157
Earned Schedule (ES). An earned value technique that measures the time at which planned value equals earned value.
Earned Value (EV). The measure of the work performed, expressed in terms of the budget authorized for that work.
Earned Value Management (EVM). A methodology that combines scope, schedule, and resource measurements to
assess project performance and progress.
Enterprise Environmental Factors (EEF). Conditions, not under the immediate control of the team, that influence,
constrain, or direct the project, program, or portfolio.
Estimate at Completion (EAC). The expected total cost of completing all work expressed as the sum of the actual
cost to date (AC) and the estimate to complete (ETC): EAC = AC + ETC.
Estimate at Completion (time) (EAC
t
). The expected total time of completing project work. EAC
t
is equal to the actual
time (AT) plus the estimate to complete (time) (ETC
t
) for the remaining work: EAC
t
= AT + ETC
t
.
Estimate to Complete (ETC). The estimated cost of completing the remaining work.
Independent Estimate at Completion (IEAC). A mathematical or statistical approach to project an EAC or a range of
EACs using EVM data. These EAC calculations are independent of any future project or environmental conditions, and
are not a replacement for a derived (bottom-up) project EAC.
Independent Estimate at Completion (time) (IEAC
t
). A mathematical or statistical approach to calculate a project
duration or range of durations using EVM data. Using earned schedule, the IEAC
t
is equal to the planned duration
divided by SPI
t
.
Independent Estimate to Complete (IETC). A mathematical or statistical approach to calculate a project completion
date or range of completion dates using EVM data. The IETC is equal to the project start date plus the IEAC
t
.
Level of Effort (LOE). A method of measurement used for support-type activities that does not produce definitive end
products that can be delivered or measured objectively.
Organizational Breakdown Structure (OBS). A hierarchical representation of the project organization that illustrates
the relationship between project activities and the organizational units that will perform those activities.
Organizational Process Assets (OPA). Plans, processes, policies, procedures, and knowledge bases that are specific
to and used by the performing organization.
Performance Measurement Baseline (PMB). An approved, integrated scope-schedule-cost plan for the project work
against which project execution is compared to measure and manage performance. The PMB includes contingency
reserve (CR), but excludes management reserve (MR).
Planned Value (PV). The authorized budget assigned to scheduled work.