47
3.3.2.2 MANAGEMENT AND CONTINGENCY RESERVES
Contingency reserves are used for identified risks that are accepted and those risks for which contingent responses
are devised. These reserves can fund contingency plans when they need to be implemented or can fund a necessary
reaction to a risk after it occurs. Contingency reserves may be global to the overall project or may be allocated to
specific control accounts.
Contingency reserves are not used for the purpose of masking overruns. Instead, these reserves are determined as a
result of understanding identified risks and their potential impacts and are placed at the appropriate levels within the PMB.
While it is expected that contingency reserves will be consumed to accommodate evolving risk responses or realized
risk impact, there may be situations when the risk is either greater or lesser than initially estimated. In these cases, it is
appropriate that a variance be recorded. Based on existing OPAs, the project team may decide, especially when impacts
are significant, to adjust the future baseline through the change control process. The PMB is not going to be as effective as
a management tool when the baseline is significantly different from the plan the project team is following. When reserves,
whether too robust or not robust enough, have the team significantly off the baseline, the project team and stakeholders
should consider baseline changes. Often, OPAs and EEFs drive environments when the original baselines are maintained
for historical purposes while additional baselines are established for effective management of the remaining work.
The PMBOK
®
Guide, The Standard for Risk Management in Portfolios, Programs, and Projects [6], Practice Standard
for Project Risk Management [7], Practice Standard for Scheduling [8], and Practice Standard for Project Estimating
[9] cover additional information regarding the use of risk responses and reserves to address the impact of risks on the
cost, schedule, or scope baselines. When using EV, any risk response, which includes activities that expend budget,
needs to be assigned within a CA, and the activity captured in the project’s scope, schedule, and cost baselines.
3.3.3 SCOPE BASELINE
The scope baseline, comprised of the project scope statement, WBS, and WBS dictionary, aligns with work and
planning packages and provides information on all of the product and project deliverables against which execution
and delivery are compared. Scope realization data, generated from the accomplishment of project scope, should
be planned at the appropriate WBS activity level for WPs within the CAs. The basis for collecting the scope data is
determined by the measurement method selected. The criteria, sometimes called the rules of credit, are outlined and
documented during planning in the development of the project scope definition that is captured in the WBS dictionary
and the WP and activities. Consideration should be given to deliverable quality.
When planning the scope baseline, the project team should consider how the scope data will be collected. The
adequate measurement of the volume of scope accomplished based on a specific point in time and, especially at the
end of each project control period (e.g., week, month), should be considered. The collection of scope realization and