07

BIM and Contracts

BY PROFESSOR DAVID MOSEY

fig0008

Introduction

In this chapter we will look at the contractual and legal implications of BIM for project team members. The Government Construction Clients Group suggested in March 2011 that ‘Little change is required in the fundamental building blocks of copyright law, contracts or insurance to facilitate working at Level 2 of BIM maturity.’1 We will examine the extent to which project teams implementing BIM should rely on this assessment.

The key coverage of this chapter is as follows;

  • How does BIM affect contractual duties of care?
  • How is BIM dealt with in standard form construction contracts and consultant appointments?
  • How does the CIC BIM Protocol work?
  • BIM and Contracts: The key issues
  • Does BIM affect advice on procurement models?
  • Lessons Learned from Cookham Wood Case Study.

How does BIM affect Contractual Duties of Care?

BIM is a set of systems that should facilitate and support agreed activities of design, costing, programming, project management, construction and post-completion operation. Adopting BIM does not automatically affect the duties of care agreed under contract or imposed by law in respect of those activities. However, the way that BIM increases data exchange and its dependence on computer software programmes can influence legal liability, while the aspirations of BIM users to improve collaboration and efficiency need to be framed within appropriate and insurable legal commitments.

The duty of a consultant to use ‘reasonable skill and care’ in creating a design,2 and its duty to produce a design that is buildable,3 should not be affected by the adoption of BIM. Likewise, the risk of raising a consultant’s duty of care to ‘fitness for purpose’ in respect of what a design will achieve – and the consequent concern that this will not be supported by professional indemnity insurance – should not occur by reason of adopting BIM. In either case, any change to the designer consultant’s duty of care occurs only by agreement of additional contractual commitments.4

Meanwhile, the implied design duty of ‘fitness for purpose’ that is the starting point for a design and build contractor,5 or for the supplier or manufacturer of a product,6 should also not be affected by adoption of BIM and can only be reduced by a clear provision of the type found in most building contracts.7

The following is worth keeping in mind when advising a client on the adoption of BIM for the first time: ‘Architects who are venturing into the untried or little tried would be wise to warn their clients specifically of what they are doing and to obtain their express approval.’

So what has been Changed by BIM?

Reasonable skill and care

The following factors are useful when assessing ‘reasonable skill and care’ in the world of BIM:

  • In its approach to BIM a consultant is expected ‘not to lag behind other ordinarily assiduous and intelligent members of his profession in knowledge of the new advances, discoveries and developments in his field’.9 This means keeping up with the profession, firstly in advising on the benefits and risks of adopting BIM, and secondly in applying BIM to the design process and to related costing, programming and project management services.
  • The professional knowledge and practices relating to BIM are continually evolving. A consultant falling behind the advance of BIM is entitled to claim that it applied ‘the state of the art’ at the time of giving its advice, although this defence will be judged by reference to the guidance and publications available to the profession as a whole at that time.10
  • Where there is a contractual obligation to comply with the Construction (Design and Management) Regulations 2015, the duty of care in relation to BIM may also be assessed in terms of its impact on a designer’s duty when ‘preparing or modifying a design’ to ‘eliminate, so far as is reasonably practical, foreseeable risks to the health and safety of any person’, or otherwise to reduce or control those risks, and ‘to take all reasonable steps to provide, with the design, sufficient information about the design, construction or maintenance of the structure to adequately assist the client, other designers and contractors to comply with their duties.’11

Duty to review designs

As regards a designer’s duty to review and check its own designs and those of other designers at each stage of BIM model development:

  • Increased access to BIM data emerging throughout the life of a project could increase the likelihood that a designer has become aware, or should become aware, of the need to reconsider an earlier design.12
  • Increased access through BIM to other team members’ designs could affect a designer’s duty to warn of errors or problems it notices in another team member’s work.13

Limits of design liability

In establishing the limits of design liability under BIM:

  • The transparency of BIM models and the way that BIM models fit together should assist in identifying more precisely who does what design and where each team member’s design liability starts and stops.
  • This should clarify the right of designers to rely on other team members’ earlier, simultaneous or later design contributions.

BIM Information Manager

As to the liability of the BIM Information Manager and the ability of other consultants to rely on the BIM Information Manager:

  • Both depend firstly on clarifying exactly what the BIM Information Manager does, noting for example CIC Protocol guidance: ‘The Information Manager has no design related duties.’14
  • The ability to rely on the BIM Information Manager as a specialist depends in part on the designer acting reasonably in this reliance.15

How is BIM Dealt with in Standard form Construction Contracts and Consultant Appointments?

Key Points

Before we look at the terms and conditions of standard forms, the place to start is in the scope of a contractor’s brief or a consultant’s schedule of services. The following key points should be checked:

  • Does the contract contain a clear set of obligations as to how the consultant or contractor will be expected to implement BIM, including for example whether this will start with the project procurement process and continue into post-completion operation?
  • Are there clear statements of the consultants or contractor’s promised BIM experience and expertise?
  • Is it made clear what effect the use of BIM will have on the consultant’s or contractor’s specific duties in respect of design, costing, programming, project management and construction?
  • Do all parties understand who will be BIM Information Manager, what duties this role will comprise and how these duties will interface with those of the design lead and the project manager so as to avoid gaps or duplications?16

Standard Forms

As regards terms and conditions relating to BIM, the standard form building contracts, consultant appointments and related guidance have so far used a light touch. This reflects the fact that BIM does not necessarily change how standard forms allocate risk and liability or how they deal with the project processes.

Some standard form building contracts expressly mention BIM, showing that the relevant drafting body has taken BIM into account. Examples are the JCT ‘Public Sector Supplement’,17 PPC2000 ‘Appendix 10’,18 and several clauses in the CIoB ‘Complex Projects Form’.19 Some standard forms mention their approach to BIM only in guidance documents, for example ‘How to use BIM with NEC3 Contracts’.20 Meanwhile, certain standard form building contracts such as FIDIC are silent on BIM, which leaves uncertainty for the user as to whether BIM has yet been taken into account by the drafting bodies. Most standard form consultant appointments are also silent on BIM, although some refer in their guidance to the ‘CIC BIM Protocol’ described below.

However, to look for a mention of BIM in a contract is not the most effective way of determining a contract’s suitability to support the adoption of BIM in practice. Instead, it is better to look at how the contract deals with the key issues affected by BIM. These issues are examined below.

It is also important to look at whether there is consistency on these issues as between the building contract, all consultant appointments and also any sub-contracts and supply agreements that govern a design contribution. For example, there are complete and consistent sets of NEC3 and PPC2000 contract forms, but JCT offers no consultant appointment except for public sector projects21 and in those cases it will be necessary to align all other consultant forms with the JCT treatment of BIM. One way of ensuring consistency in the contractual treatment of BIM was the publication in 2013 of the ‘CIC BIM Protocol’, and this is what we will examine next.

How does the CIC BIM Protocol Work?

The CIC BIM Protocol is a supplementary contract document signed, in addition to each consultant agreement or building contract, by each project team member – including every consultant, the main contractor and any sub-contractors and suppliers who make design contributions. In the event of conflict or discrepancy, it overrides the consultant appointment or building contract (Clause 2.2).

Licensing of Models

The provisions and guidance of the CIC BIM Protocol propose a reasonably balanced approach to the licensing of BIM models, including:

  • Grant of a non-exclusive licence for the client to transmit, copy and use models for the agreed project-related purposes for which they were prepared (Clause 6.3).
  • The right for the client to grant equivalent sub-licences and for team members to grant equivalent sub-sub-licences (Clauses 6.3, 6.6, 6.7).
  • Exclusion of the right to amend models except for agreed purposes (Clause 6.5.1) and exclusion of the right to reproduce models for the purpose of project extensions (Clause 6.5.2).
  • Mutual obligations on the client and project team members to procure licences as required to meet their agreed licence obligations under the protocol (Clauses 6.9, 6.10).

Limits of Liability

The protocol also includes the following limits on a project team member’s liability:

  • No warranty as to the integrity of electronic data transmission, and no liability for corruption or alteration occurring after transmission (Clause 5).
  • Cross-reference to support any right to revoke or suspend a licence to use models in the event of non-payment (Clause 6.4).
  • No liability for the modification, amendment, transmission, copying or use of BIM models other than for agreed purposes (Clause 7).

Appendices

The Appendices to the CIC BIM Protocol comprise important practical documents, namely:

  • Appendix 1: The ‘Model Production and Delivery Table’, which sets out the ‘Levels of Detail’ to be achieved in respect of each BIM model by each project team member at each stage.
  • Appendix 2: Details of the BIM Information Manager’s role, and of the ‘Employer’s Information Requirements’ regarding the “Common Data Environment” created through BIM, including agreed software and formats plus cross-reference to the BIM ‘Execution Plan’ and related project procedures.

These documents need to be integrated with the consultant services schedules, the contractor’s brief and the project programme.

Duty of Care

The obligation on project team members to produce models in accordance with agreed Levels of Detail specified in the Model Production and Delivery Table is limited to ‘reasonable endeavours’, a lower duty of care than the accepted standard of ‘reasonable skill and care’ (Clause 4). In addition, a team member’s compliance with the Model Production and Delivery Table and the Information Requirements is stated to be ‘subject to events outside its reasonable control’ (Clause 4), a generic exception which overrides the detailed provisions for extension of time contained in all standard form building contracts.

Client Concerns

Some of the above provisions dilute what a client would expect as commercial norms, and anyone recommending the CIC BIM Protocol should make very clear its potential impact on client rights.

The absolute obligation on the client to secure protocols in substantially the same form from all other project team members, and to update the Information Requirements and the Model Production and Delivery Table (Clause 3), should also be made clear to the client before the CIC BIM Protocol is adopted.

BIM and Contracts: The Key Issues

There are practical measures by which project teams can use contracts to get the best out of BIM while not exposing themselves to additional liability, and these are set out below. Some of these issues are dealt with (to varying degrees) in existing standard form contracts; others need additional attention, particularly to ensure consistency as to how they are addressed in consultant appointments and building contracts. In all cases, it will be important for advisers on a project using BIM to check how these issues are dealt with in the contractual provisions and procedures before making a recommendation.

Contractual Status of Model Production and Delivery Table

BIM provides clarity as to the Level of Detail in each model at each stage of a project, and requires that consultant appointments and building contracts reflect that clarity in deadlines setting out the agreed sequence of model production, delivery, comment and approval. There should be a contractual commitment by all team members:

  • To produce and deliver their BIM models to the agreed Level of Detail by agreed deadlines at each stage
  • To provide comments and approvals by agreed deadlines at each stage
  • To specify matters that may prevent agreed deadlines being met.

Certain standard form building contracts provide documents that could be linked to or embody the Model Production and Delivery Table, for example:

  • The JCT Information Release Schedule,22 although this only commits the main contractor under the JCT 20111 building contracts, with no corresponding commitment in the JCT Consultant Appointment (Public Sector).
  • The NEC Key Dates Schedule,23 which appears both in the NEC Building Contract and in the NEC Professional Services Contract.
  • The PPC2000 Partnering Timetable and Project Timetable24 which, under the PPC multi-party structure, mutually commits the main contractor and all consultants to agreed deadlines.

Mechanisms to achieve Collaboration and Consensus

BIM is often described as collaborative, and clearly creates significant opportunities for team members to work collaboratively, but without additional discussions this may go no further than agreed arrangements for sharing BIM data and expecting timely feedback. These can be dealt with in the agreement of deadlines for model production, delivery, comment and approval as described in above.

If collaboration through BIM is intended also to describe the culture of the project and the way that team members assist each other, then this needs clarification in the contract terms so that there is no room for misunderstanding or opting out. For example, a forum for clash detection, early warning and risk management is described in the next section. Other contract provisions that support a collaborative culture include:

  • Direct mutual agreement to act in ‘good faith’ or otherwise in a collaborative manner
  • Direct mutual commitment to agreed objectives.

These appear, for example, in the following standard forms:

  • In the JCT forms, a ‘good faith’ provision appears in the optional Appendix 8 to the 2011 building contracts – but there is no equivalent commitment in the JCT Consultant Agreement (Public Sector).
  • In the JCT forms, mutual direct commitments to agreed objectives appear only in the ‘JCT Constructing Excellence Project Agreement’.
  • In NEC3, a ‘good faith’ provision is given in Clause 10.1 of all building contracts and the consultant appointment form.
  • In NEC3, no mutual direct commitments are given, as these are expressly excluded in NEC3 Partnering Option X12.
  • In PPC2000, a ‘good faith’ provision is included in Clause 1.3 of the PPC2000 Partnering Terms.
  • In PPC2000, the multi-party structure creates mutual direct commitments between the client, all consultants, the main contractor and key sub-contractors.

Clash Detection, Early Warning and Risk Management

BIM enables design inconsistencies to be revealed through clash detection, but for BIM to enable collaborative working, there needs to be a contractual mechanism establishing what team members do when clashes are detected and notified. This should comprise a forum tasked with seeking a constructive solution. Although the JCT forms do not provide for such forums, both NEC Option X 1225 and PPC200026 provide for such ‘Core Groups.’

Intellectual Property Licences

Intellectual property rights should not need different protections by virtue of appearing in BIM models. For example, existing statutory copyright protection covers graphic and non-graphic design work plus ‘computer programmes’ and ‘preparatory design material for a computer programmes’, and arguably does not need clarification to extend to BIM models.27

However, it is important to spell out that athough the CIC Protocol offers a balanced approach to the licensing of BIM models, it creates an additional burden on the client by making it the contractual gatekeeper of all model licences, leaving project team members without direct remedies in the event of breach of each other’s licences. The multi-party structure of the PPC2000 contract solves these problems by creating direct licences and mutual indemnities between all the project team members who sign it.

Liability for Corruption of Data

It is worrying that the CIC BIM Protocol excludes any warranty as to the integrity of electronic data delivered, and also excludes liability in respect of any corruption or amendment of data after transmission. This places all risks with the client, and does not, for example, require project team members to apportion any liability to the BIM software providers. By contrast, there are no equivalent exclusions in the JCT, NEC3 or PPC2000 standard form building contracts.

Links between Design, Construction and Operation

The benefits of BIM should extend long beyond completion of a capital project, if it is used to create accessible data that supports interactive operation and maintenance systems in place of traditional ‘O and M’ manuals. For example, the UK Government’s ‘Soft landings’ initiative includes trials of new project team contractual commitments, supported by BIM, which extend beyond the typical defects liability period.

Standard contract forms can link the capital and operational phases of a project, and the JCT, NEC and PPC contract suites all offer compatible ‘term’ contract forms. However, the development of contract models that help to fulfil the operational potential of BIM data also depends on the adoption of procurement models which invite the market to submit whole-life asset management proposals.

Closer integration of design, construction and operation phases in the life of a built asset forms part of the UK Government’s approach to BIM level 3. For example, ‘Digital Built Britain’ includes proposals for the ‘Development of BIM and asset data enabled FM and AM Contracts’28 (see Chapter 4).

Does BIM affect Advice on Procurement Models?

Traditionally, advice on selection of a procurement model has focussed only on identifying which team member or members are responsible for design, and on how to transfer design and construction risk away from the client. The only procurement options that also focus on the timing of each team member’s appointment have involved fragmentation of these responsibilities through the separate appointments of individual specialist contractors.

So, if BIM is intended to support a collaborative approach, can a new procurement model be devised that obtains BIM model contributions from the main contractor and from specialist contractors without fragmenting the warranties relied on by the client?

Early contractor and supplier design input has been advocated for many years, for example by the ICE (as quoted in ‘Accelerating Change’), which states, ‘Designers must involve the contractors, specialist subcontractors and key manufacturers as soon as possible. In order to interpret and develop a functional brief it is essential that designers (including specialist subcontractors and key manufacturers) are able to get close to clients.’29

While early contractor involvement has been devised ad hoc by individual project teams and although it is a model embedded in the PPC2000 contract form, the UK Government introduced the first formal assessment of its merits under a ‘Trial Projects’ programme pursuant to their 2011 ‘Government Construction Strategy’. Meanwhile, the Royal Institute of British Architects restructured its ‘2013 Plan of Work’ to identify design work stages that can be led by an early appointed main contractor and its specialist supply chain, integrated as members of a single design team.30

The Government’s ‘Two Stage Open Book’ procurement model was adopted on Trial Projects combining early contractor involvement with BIM. This creates a single project team, including the main contractor, which is appointed early under a conditional contract and a binding timetable describing how they will work together through BIM to develop designs, agree costs and reduce risks ahead of the client approving start on site.31

The results achieved through the Government’s Trial Projects are set out in online guidance which describes the prerequisites, processes and techniques for successful early contractor involvement, and the measurable benefits this can help to achieve, particularly when implemented in conjunction with BIM.32 These benefits include audited savings of up to 20 per cent, greater cost and time transparency, improved quality control and risk management, improved opportunities for small to medium enterprises and other local/regional businesses, and greater employment and skills commitments.

We will next examine the first detailed Government case study of BIM combined with ‘Two Stage Open Book’ in order to consider what lessons it offers when advising on the best procurement options to adopt in conjunction with BIM.

Lessons Learned from the Cookham Wood Case Study

For the team that delivered the Cookham Wood Trial Project, a combination of early contractor involvement, collaborative working and BIM was integral to the results achieved. BIM Level 2 models were used in the brief issued to prospective main contractors, and were developed by bidders as part of their proposals for project team selection. Interserve Construction were appointed as main contractor and lead designer, bringing with them Arup as consulting engineers, EMCOR as mechanical and electrical specialists, and SCC as precast volumetric cell providers. HLN Architects were the Ministry of Justice’s (MoJ) appointed designer and technical assessor.

Savings and Improved Value achieved using BIM

The Cookham Wood Trial Project case study, which was independently audited, attributed significant improved value to ‘Two Stage Open Book’ and BIM. These included 20 per cent agreed savings, namely a cost of £2,332 per square metre against a baseline benchmark of £2,910 per square metre. For example, Interserve and its tier 2 specialist subcontractor SCC submitted a ‘precast volumetric cell’ proposal in response to the MoJ brief; this was developed through BIM by the wider design team and led to a time saving of six weeks and a saving in overheads of £85,000.33

Other innovations driven by ‘Two Stage Open Book’ and BIM included:

  • The use of solid precast floor slabs in place of pre-stressed floor slabs, resulting in a time saving of 12 days.
  • The creation of ‘indestructible’ lighting in the education block through a bespoke solution proposed by EMCOR that also created a significant cost saving.
  • Development by Arup and EMCOR of service ducts and cell risers that could be serviced more quickly and reliably by repair and maintenance engineers.34

BIM Execution Plan and Core Group

Interserve prepared a BIM Execution Plan linked to a series of agreed deadlines in relation to the preconstruction phase of the project.35 By this means, specified Construction Operations Building Information Exchange (COBie) data drops and related activities were supported by clear contractual obligations, including peer group pressure under the governance of named individuals comprising the ‘Core Group’. Core Group members met whenever required to approve design development proposals and to resolve questions and problems arising from clash detection, in each case deciding on courses of action by unanimous agreement of all members present.36 This group worked alongside the design team, who were tasked with the development, coordination and exchange of information through the BIM models.

Mutual Reliance and Clash Detection

Each team member agreed to be responsible for errors, omissions and discrepancies in the BIM models it prepared or contributed to, ‘except to the extent of its reliance (if stated in such Partnering Documents) on any contribution or information provided by any one or more other Partnering Team members’.37 As the sequence and nature of each contribution was spelled out, each team member was contractually entitled to rely on all earlier designs, and was made aware of which partners would rely on the completeness, accuracy and timeliness of that member’s contributions.

The team members agreed to warn each other ‘of any error, omission or discrepancy of which they become aware and (within the scope of their agreed roles, expertise and responsibilities) to put forward proposals to resolve any such error, omission or discrepancy fairly and constructively within the Partnering Team without adversely affecting the agreed cost or time for completion or quality of the project’.38 This clause underpinned the commitment of all parties to BIM clash detection and to the notification of pragmatic solutions. It helped to establish that no team member would, by notifying a warning of clash detection and a proposal to resolve it, be charged with any additional responsibilities beyond those already within its agreed contractual role and expertise.

Intellectual Property Licences

Under the multi-party structure, a set of mutual intellectual property licences were directly entered into between all team members ‘for any purpose relating to the completion of the Project and (only in regard to the Client) the Operation of the Project’.39 As regards liability arising from the licensing of intellectual property rights, the liability of team members was excluded ‘for the use of any design or document that it prepares for any purpose other than that for which it was agreed to be prepared as stated in, or reasonably inferred from, the Partnering Documents’.40

Conclusion

This chapter has demonstrated how to secure contractual protections for all project team members by looking for specific provisions and processes that support BIM. It has shown how integrated collaborative contracts and early contractor involvement can help BIM to fulfil its potential. It has also explained the contract systems used to deliver savings and other improved value on the Cookham Wood Trial Project.

..................Content has been hidden....................

You can't read the all page of ebook, please click here login for view all page.
Reset
18.223.32.230