299Capacity Analysis
may require the use of more than one document, and is consistent with PPAP
requirements. For end-item part numbers that have multiple value streams, the
capacity planning analysis must begin by looking at a single value stream. This
is due to considerations made to individual process scrap losses, which have
impact on the individual process required OEEs. In effect, the capacity analy-
sis is generally setup on a part-specic basis. However, depending on the part
and manufacturing process, it may be appropriate to group families of parts or
several manufacturing lines. If in doubt, check with the customer for approval.
Improving Required OEE
By adding operating time, reducing up-line scrap loss, or decreasing net
ideal cycle time, capacity gaps can be eliminated. The minimum level of
efciency required by a supplier to meet customer’s volume requirements
is based on the supplier’s planned operating pattern and manufacturing
assumptions. The required OEE for each process must be understood and
identied as early as possible by both customer and supplier. For each pro-
cess, the required OEE is the target—capacity gaps can only be identied
by comparing demonstrated OEE to this target. The basic question here is:
Are the required OEEs for each process feasible? Specic items to reduce
the required OEE with minimal investment that may be considered are to
expand operating pattern, add extra shifts of expanded hours, and consider
overtime. Another option is to reduce constraint cycle times by: (1) machine/
equipment design, (2) coordination with equipment suppliers to reduce cycle
time, (3) introduce faster processes when and if possible, and (4) track and
optimize cycle times at ramp-up.
Shared Loading Analysis
Shared loaded analysis is the evaluation of how much time is allotted for
production using a stream for the customer. Make sure that the allotted time
is rated correctly and fullls the requirements of the customer. Generally,
there is only one exception to this rule where total allocation is calculated.
The exception is for machining and outsourced e-coat. To complete a Shared
Loading Plan for a process, the following information is needed:
1. APW and MPW volume information adjusted for downstream scrap
losses, along with the NICT for all parts that are planned for produc-
tion on the specic process; average demonstrated OEE from most