56 Section 3
3.4.2 ESTABLISHING THE PMB
The PMB consists of three baselines integrated into one. Typically, as part of setting the baseline, there is a process
(either documented in an OPA or called for in an EEF) where the work described under the baseline is authorized,
tracked, and funded. Additionally, as each CA is a segregated part of the project that is managed, the project team
frequently develops and maintains a CA plan that captures the specifics of the CA.
3.4.2.1 AUTHORIZE THE WORK
Authorization is the formal permission and direction to begin a specific project effort, which, typically, is a CA. It is a
method for sanctioning project work to ensure that the work is done by the identified organization, at the right time, in the
proper sequence, and within the approved baseline. In its simplest form, the work authorization process follows these steps:
Step 1. The project manager receives authorization to proceed with the project by means of a project charter
or customer contract/authorization. This authorization may include limits on the funds available to the project
manager, which is the amount of budget that is authorized.
Step 2. The project manager authorizes the next tier of management to proceed with the assigned work,
usually by issuing a work authorization document. Typically, this next level is the CA level, but there could
be one or more additional levels between the total project and the CAs. If so, each level receives its own
authorization and then continues the authorization within its prescribed, unbroken chain of authorization.
Step 3. In some organizations, functional manager concurrence or authorization may be required.
Step 4. The CA manager may authorize specific individuals to begin work and provide the scope, planned
budget (often in hours), and charge numbers required to be used.
3.4.2.2 PROJECT BUDGET LOG
The project budget log is the central repository for all project budgets. At any time, the project manager should
be able to review the project budget log and obtain a complete accounting of the value and classification for every
element of the project budget in addition to changes to the budget throughout the life of the project. As work is
authorized for control accounts, entries are made in the project budget log to show the movement of budget from the
undistributed budget to the distributed budget. When the entire project is authorized into control accounts (or control
accounts and summary-level budgets), the value of the undistributed budget will be zero. Within CAs, the budget is
authorized to work or planning packages. An example of the initial project budget log is shown in Figure 3-9. A broader
example is shown in Appendix X4.