Index

accepting risk, 170

accountability, in work breakdown structure (WBS), 52, 53

active listening, 160

activities

in crashing the schedule, 92, 93

defining, 61–62

defining relationships between, 65–67

dependencies between, 64–65

estimating, 71–86

overlapping, 93

sequencing, 52, 62–69

activity-on-node, 62–63

actual cost (AC), 139–140, 143

actual cost of work performed (ACWP), 139–140, 143

addition, termination by, 179

administrative assumptions, 41

administrative closure, 181, 185

administrative dependencies, 64

affinity diagrams, for work breakdown structure (WBS), 59

agendas, meeting, 155

analogous (historical) estimates, 74

assessment of risk, 166–168

asset availability assumptions, 42

assumptions

in estimating activities, 73

in scope statement, 41–42, 45

types of, 41–42

asynchronous communication, 149–150

authorization process, 18

avoiding risk, 169

back-end loaded budgets, 103

backward pass, 89–90

baseline

approved baseline plan, 117

baseline schedule, 123, 124, 126

as control point, 138

current baseline plan, 121

defined, 123

project plan as, 2

scope, 59–60

updating and communicating, 128

benefits, expected, 19

bottom-up estimates, 75, 83

brainstorming, for work breakdown structure (WBS), 58

budget at completion (BAC), 142

budgeted cost of work performed (BCWP), 139

budgeted cost of work scheduled (BCWS), 139

budgeting, 12–13, 96

budget plan, 111

business case

defined, 18

for undertaking project, 18–20

change

change control, 133–134

defined, 133

sources of, 134–135

change control, 133–134

change log, 183–184

change management forms, 183–184

charter, project, 24, 106

checklists

interview, 158–159

project closure, 184

for work breakdown structure (WBS), 58

clients

acceptance of deliverable, 176, 182

in authorization process, 18

specifications and, 39

as stakeholders, 18

closing a project, see project closure

collecting requirements, project scope, 28–34

communications, 146–150

asynchronous, 149–150

communication matrix in, 113

communication plan in, 112–113

communications management and, 13

effect of message in, 147–149

factors in, 146–147

synchronous, 149–150

conditional diagramming method, 63

conditions, project, 67

confirming, in directing project teams, 153

constraints

examples of, 40

in scope statement, 34–35, 37, 40

contingency

contingency plans and, 167

defined, 85

in estimates, 84–85

reserves and, 36–37, 135, 170

contract incentives, 91–92, 103

contract types, 36, 169

contractual closure, 182

controlling

baseline as control point, 138

importance of, 117, 118

nature of, 10, 11–12, 118

tools for, 117

see also project control process

convention, dependencies of, 65

coordinating, 11

corrective actions, in data analysis, 132

cost constraints, 34–35, 37

cost management, 12–13

cost performance index (CPI), 140–141

cost-plus contracts, 169

costs, estimated, 19, 27

cost variance (CV), 140

CPM (critical path method), 87–90, 108

crashing the schedule, 91–93

activities in, 92

project objectives in, 92–93

resources in, 91–92

creativity, in problem solving, 152

creativity tools, in planning phase, 31–32

critical path method (CPM), 87–90, 108

critical success factors, 45

defining project, 18

functional managers and, 23

critical success measures, 18

cultural confrontations, 150–151

customers

in authorization process, 18

specifications and, 39

as stakeholders, 18

data analysis, 131–132

corrective actions, 132

sanity check, 131

significance test, 132

deliverables

acceptance by client, 176, 182

review in determining project status, 122

turnover in project closure, 181

delivering, in directing project teams, 152–153

demand function, 63

dependency relationships, 62–63, 64–65, 107, 123, 127, 130

directing project teams, 9, 152–153

distribution of estimates, 76–78

distribution-of-estimates guideline, 78

duration-based activities, 84

duration estimates, 84, 107, 110, 123

early finish, 88–89

early start, 88–89

earned value analysis, 138–143

indices and ratios in, 140–143

key values in, 138–139

in measuring work accomplished, 139–140

earned value (EV), 139

effectiveness, improving meeting, 156–157

effort/work effort, 179

encoding, in communication process, 149

end users, specifications and, 39

enterprise portfolio management, 7

enterprise skills inventory, 96

estimated time, 83

estimate to complete (ETC), 142

estimating activities, 71–86

building contingency in estimates, 84–85

duration-based estimates, 84, 107, 110, 123

guidelines for estimating, 75–80

improving estimates over time, 86

methods of estimating, 74–76

plan parameters, 71–72

precision of estimates, 83–84

resource-based estimates, 84

risk in estimating process, 80–83, 85

steps in, 73–74

work breakdown structure (WBS) in, 72–73

estimation at completion (EAC), 143

evaluating, in managing project teams, 153–154

exclusions, in scope statement, 39

executing projects, 117–135

change control, 133–134

collecting project information, 122

data analysis, 131–132

labor hours, 127–131

monitoring project work, 121

nature of, 11, 117

project control process, 118, 119–121, 137–143

project kick-off meeting, 118

project meetings, 118–119

schedule importance, 122–127

sources of change, 134–135

exit criteria, 177–178

expert judgment, in planning phase, 30

extinction, termination by, 179

fast-tracking, 92

financial records, in administrative closure, 181, 185

finish-to-finish (FF) activities, 65

finish-to-start (FS) activities, 65

fixed-price contract, 36, 169

flexibility, of work breakdown structure (WBS), 54–57

float, 90

focus groups, 30

following up

in administrative closure, 181

after interviews, 161

after meetings, 156

forward pass, 88–89

free float, 90

front-end loaded budgets, 103

functional decomposition, 51–52

functional groups, in estimation activities, 76

functional managers

and critical success factors, 23

in estimating activities, 76

fuzzy requirements, in planning phase, 33–34

Gantt charts, 107, 123, 125

gap analysis, in planning phase, 30–31

goals

defining project, 21, 45

goal breakdown structure, 20–23

senior managers and, 23

government agencies, 38

growth of organization, 19

Guide to the Project Management Body of Knowledge (PMBOK® Guide), 11–13, 27–28

human productivity, in estimating activities, 79

human resources management, 13

ideal estimator, 78

incentives, contract, 91–92, 103

index cards, for work breakdown structure (WBS), 59

industry-specific professional/trade associations, 38–39

initiating, 17–24

authorization process, 18

case for undertaking project, 18–20

goal breakdown structure in, 20–23

nature of, 11

project charter and, 24, 106

project closure, 182–183

integration

integration management, 12

termination by, 178–179

interviews, 158–161

active listening in, 160

checklist for, 158–159

conduct during, 160–161

consolidating information after, 161

general questions for, 159–160

organizational questions for, 159–160

in planning phase, 30

technical questions for, 159

kick-off meeting, 118

knowledge areas, in project management, 12–13

labor hours, 127–131

lag relationships, 65–67

last dollar, 36–37

late finish, 36–37, 88, 89–90

late start, 88, 89–90

leading project teams, 145–152

communication in, 146–150

leadership skills and, 146, 148

motivation in, 148, 150–151

problem solving in, 148, 151–152

project management skills and, 147

lead relationships, 65, 67

lessons learned, 183–185

level of detail, in estimating activities, 76

listening, active, 160

logic network diagrams, see network diagrams

lump-sum contract, 36, 169

macro-level assumptions, 42

maintenance and warranties, 181

management by walking around, 122

management reserves, 36–37, 135, 170

managing project teams

categories of management processes, 11–12

components of, 153–154

management, defined, 9

mandatory (hard) dependencies, 64

Mantel, Samuel J., Jr., 178–180

meetings, 154–157

conducting, 155–156

following up after, 156

improving effectiveness of, 156–157

planning for, 155

project, 118–119

project kick-off, 118

status, 122

types of, 154

see also interviews

Meredith, Jack R., 178–180

message, in communication process, 147–149

milestone plan, 111

milestones, 51–52, 62, 111

mind mapping, for work breakdown structure (WBS), 59

mission, defining project, 18, 20

mitigating risk, 169–170

mitigation plans, 169–170

monitoring

components of, 121

nature of, 11–12

motivation, 148, 150–151

network diagrams, 52

critical path method in, 87–90, 108

nature of, 62–64

sample, 66, 68, 69

objectives

in crashing the schedule, 92–93

defining project, 18

ensuring project requirements are met, 177–178

project, 92–93

of project closure, 176–177

in scope statement, 34–37, 45

SMART, 32–33

observing, in managing project teams, 153–154

operational dependencies, 64

order-of-magnitude estimates, 83

organizational assumptions, 41

organizational breakdown structure, 111

organizational culture

contingency in estimates and, 85

cultural confrontations, 150–151

organization plan, 111–112

organizing, 10

overlapping activities, 93

overly optimistic estimator, 78

ownership, of estimates, 75–76

parallel activities, 92

parametric estimates, 74–75

path float, 90

percent complete, 127, 129

performance

earned value analysis in measuring, 138–143

performance reporting, in project closure, 181, 186

pessimistic estimates, 76–77

planned value (PV), 138–139, 141

planning, 27–46

collecting requirements, 27, 28–32

defining activities, 61–62

in directing project teams, 9, 152–153

estimating activities, 71–86

fuzzy requirements, 33–34

for interviews, 158–159

for meetings, 155

nature of, 9, 11

project budgets in, 36, 72, 103–104

project plans, 105–113

questions in, 10

resource balancing in, 97–103

resource identification in, 95–97

in risk management, 168

scheduling activities, 87–93

scope definition, 27–28, 29

scope documents, 42–46

scope management, 12, 28

scope statements, 28, 34–46, 106

sequencing activities, 62–69

SMART requirements, 32–33

work breakdown structure, 28, 47–60

portfolio management

defined, 7

importance of, 7–9

portfolios, defined, 7

postcompletion data, 181

precedence diagramming method (PDM), 62–63

precision of estimates, 83–84

predecessor activity, 64–67

preparing, in directing project teams, 152–153

prioritizing risk, 166–168

problem/opportunity, 18

problem solving, 148, 151–152

procurement management, 13

product scope, 27

professional associations, 38–39

profitability, 19

program evaluation and review technique (PERT), 82–83

programs, defined, 7

project budget, 36, 72, 103–104, 135

project change management, 138

project charter, 24, 106

project closure, 175–186

administrative closure, 181, 185

benefits of, 176

common situations in, 176

contractual closure, 182

exit criteria, 177–178

finance records, 181, 185

formal acceptance by client, 176, 182

initiating, 182–183

nature of, 12, 175–177

objectives of, 176–177

performance reporting, 181, 186

premature, 180

review of lessons learned, 183–185

staff release, 181, 186

termination by addition, 179

termination by extinction, 179

termination by integration, 178–179

termination by starvation, 179

project control process, 118, 119–121, 137–143, see also controlling

baseline in, 138

central precepts of, 137–138

earned value analysis in, 138–143

project scope and, 28, 59–60

types of project control, 119

project drivers, 35–36

project float, 90

project management

defined, 7

evolution of, 8

functions of, 9–11

information systems in, 8, 122

knowledge areas in, 12–13

management, defined, 9

management processes in, 11–12

Project Management Institute, 11

Project Management (Meredith and Mantel), 178–180

project management software, 88

project managers

concept of, 8

conducting interviews, 158–161

conducting meetings, 154–157

directing project teams, 152–153

leading project teams, 145–152

managing project teams, 153–154

presenting options to senior management, 37

project results and, 17

project objectives, see objectives

project performance baselines, 138

project plans, 105–113

as baseline, 2

budget plan, 111

communication plan, 112–113

milestone plan, 111

organization plan, 111–112

project charters, 24, 106

project scope statements, 106

resource utilization plan, 110

risk management plan, 112, 163–171

schedule plans, 107–110

project reviews, 184

projects

defined, 6

as temporary, 6–7

as unique, 6–7

project schedule, see scheduling activities

project scope

changes in scope, 134

collecting requirements, 28–34

controlling scope, 28, 59–60

defining, 27–28, 29

scope management and, 12, 28

scope statement, 28, 34–46, 106

verifying scope, 28, 59

work breakdown structure (WBS), 28, 47–60

project scope creep, 59–60

project status, techniques for determining, 122

project teams

directing, 9, 152–153

leading, 145–152

managing, 153–154

project triangle, 34–35

quality assurance, 13, 86

questions

general and organizational, 159–160

interview, 159–160

in planning process, 10

in scope definition, 43–46

technical, 159

reacting, in managing project teams, 153–154

receivers, in communication process, 147–149

reflecting

lessons learned and, 183–185

nature of, 160

reproachable behavior, 150–151

requirements, defining project, 18

reserves, 36–37, 135, 170

resource allocation, 72

resource assumptions, 42

resource-based activities, 84

resource constraints, 64

resource distribution, 72

resource histogram, 96–97, 101

resource leveling, 63

resource managers, see functional managers

resources

balancing in planning process, 97–103

changes in project budget, 135

in crashing the schedule, 91–92

in estimating activities, 72, 79–83

identifying in planning process, 95–97

in scheduling activities, 91–92

resource smoothing, 72

resource utilization plan, 110

response plans, 168–171

acting on, 171

developing, 170

planning responses to risk, 168

possible responses to risk, 168–170

responsibility assignment matrix, 52, 53

return on investment, 78, 170

risk

accepting, 170

categories of, 164

defined, 112

determining likely, 164–165

in estimating activities, 80–83, 85

ongoing risk identification, 165–166

project risk analysis, 53

in scope statement, 40–41, 45–46

see also risk management plan

risk management, 13, 105–106, 163–164

risk management plan, 112, 163–171

response plans, 168–171

risk assessment in, 166–168

risk identification in, 164–166

risk prioritization in, 166–168

see also risks

sanity check, in data analysis, 131

schedule performance index (SPI), 140

schedule variance (SV), 130, 139–140

scheduling activities, 87–93

accelerating project schedules, 91–93

activity dates in, 87–90

baseline schedule, 123, 124, 126

changes in schedule, 134

Gantt charts, 107, 123, 125

importance of project schedule, 122–127

percent complete schedule, 127, 129

project float and, 90

project schedule as table, 109

schedule plan and, 107–110

variances in, 127, 130

scientific assumptions, 41

scope

product, 27

project, see project scope

scope control, 28, 59–60

scope creep, 59–60

scope management, 12, 28

scope statement, 28, 34–46, 106

assumptions in, 41–42, 45

constraints in, 34–35, 37, 40

exclusions in, 39

objectives in, 34–37, 45

risks in, 40–41, 45–46

sample scope document, 42–46

specifications in, 37–39

scope verification, 28, 59

senders, in communication process, 146–149

senior managers

and goal statement, 23

project options and, 37

sequential activities, 52, 62–69

significance test, in data analysis, 132

simulation estimates, 75

slack, 90

SMART requirements, 32–33

solution/vision, 18

specifications

defining project, 18

in estimating activities, 73

in scope statement, 37–39

subject matter experts and, 23

staffing

nature of, 10

staff release in project closure, 181, 186

stakeholders

in authorization process, 18

defined, 18

standards

in estimating activities, 73, 85

sources of, 37–39

start-to-finish (SF) activities, 65

start-to-start (SS) activities, 65

starvation, termination by, 179

statement of work, 73

status collection templates, in determining project status, 122

status meetings, in determining project status, 122

sticky notes, for work breakdown structure (WBS), 59

strategic projects, 19–20

subject matter experts

in estimation activities, 76

and specifications, 23

successor activity, 65–66

survival of organization, 19

SWOT analysis, 20

synchronous communication, 149–150

tasks, see activities

technical assumptions, 41

templates, for work breakdown structure (WBS), 58

termination of project

by addition, 179

by extinction, 179

by integration, 178–179

by starvation, 179

three-point estimates, 80–83

time

in estimating activities, 71

improving estimates over time, 86

time-and-materials contracts, 169

time constraints, 34, 37

time/cost/resource trade-off

in estimating activities, 79–80

in three-point estimates, 80–83

time management, 12

top-down estimates, 74

trade organizations, 38–39

transferring risk, 169

trend analysis, 131–132, 141

triggers, 165, 171

variance analysis, 138–143

indices and ratios in, 140–143

key values in, 138–139

in measuring work accomplished, 139–140

verifying scope, 28, 59

vision, defining project, 18, 20

walk-throughs

in determining project status, 122

in planning phase, 31

warranties and maintenance, 181

workaround, 171

work breakdown structure (WBS), 28, 47–60

accountability in, 52, 53

considerations in creating, 49–51

creating, 47–48

with durations and dependencies, 110

in estimating activities, 72–73

examples of, 50, 56, 57, 58

flexibility of, 54–57

in monitoring project work, 121

nature of, 47

as outline, 48–49

scope control, 28, 59–60

scope verification, 28, 59

sequencing activities, 62–69

techniques in creating, 57–59

as validation tool, 51–54

work effort, 179

work packages, 48, 52, 72–73, 107, 111–112, 123, see also activities

worst-case estimator, 77–78

..................Content has been hidden....................

You can't read the all page of ebook, please click here login for view all page.
Reset
3.149.231.128