The Top-10 Risks List is a simple tool that helps to monitor a software project's risks. The list consists of the 10 most serious risks to a project ranked from 1 to 10, each risk's status, and the plan for addressing each risk. The act of updating and reviewing the Top-10 Risks List each week raises awareness of risks and contributes to timely resolution of them.
Efficacy
Potential reduction from nominal schedule: | None |
Improvement in progress visibility: | Very Good |
Effect on schedule risk: | Decreased Risk |
Chance of first-time success: | Excellent |
Chance of long-term success: | Excellent |
Major Risks
None
Major Interactions and Trade-Offs
Can be used in combination with virtually any other practice.
For more on top-10 risks lists, see Top-10 Risks List in Risk Control.