What’s different about Business Programme management?
Prerequisites for effective portfolio management
Directing a ‘portfolio’ of projects is a key senior management task, as it is this ‘bundle’ of projects that will take you from where you are now to your, hopefully, better future.
’What shall become of us without the barbarians? Those people were a kind of solution.’
CONSTANTINE CAVAFY, 1863–1933
In Chapters 12 and 13 we considered the following definitions: A project, in a business environment, is:
Subprojects are tightly coupled and tightly aligned parts of a project.
Programmes are a tightly coupled and tightly aligned grouping of projects.
We also saw how a project moves from being ‘undefined’ to being ‘defined’. This was then put into the context of four project types:
Once this is understood, you should be able to define a single project in terms of its life cycle stages. However, business is rarely so simple that a single project or even programme can achieve all that is needed. The next step is to understand how bundles (or portfolios) of programmes and standalone projects are used together with other business activities to further your aims. We will call these ‘Business Programmes’.
Business Programmes comprise current benefit generating business activities together with a loosely coupled but tightly aligned portfolio of projects and programmes, aimed at realising the benefits of part of a busness plan or strategy.
They are best explained by using a simplified example.
You may have a business objective to increase your revenue from $10m to $15m in two years. You’ve chosen to do this by increasing your share of an under-exploited segment of your market. The alternative is to withdraw from that segment, milking whatever cash you can from it on the way. In order to achieve the required target revenue, you have found that you need to:
You can see that the five projects are aligned to your overall strategy and that each provides a discrete business benefit. Most are independent. (Only Project 2A depends on Project 2 as you cannot enhance a product until you know what it is.)
Notice that the approach has been to split the new product development into two phases (Projects 2 and 2A). This benefits you by gaining early revenue and having a foothold in the market. Traditionally, organisations make their projects too big. Dividing projects into smaller pieces (chunks of change) makes success more likely and implementation easier.
Finally, you need to take account of the benefits you are expecting from the product as it currently is in the market. Your aim is to obtain a $15m revenue. The benefits from your current product and future projects and initiatives need to be sufficiently high to meet that target.
As a business manager, you are not particularly concerned with the individual performance of each project and product. Of more interest is the total benefit. Thus, if your current product starts to perform better than expected, a delay in a project may not be too significant. Only you can decide the relative importance of the projects within the business programme.
Keeping to the example, how did the managers derive their approach and end up with the five projects I described? The starting point was a problem for the directors of the organisation: they needed more revenue. They needed to look at their complete mix of products and markets and decide the most likely areas for gaining the additional, profitable revenue. (Perhaps they needed a new product and a new market!) One option identified by the review was that they either take a minimum prescribed market share of a particular segment or they withdraw from it completely. It was considered untenable to keep the status quo. This would lead to a decline in revenue to about $7m per year. This conversation is firmly within the domain of business strategy and planning. What is needed now is to take it to action.
The five projects could not, in fact, have come about directly as the result of a strategic review. The organisation simply would not have known enough to make that jump. At most, a required timescale and overall affordable budget annual cash flow could have been set (i.e. constraints applied by the business). However, a project could have been initiated to look at various options – a quest! The Initial Investigation Stage would spawn a set of possible projects. These may just have been:
Each fulfils the definition of a business project by realising discrete benefits. Each will further the aims of the organisation to attain more revenue.
However, the investigative stages of Project 2 came up with a constraint on manufacturing the new product. It was not possible to do it in the time available and hence a decision was made to create the product in two phases. We now have:
Again, the Detailed Investigation Stage of Project 2 found, as part of the market research, that delivery time was a more important buying factor than realised. If amendments to Project 2 were made to incorporate this, it would have slipped and the revenue targets would have been missed. Consequently, a separate project was started off to take this aspect into account (Project 2B) (see Figure 14.1).
Notice what has happened. Projects spawn projects! A simple business objective of ‘Get $15m revenue’ has been translated into action in the form of five projects. When combined, these realise the benefit that the business requires.
Note that each project is defined such that it delivers a slice of that benefit, either independently or, as in the case of Projects 2 and 3, in series. Also notice that the business solution has been broken into discrete pieces. This has the effect of making them easier to implement and also allows benefits to be realised earlier than if the full scope were undertaken in a single project. You can also proceed with parts of the business programme as soon as you’re ready, while other parts are still in the fog.
Look at the projects that have resulted. Did they start off as fogs, quests, movies or painting by numbers? Probably the mix is as follows:
Project 1 – enhance old product: | Painting by numbers |
Project 2 – the basic new product: | Movie |
Project 2A – the enhanced new product: | Quest or fog |
Project 2B – decrease delivery time: | Quest |
Project 3 – reduce faults: | Quest |
Project 2 has to use existing manufacturing plant for producing the new product. Project 2A needs to be converted to a painting by numbers project if it is to succeed. Projects 2B and 3 are more open ended. You may spend a fortune looking at possibilities but still not achieve a breakthrough. This, on its own, gives you a feel for the risk you are facing. You are not likely to have too much confidence in the benefits for those projects which finish more than a year from now. So, to make sure that your business programme is robust, you will need continually to reforecast your benefits. With a business programme like that shown, a related business planning and forecasting cycle of three months would probably be about right.
The example is necessarily simpler than most situations you will find in practice as most Business Programmes comprise many more projects; nevertheless, it does demonstrate the key aspects of Business Programmes.
In some cases, it is necessary to include new scope in an on-going project. Proper control of changes to the project scope are required to ensure that only beneficial changes are made. Chapter 25 explains this more fully.
Business Programme management provides a framework and practical tool for managing multiple programmes and projects in pursuit of defined strategic objectives. Business Programme management complements project and programme management but it takes a much broader, enterprise-wide view as it also includes benefits from current operations. Benefits from projects usually start after the project has been completed and the project team has been stood down. However, benefits from Business Programmes start to flow as soon as the first project within the business programme has been completed and its outputs incorporated into ‘normal business’. The key focus for Business Programme management is ensuring that current activities plus the programmes and projects as a whole provide the benefit required overall, regardless of the performance of individual components. Other differences are highlighted in the table that follows.
The advantages of taking a ‘Business Programme approach’ is that you are able, as we have seen from the simple example, to break up the required changes into achievable pieces and manage the implementation in a coordinated way. The change is therefore less likely to appear chaotic to the recipients (be they your own employees, your suppliers or your customers). You are also able to maintain a focus on the true business objectives of the Business Programme rather than be lost in the minutiae of delivery. This enables you to spot future gaps in benefits (either due to late projects or under-performance in benefit terms from ones already delivered) and take the necessary corrective action. You are also able to take a balanced view of the risks associated with a Business Programme.
Business Programme management | Programme and project management |
Broadly spread activity, concerned with overall strategic objectives as part of a business plan. It’s a continuous activity, with no defined end-point | Intense, and focused activity aimed at realising a ‘slice’ of benefit to the business programme as defined in a business case. It is a discrete activity, with a defined end-point |
Is suited to managing and balancing a large number of constituent programmes and projects with complex and often changing interdependencies | Best suited to realising achievable benefits directly related to deliverables and outputs |
Is suited to managing the impact of and benefits from a number of aligned programmes and projects in such a way as to ensure a smooth transition from the present to the new order | Is suited to delivering defined benefits within a given environment or scope |
Includes benefits from current operations and from the outcomes of current and future projects | Includes future benefits of the project or programme itself |
Is governed and constrained by organisation cash flow often seen as an annual budget | Is governed and constrained by a discrete programme or project budget |
I have already mentioned the difficulties that certain words can create; ‘programme’ is just such a problematic word (see pp. 62, 151). No matter how hard you try there will always be someone, somewhere who takes a different view. Accept it and don’t fight it. I expect there are many readers who say my definition of Business Programme is their definition of ‘portfolio’ – neither of us is wrong, but the key point is that, in your organisation, you must make sure you use words consistently in all your written documents, especially management reports. If you use the language consistently, people will gradually pick it up. In this book I distinguish business programme from programme from project. In a small organisation the business programme may represent the entire organisation, in which case the term becomes redundant – the organisation is the Business Programme. In larger organisations, the business plan will need to be divided into a number of Business Programmes each of which represents a part of the overall business plan.
To test if your ‘programme’ and mine are similar, look at Figure 14.2. Business Programmes are above the ‘authorisation process’; they are the entities from which programmes and projects are initiated. They are governed by business plans, which usually give no authority for actual work to take place. Projects are below the ‘authorisation process’, being governed by business cases, which are used as the basis for authorising funding and resources to start work.
If a Business Programme is a chunk of the business plan, who is accountable for it and what are those accountabilities? For small organisations, we have seen from the Point of Interest above that ‘Business Programme’ may be a meaningless term – the organisation is the Business Programme. It therefore follows that the role of the CEO or President and that of the senior team is relevant. These roles are primarily about the leadership of change and this requires both sponsorship (benefit/needs) and management (making it happen). For Business Programmes, I will call these roles ‘Business Programme Sponsor’ and ‘Business Programme Manager’, respectively.
If you are to have Business Programmes in your organisation, you will have a number of them and therefore you will need some body or individual accountable for directing them. There is no accepted term for such a body; for convenience I will call this the ‘Business Strategy and Planning Board’. Together, these business programme accountabilities form a key part in the governance of the organisation. The other aspect of governance is authorisation, where ‘permission’ is required before any work is started or funds spent. I deal with this in Chapter 15.
Naming roles and bodies can be very difficult. Each needs to be as self-explanatory as possible so that people can intuitively understand what each role is for. This can be doubly difficult in a project environment where the words ‘project’ and ‘programme’ take on so many different meanings. I have chosen a set of role names which are consistently applied throughout the book and which draw on associated terminology. I tend to use ‘sponsor’ where the role is ‘directing’ and ‘manager’ where the role is ‘managing’. You may call them what you want but I advise that:
Keeping roles and titles separate enables you to have a number of roles undertaken by a single person or body, thereby saving you from having to rewrite all your processes simply because of a minor change in personnel. For example, the CEO’s Leadership Team may take on the role of the Business Strategy and Planning Board and the Project Review Group. Changing role names is a common ploy by ‘new directors’ to show they ‘have arrived’ but all it usually does is confuse people. A colleague of mine once referred to this as ‘rearranging the deck chairs on the Titanic’.
The Business Strategy and Planning Board is accountable to the Chief Executive Officer for setting business strategy, directing corporate change and ensuring the business programmes realise the benefits required.
The Business Programme Sponsor is accountable to the Business Strategy and Planning Board for directing the Business Programme, ensuring that the portfolio of projects and activities (Business Programme) within his/her scope realises the required benefits.
The Business Programme Manager is accountable to the Business Programme Sponsor for day-to-day management of the Business Programme, ensuring that the portfolio is planned and managed to ensure maximum focus and speed of benefit realisation.
A Business Programme Board, if required, would support the Business Programme Sponsor in carrying out his/her accountabilities, particularly in respect of senior management alignment and engagement.
A Business Programme Office would provide the Business Programme Sponsor and Manager with the necessary administration, expertise, knowledge and resources to ensure that the above accountabilities are undertaken effectively. See Chapter 17 for more on this.
Test the business programme roles. Replace the words Business Programme Sponsor by CEO and the business by shareholder. Notice the fit? The implication is that the role is truly one of leadership and not one of functional management. Business Programme Sponsors may be top directors or executives who have some functional accountability but, in the world of projects, they need to take on a cross-organisation role as we know any single function can achieve very little on its own. You will see a similar correlation between COO (or deputy CEO) and Business Programme Manager.
Look at any one of your longer running projects, say over a six-month duration. Critically review it to decide if you could have implemented it in smaller pieces. What was the minimum that was needed to be done?
Look at projects you are starting off now. Can these be divided into more digestible pieces?
Forecasting cycles
How often do you do your business forecasting? Annually? Quarterly? Monthly? If you do it only annually, consider how you can have confidence in the forecasts. Do you really know so much about the future that you could forecast a year in advance? Is your organisation really in such a slow-moving competitive environment?
Note: Forecasting is predicting what your management accounts and information systems will tell you in the future. Setting a target is not forecasting.
In Chapter 1 we identified a number of commonly found deficiencies in how projects are managed. A key factor in the success of your organisation is the speed and effectiveness with which you can stay ahead of, or respond to, changing circumstances. Unless deficiencies in implementing the necessary changes are addressed, you will always be losing time and energy in fighting internal conflicts rather than addressing real external opportunities and threats.
No organisation, however, has just a single project, there are always several on the go and (as we have seen from the example on p. 163) ‘projects spawn projects’ there will always be more to come, either as part of a programme or as stand-alone initiatives. Directing this ‘portfolio’ of projects is a senior management task, as it is this ‘bundle’ of projects that will take you from where you are now to your, hopefully, better future.
A portfolio is a range of investments held by a person or organisation. A business programme is a very special type of portfolio.
I also use the word portfolio to represent any bundle or grouping of projects which we may choose to select for the convenience of management, reporting or analysis. After all, projects are investments of time and resources made by organisations to achieve benefits. Thus, the full set of projects undertaken within a organisation is its organisation portfolio. The set of projects held by a project sponsor is a sponsorship portfolio. The set of projects project managed by a person or function is a management portfolio.
At an organisation portfolio level, the actual performance of individual projects (or even programmes) becomes less critical. You can accept some being terminated, some being late, some costing too much or simply delivering the wrong thing. What is more critical is that the whole portfolio performs well enough to move your business forward as effectively and efficiently as possible. Like investments in the stock market, your portfolio of projects should be balanced with respect to risk. You should have some (but not too many!) projects which are risky, which will create a step change if they work or which are pushing forward the boundaries of your thinking and capability. Without these, you will be too rooted in today’s paradigms and not reaching for new horizons.
Figure 14.3 illustrates the framework. Future benefits come from three sources in your organisation:
Any change starts as a proposal, becomes part of the project portfolio and eventually its output is subsumed into ‘business as usual’. The speed and reliability with which you can do this is a critical success factor for your organisation.
So what are the prerequisites for managing a portfolio on a organisation-wide basis? The central ‘plank’ to managing a portfolio is reliable management of the individual projects:
To make these work, you must have a organisation-wide environment (Figure 14.4) for:
The lack of any of these capabilities has implications on your organisation:
Business programmes are a vehicle which enable you to tackle these needs. Business programmes are chunks of your strategy and your business plan. They are the link between what you do now and what you will do in the future. They therefore also form the most appropriate vehicle for dividing up your organisation’s spending, with the highest priority business programmes attracting the greatest investment. Finally, they are the control environment for ensuring you do not overload your organisation with ‘too much change’.
The list of factors needed to control a project portfolio is long. In this workout you should assess your current ‘health’ and use that as a prompt for discussion to help you decide which you need to concentrate on first.
Take each in turn and, with respect to projects and change initiatives in your organisation:
Competence | Score | Implications |
Strategic alignment | ||
Decision making | ||
Resource management | ||
Business planning | ||
Register management | ||
Fund management | ||
Project management |
3.17.76.175