Chapter 41. Top-10 Risks List

image with no caption

The Top-10 Risks List is a simple tool that helps to monitor a software project's risks. The list consists of the 10 most serious risks to a project ranked from 1 to 10, each risk's status, and the plan for addressing each risk. The act of updating and reviewing the Top-10 Risks List each week raises awareness of risks and contributes to timely resolution of them.

Efficacy

Potential reduction from nominal schedule:

None

Improvement in progress visibility:

Very Good

Effect on schedule risk:

Decreased Risk

Chance of first-time success:

Excellent

Chance of long-term success:

Excellent

Major Risks

None

Major Interactions and Trade-Offs

  • Can be used in combination with virtually any other practice.

For more on top-10 risks lists, see Top-10 Risks List in Risk Control.