100 Section 4
4.6.2 CHANGE ANALYSIS
Changes to the project or product scope impact the resources, schedule, and cost of a project. The change control
process should account for the analysis that a scope change entails. Changes that do not impact the scope, such
as changes to the schedule or the costs, still impact the PMB. The change control process needs to ensure that the
integrity of the integrated baseline is not compromised because of these changes or due to external dependencies
that these changes impact.
A change control board (CCB) is frequently used to analyze the impact of scope, schedule, cost, and other types
of changes on the project and the PMB. The only changes that are implemented are those that are approved by the
change control board. On small projects, the project manager may act as the CCB.
4.6.2.1 SCOPE CHANGE ANALYSIS
All scope changes should be analyzed, the scope should be defined, and the impact on the CAs should be assessed.
In addition, the need to add new or delete existing CAs should also be determined. Not all changes to the scope result
in a cost or schedule impact; however, given the integrated nature of the PMB, it is probable that a scope change will
impact the other two areas.
When the scope of the project is changed, such as adding new scope, the PMB should be changed at the WBS level
where the scope change occurs.
When new work is added to the CA, the new work should be placed into one or more new work or planning
packages. When an existing WP needs to be modified, it should first be closed, then the remaining budget plus new
budget should be placed in a new WP. In the latter case, when closing the CA, make the current budget (i.e., the
cumulative-to-date PV) equal to EV. This eliminates the schedule variance (i.e., no work remaining to be accomplished
in the CA), but the CV is maintained at whatever value it has. Actual costs should not be changed for a CA that is
closed due to a scope change. Preserving this cost information maintains the historical CV, which contributes to the
project’s overall CV. The cumulative PV cannot be changed without changes to the scope and corresponding budget.
Cumulative AC or EV cannot be changed either, except to correct prior errors.
Work scope, when moved from one CA to another, is always moved together with its corresponding budget since
each budget allocation is authorized specifically for the WBS element to which it is assigned. This maintains the
integrity of the PMB. Budget should never be transferred to eliminate variances as this undermines the reporting
metrics and jeopardizes effective monitoring and control.