Chapter 13
IN THIS CHAPTER
Calculating the correct conductor size
Making sure you have the right size (and type) of conduit
Protecting the conductors with properly sized overcurrent protection devices
After you identify all the components your client’s PV system requires, you need to determine the correct sizes for all the conductors (wires), conduit, and mandatory safety equipment that must be installed (I walk you through what all of these are in Chapter 10). Some of these components may need to be special ordered, so sizing them correctly during the initial design process is critical. After all, one missing piece can bring an entire job to a grinding halt, frustrating everyone involved.
In many cases, the methods used in this chapter are the same as the ones used by electricians for sizing standard electrical equipment. However, there are a few places where you need to look at the process a little differently. Don’t worry, though, because I share what they are in this chapter. I give you methods for making sure the conductors used in the PV system you’re designing are large enough for proper system performance and sized to meet the requirements of the National Electrical Code® (NEC®). I also explain how to size conduit and overcurrent protection devices. (For details on the installation of these components, see Chapter 17.)
When I start sizing the safety components of a PV system, I like to size the conductors used throughout the system based on National Electrical Code® (NEC®) requirements to ensure that they’re large enough to safely allow current to flow through them. To do this correctly, you must conduct some circuit identification. In other words, you need to pinpoint where in the system the conductors go because the conductors from one part of the system to another don’t have the same requirements. For example, the conductors from the PV array to the inverter are subject to different requirements than the conductors from the inverter to the AC main distribution panel (MDP). Note: The actual conductors used can be the same on the DC and AC sides of the system as long as they’re installed properly (I cover different conductor types and where they go in Chapter 10).
Following are the proper circuit designations and where they’re located in relation to the installed equipment (see Chapter 10 for more details about different types of circuits):
In the next sections, I show you how to determine the proper conductor size for the PV systems you design. I also present the safety factors you should use during the conductor sizing process.
Starting at the PV array, you can look at the individual circuits and size the conductors as they work their way to the inverter; these circuits are known collectively as the PV circuits. To size the conductors in these circuits, you have to define the maximum amount of current they’ll ever carry.
The number of modules (or strings) wired in parallel × The short circuit current, Isc, rating of the module (or string) × 1.25
Note: The 1.25 factor is in place to recognize that PV modules produce current based on the available irradiance (irradiance is the intensity of the solar radiation striking earth; flip to Chapter 4 for more information). The NEC® also recognizes that a PV array can (and will) produce more current than its modules are rated for if given the opportunity.
If you keep reading to Article 690.8(B)(1) of the NEC®, you’ll see that a second safety factor of 1.25 is applied. It’s there because the NEC® dictates that the conductors and overcurrent protection devices (OCPDs) used in electrical systems “shall not continuously carry more than 80 percent of the maximum current.” The NEC® is calling for you to oversize the conductors so that when current is run continuously (more than three hours at a time), the conductors won’t overheat, fail, and cause fires.
At this point, all you’ve done is define the ampacity (amount of current flow) required by the conductors on the PV side of the system. As I explain in the later “Putting together the details to determine conductor sizing” section, you have to adjust this ampacity value based on the locations of the conductors.
For example, if you have an array that consists of ten modules in series with each module short circuit current rated at 5.5 A, the maximum current from that series string of ten modules will be 5.5 A × 1.25 = 6.9 A. To define the ampacity required for the conductor connected to this string, multiply the maximum current by 1.25 again to get 6.9 A × 1.25 = 8.6 A. These results mean that the individual string is rated at 5.5 A but that the conductors and any OCPD connected to that string must be rated for at least 8.6 A.
Unlike the PV circuits covered in the preceding section, inverter input circuits on battery-based systems and inverter output circuits (anything from the inverter’s AC output to the load panels) aren’t subject to varying current levels based on irradiance. The maximum current levels for battery-based inverter input circuits or any inverter output circuits are actually based on the equipment to which they’re connected. (Note: The inverter input for a grid-direct inverter is on the PV side and falls into the previous section’s requirements.)
To calculate the ampacity required by the conductors and OCPD, you only have to apply one 1.25 factor so you don’t continuously run more than 80 percent of the maximum current across these components. Here’s the formula:
Maximum output current × 1.25
For example, a 4 kW inverter operates at 240 VAC and has a maximum current output of 16.7 A. According to the preceding formula, the conductors and OCPDs connected to this inverter’s output circuit would need a minimum rating of 16.7 A × 1.25 = 20.9 A.
Maximum continuous power output ÷ Minimum operating voltage
Performing this calculation tells you the largest amount of current that can continuously run through the conductors.
If the specified inverter has a continuous power output rating of 3 kW and it can operate all the way down at 42 VDC, the conductors between the battery bank and the inverter need to be able to handle at least 3,000 W ÷ 42 VDC = 71.4 A.
At this point, you’ve calculated the maximum amount of current each conductor will need to carry based on the NEC® requirements for each circuit (if you haven’t, refer to the earlier sections in this chapter for help). Now you need to take the conditions of use into consideration; in other words, you have to adjust the maximum current levels you found based on the locations where the conductors will be used (on the roof, in the attic, through the basement … you get the idea) as well as how many will be run together.
Prepare to turn to the following four tables in the NEC® when determining the proper application of the conditions of use:
The following sections provide basic instruction on using each of these tables.
Conductors used in PV systems must be evaluated under the conditions typical of where they’ll be used, and the tables in Article 310.15 of the NEC® can guide you on what derate factor (the values used to reduce conductor ampacity values from the starting points listed in the tables) to apply based on a conductor’s location.
The values listed in Tables 310.16 and 310.17 (which are represented in Figures 13-1 and 13-2; both figures show only a portion of the tables) represent the amount of current each type and size of conductor is rated for. The columns marked “Size AWG or kcmil” represent the physical size of the conductor. AWG stands for American Wire Gauge; the AWG convention is that large numbers represent small wires and small numbers represent big wires. After 0000 (pronounced four aught), the big wires are represented by their cross-sectional area instead of the AWG convention. The other columns list different types of conductors by abbreviation.
The ampacity values are based on an ambient air temperature of 30 degrees Celsius (86 degrees Fahrenheit) and no more than three current-carrying conductors (the ground wire isn’t a current-carrying conductor) run together. You adjust these values when applying the appropriate conditions of use.
Note that the tables listing the conductor ampacities also include different columns labeled with different temperatures. These are the temperature limitations of the conductors due to the insulation protecting the conductive material. Table 310.16 in Figure 13-1 differentiates between copper and aluminum conductors. Aluminum has less ampacity than copper, so to carry amounts of current that are equal to their copper counterparts, aluminum conductors must be physically larger. In all the examples I give in this book (and in most PV installations), copper conductors are used exclusively.
Conductor sizes are also limited by the rating of all the terminals, connection points where a conductor is physically connected to a termination such as a disconnect, fuse holder, or circuit breaker, that the wires are connected to. These terminals are where the conductors from the PV system connect inside the various combiner boxes, disconnects, inverters, and other pieces of electrical equipment. When you make calculations related to terminals, be sure to use Table 310.17.
Determine the maximum circuit current.
See the earlier “Defining the PV circuits’ maximum and continuous current” section for the how-to.
Calculate the continuous current requirement.
For help determining the continuous current requirement, refer to the related section earlier in this chapter. (Note that the continuous current requirement defines the OCPD value you need to use in the later “Sizing Overcurrent Protection Devices and Disconnects” section.)
Divide the value in Step 3 by the appropriate temperature-correction factor for the expected temperature the conductors will be exposed to from the 90 degrees Celsius (194 degrees Fahrenheit) column in Table 310.16 to find the corrected conductor ampacity required.
Choosing the temperature-correction factor from the 90 degrees Celsius (194 degrees Fahrenheit) column assumes you’re installing only conductors with 90 degrees Celsius (194 degrees Fahrenheit) ratings, as I suggest in the preceding section. If you want to use conductors rated at 75 degrees Celsius (167 degrees Fahrenheit), be sure to use that column of Table 310.16 instead.
Verify that the conductor selected has a large enough ampacity based on the lowest terminal ratings that will be used.
To do this, look at the ampacity value listed in the appropriate column in Table 310.17 (which consists of terminal temperature listings) and check that the ampacity value listed for the chosen conductor is greater than or equal to the continuous current value in Step 2.
I know how tricky these calculations can be to make, so I want to share an example with you. For the purposes of this example:
With this information, you can apply the previously described steps to determine the minimum conductor size necessary to satisfy the NEC®:
Find the maximum current.
8 strings in parallel × 5.9 A per string × 1.25 = 59 A
Determine the continuous current
59 A × 1.25 = 73.75 (round up to 74 A)
Derate for more than three current-carrying conductors.
In this example, all the PV source circuits are placed in parallel and a single PV output circuit leaves the combiner box. Therefore, no derate factor is applicable.
Apply the conditions of use.
74 A ÷ 0.87 = 85 A
You find the appropriate temperature derate factor from the bottom of Table 310.16. The 90 degrees Celsius (194 degrees Fahrenheit) column, which you use for THWN-2 conductors, has a temperature derate of 0.87 at 45 degrees Celsius.
Note: If the conductors were exposed to sunlight on a roof, you’d also used a factor from Table 310.15(B)(2)(c).
Check Table 310.16, using the value from Step 3.
4 AWG in the 90 degrees Celsius (194 degrees Fahrenheit) column at the top of Table 310.16 is the smallest conductor that exceeds 85 A. A THWN-2 conductor therefore has an ampacity value of 95 A.
Confirm that the conductor ampacity is large enough.
According to Table 310.17, 4 AWG conductors rated at 75 degrees Celsius (167 degrees Fahrenheit) — the terminal ratings — have an ampacity of 85 A. This value exceeds the continuous current value of 74 A from Step 2. You now know that a 4 AWG conductor installed in this location meets the NEC® requirements for ampacity and can safely carry current from this array.
You can follow this process for all the circuits used within a PV system. When calculating for circuits other than those on the PV side (the inverter output circuit, for example), you start at Step 1 with the maximum current value as given by the manufacturer as I describe in the earlier “Calculating non-PV circuits’ maximum current” section. You then proceed through the rest of the steps as normal.
The NEC® requires that the conductors you use in any PV system must be large enough to carry current from the source to the load safely, but no NEC® requirement dictates that you must deliver the power as efficiently as possible. As a PV system designer and installer, though, you want to make sure that the power supplied by the PV system is never reduced because the conductors are too small.
No matter how large you size the conductors in your system (see the previous section for guidelines), some amount of voltage drop will occur. As current flows in the conductors, resistance in the conductors fights that current flow. As you discover in Chapter 3, voltage has a direct relationship to current (which is measured in amps) and resistance via Ohm’s Law, which can be stated in several ways:
This interplay between current flow and resistance means you need to evaluate the conductors used in your system and make sure they aren’t so small that excessive resistance causes too much loss.
Because the NEC® doesn’t dictate the maximum amount of voltage drop, you get to decide which amount suits you best. Within the solar industry, the level of voltage drop is referred to in terms of the DC and AC sides of the system.
I show you how to calculate the voltage drop values for DC and AC circuits in the next sections. In both examples, I use Ohm’s Law and some given properties for copper conductors (but you can solve for any of the pieces of information as long as you can define all the other parts of the equation). Note: In the real world, you may need to take slight differences in the nature of AC circuits into account when calculating the AC voltage drop. For all practical purposes, though, using Ohm’s Law as I show you is accurate enough.
The first step in calculating the voltage drop from the PV array down to the inverter is to break down the individual parts of the PV circuit(s).
Note: By considering the longest PV source circuit length, you’ll be slightly more conservative for the shorter lengths, which results in slightly better performance in those circuits.
Before you can run your calculations, you need to collect the following information about the PV system:
Calculating the DC voltage drop requires you to apply the information you collected regarding the module specs and the conductor properties (length and resistance) to a form of Ohm’s Law a little differently than Herr Ohm intended (although if given the chance, I think he’d approve). The difference is that a length value is associated with the equation:
Suppose you have an array that consists of three strings of ten modules and all the strings are arranged on a roof in rows of ten. These three strings are all wired to a roof-mounted combiner box that runs down from the roof to the inverter mounted outside next to the utility meter and MDP. This setup means you have three PV source circuits running from the strings to the combiner box and a single circuit running the rest of the way out.
Each PV module is 36.2 V and 4.9 A, and the strings are wired with 12 AWG conductors. With all of this information, you can measure the total circuit length for the circuit and calculate the total voltage drop. In order to determine the voltage drop in the PV source circuit, you need to collect the following module and conductor information:
Here’s how to calculate the number of volts that will be lost in this circuit (in other words, the voltage drop, or Vdrop), using the preceding information:
This number indicates how many volts will be lost due to the resistance in the conductor. Your next step is to relate this voltage drop to a percentage of the entire circuit. To determine the voltage drop in a percentage, divide the calculated loss by the original Vmp value for the array:
Vdrop % = Vdrop / Vmp of the array
So when you apply the values calculated in the example, you get the following:
0.73 V ÷ (36.2 V × 10) = 0.73 V ÷ 362 V = 0.002 = 0.2%
This result indicates that a 0.2-percent voltage drop exists in the PV source circuits. To determine the voltage drop in the PV output circuit, repeat this process. If when you add these two voltage drop percentages together, the total voltage drop is less than your desired amount of 2 percent, the conductor sizes check out. If the total voltage drop is greater than your desired amount, you need to upsize one of the conductors to minimize the loss.
When you go to look at the voltage drop on the AC side, you use the exact same equation that I feature in the preceding section with different numbers for the voltage and current values.
Say you have an inverter that’s operating at 240 VAC and a maximum current output of 24 A. The inverter output circuit is 10 AWG, and the inverter is 75 feet from the MDP. To find the AC voltage drop in this example system, you need to collect the following information:
You can apply these values to the voltage drop equation in the preceding section:
To determine what this is in terms of a percentage value:
This percentage exceeds the recommended maximum voltage drop of 1.5 percent for utility-interactive systems, so in this case, I recommend looking at the next-largest size of conductor to minimize the effects of excessive voltage drop on this circuit.
Almost all conductors require proper protection. The exceptions are conductors used in PV source circuits and a type of conductor called ground wiring.) For PV systems, most conductors are run inside a conduit, which is either a metal or PVC tube that protects conductors from their surroundings.
After you establish the appropriate conduit type and the size and number of conductors you need to run, you can use the tables in Annex C of the NEC® to look up what size conduit is required. When you find the appropriate conduit table, you can then go to the appropriate section of that table — the one that lists your specific conductor type (for example, THWN-2). The tables then list all the available conductor sizes in a column. Find your conductor size and then move across the table to find the conduit that can hold the minimum number of conductors you want to use.
When wiring the components of a PV system, it’s your responsibility to protect the conductors from the possibility of too much current flowing through them. Enter overcurrent protection devices (OCPDs). These devices come in the form of either circuit breakers or fuses. The exact requirements and locations for OCPDs vary based on the current’s source (see Chapter 10 for details). In the sections that follow, I provide guidelines for basic OCPD sizing, as well as specifics for sizing OCPDs on PV and inverter circuits.
Note: You size disconnects exactly the way you size OCPDs, but for simplicity’s sake, I just refer to OCPDs in the following sections.
Believe it or not, in the process of sizing the PV system’s conductors, you also defined the required size of the OCPDs for the conductors. (It’s based off the continuous current requirement in Step 2 of the process described in the earlier “Putting together the details to determine conductor sizing” section.)
When you calculate an OCPD size, most likely it’ll be a value that isn’t commonly available. Fortunately, the NEC® allows you to round up to the next available OCPD size. These commonly available sizes can be found in Article 240.6 of the NEC®. In the example I use earlier to show you how to calculate the conductor size, the continuous current value was 74 A. OCPDs sized at 74 A aren’t regularly available, so the OCPD size you’d need to use for the circuit in question would be rated at 80 A (the next available size).
To put these limitations in perspective, if you run the calculations and determine that a 35 A OCPD is required for your installation, then you can’t use a 10 AWG conductor, even though in some situations that conductor has an ampacity value of 40 A.
Although you may be used to placing OCPD on each and every circuit you wire in a regular electrical system, placing OCPD in every PV source and output circuit isn’t an absolute requirement. When your system meets Article 690.9 of the NEC®, you can actually place two strings of PV modules in parallel without having to put OCPDs on either string. As soon as you add a third string, though, you should place OCPDs on the strings.
To meet NEC® requirements eliminating OCPDs on PV circuits, you first have to size your conductors to meet Article 690.8. Next, you can’t have any potential backed currents, current that can come back from sources such as batteries and inverters. (This is true when using grid-direct inverters, but if you’re using battery-based inverters, you won’t meet the requirements, so you have to use OCPD on all PV circuits.) Finally, the short circuit current (Isc) from all sources can’t exceed the ampacity of the conductors. (This last requirement is where the limit of two strings in parallel comes into play.)
The idea is, if you have three strings in parallel and a fault occurs on one of the strings (meaning that string becomes a load and starts accepting current), the Isc values from the other two strings (the external sources) will exceed the conductors’ ampacity and the modules’ rating.
As for the AC output of your inverter, you always need an OCPD for this circuit. A variety of options exist for installing this protection, with the most common being a circuit breaker located in the MDP. This circuit breaker serves as both a way to disconnect the inverter and a method of protecting the conductors. (Some installations call for a fused AC disconnect to be installed rather than a circuit breaker; I cover such installations in Chapter 17.)
To determine the amperage rating of the OCPD connected to the inverter, you need to refer to the inverter manufacturer’s specifications. Many inverter manufacturers list this value on their spec sheets. If you encounter one that doesn’t, you may need to dig into the installation manual; if nothing else, that should indicate the maximum OCPD sizing you can use in conjunction with the inverter.
18.224.63.87