34 Section 3
Measurement Methods Key Points to Consider When Determining the Method
Discrete
Effort
Fixed Formula
Weighted Milestone
Percent Complete
Physical Measurement
Apportioned Effort
Level of Effort
50/50, 25/75, 0/40/60, etc.—Using this method, work is credited for
EV as soon as it starts with a specific percent. (25/75 starts with 25%
being taken in the first period in which the method is used with 75%
taken when work is completed). Note that the real progress is invisible,
and this method can give a false sense of accomplishment. This
measurement method should only be used for work that spans two or
three reporting periods.
0/100—The 0/100 method does not incrementally credit EV for partial
work; therefore, the start of the work is not explicitly reported. This
measurement method should only be used for work that is scheduled to
start and complete within one reporting period.
The weighted milestone method has one or more milestones in the
measurement period. Each milestone has an objective, verifiable
accomplishment that is associated with it. The milestones are weighted
to reflect the relative accomplishment of the milestones against the
whole.
The percent complete method entails an estimate of the percent
complete of the BAC at each measurement point. There should be
measurable criteria associated with the percent complete
measurements, or they can be subjective and inaccurate.
The evaluation of work progress in the project work packages is related
to the physical nature. Whereas testing, measurement procedures,
and/or specifications should be explicit and be agreed upon in advance.
To use apportioned effort, the project manager should have pragmatic
knowledge and validated performance records to create the percentage
of apportioned effort pertaining to the discrete work package.
Level of effort (LOE) can be misused and distort the real progress of the
project, because the PV of the LOE determines EV for each reporting
period (there is never a schedule variance) no matter how much of the
work is actually performed.
Table 3-2. Key Points When Determining Measurement Methods
Discrete effort. Discrete effort is a tangible, measurable activity that is planned, measured, and yields a specific
output. Discrete effort is directly related to specific end products or services with distinct and measurable
points. Examples include pouring concrete for a bridge abutment or writing a user’s manual.
Four principal measurement methods are available for WPs classified as discrete effort. Measurement methods
used for discrete effort enable accurate measurement of work accomplished. The key is to measure the output