terminated or deferred. When components
are removed from the portfolio, the organization then:
a. Revises its component categories
b. Reallocates resources
c. Revises the portfolio performance plan
d. Revises the portfolio strategic plan
71. It is important to have a dened process in place to determine the priority
of each component in the program for many reasons, one of which is to:
a. Guide talent development
b. Minimize risks
c. Understand strategic objectives
d. Document assumptions and constraints
72. Assume you have completed your risk probability and impact assessment.
Since you work in a non- regulatory environment and also one in which the
potential effect of legislation is low on your portfolio’s components, these
types of risks probably do not require additional work. However, a best
practice is to:
a. Continue to monitor them if the strategy changes
b. Conduct some scenario analyses to determine whether or not further
analysis is required
c. Realize further investment is not needed on these risks
d. Maintain them on a watch list
228PfMP® Exam Practice Tests and Study Guide
73. It is estimated that billions of dollars are lost annually because of software
projects that cannot be completed or on other software projects that are
completed but later are found to have effects. Often the problem is the
lack of capability of the assigned resources to do the work, and defects are
identied at the time the software is to be delivered. Because of the costs
involved with resource misallocations, your company decided it would
develop an economics- based model it then could sell to others to best allo-
cate resources to software projects. Such an approach:
a. Will not be helpful unless agile development will be used
b. Can support resource capacity analysis
c. Can model scenarios to use resources based on priorities
d. Will be useful in dependency analysis
74. As a portfolio manager in an organization that is in the process of formal
implementation of portfolio management, you reviewed a number of prioriti-
zation models and software packages that could be used. You then decided
on a scorecard approach focusing on alignment to strategy, ROI, risk, and
dependencies. This approach:
a. Is documented in the portfolio strategic plan
b. Is documented in the portfolio performance plan
c. Receives stakeholder buy in from the communications plan
d. Is part of the governance model
75. Your company has embraced portfolio management. Each business unit has
a Portfolio Review Board that meets monthly for detailed reviews and pri-
oritization, and the company’s executives meet quarterly to prioritize at the
corporate level. There are numerous artifacts to maintain, especially these
governance decisions. As the corporate portfolio manager, you decided to:
a. Establish a portfolio management information system
b. Establish a portfolio management portal
c. Maintain a governance decision register
d. Establish a portfolio knowledge management system
76. Assume you are considering a proposed project to be part of your portfolio.
But, when the Portfolio Review Board met, it realized it could not consider it as
overhead because of its size, and it was not time to treat it as a capital invest-
ment because of nancial constraints in your oil company. It also is considered
to have many risks associated with it. You decide the best approach is to:
a. Set it up to treat the project as an option
b. Inform the project’s sponsor to resubmit it at a later time
c. Prepare a NPV analysis
d. Use probability and decision- tree analyses
Practice Test 2229
77. Assume you have decided to use interviews and questionnaires to help
identify risks on an ongoing basis and to maintain a risk register. You plan
to have a report available on the top ten risks that might affect the portfolio,
either positively or negatively, and assess the probability and impact of the
ten on this list. The list will change, and you then will update members of
the Portfolio Review Board and other interested stakeholders. In your portfo-
lio risk plan, you should:
a. Document this approach in the methodology section
b. Use subject matter experts to validate your approach before you prepare
your risk plan
c. Select risks to be in the top ten with at least one from your ve risk
categories
d. Determine which risks will arise from various situations as part of your
approach
78. Your goal as the portfolio manager is to optimize and balance the portfolio
for greatest performance and also overall value delivery. This means you
need to:
a. Follow the portfolio strategic plan
b. Communicate effectively with stakeholders at all levels
c. Set up appropriate criteria to rank components
d. Create the portfolio mix with the greatest potential
79. It is easy to focus on the benets programs will deliver to the organization,
and the deliverables projects will produce. Many organizations do not have
a clear understand of all of the programs and projects under way, and many
people do not want to disclose some ‘pet’ projects that are under way as
they believe they are breakthrough initiatives for the company. Your organi-
zation lacks such an inventory and requires one as the executive team man-
dated that a portfolio management process be followed. The executives plan
to meet monthly to determine whether or not new components should be
added, and others deferred or terminated. The overall objective is to ensure:
a. Components are focused on alignment to strategic objectives
b. The portfolio strategy focuses on preventing poor return on investment
in the components that are pursued
c. Component benets are emphasized along with deliverables
d. The emphasis continues on the triple constraint as new components are
pursued
..................Content has been hidden....................

You can't read the all page of ebook, please click here login for view all page.
Reset
3.15.137.213