38 ◾ Advances in Communications-Based Train Control Systems
2.12 CBTC Test Duration
e duration of the eld CBTC testing phase depends on various factors, and it
is not possible to dene test duration without knowing project specics. However,
based on the examples from projects in the last decade in dierent countries by dif-
ferent suppliers, a range of duration is provided in this section.
As discussed previously, CBTC projects are of two types: greeneld projects on
new lines and browneld projects on existing lines where revenue service must be
maintained during the project. For greeneld projects, the total duration of the proj-
ect can be planned in as little as 2 years, whereas the minimum time for a browneld
project is about 5 years. CBTC projects are often more dicult than anticipated
and important delays are very common, especially with browneld projects where a
5-year project is considered successful when executed in less than 7 years.
e experienced delay between the rst CBTC eld tests and the revenue service
is at least 1 year. For browneld projects where CBTC starts revenue service on a
section by section basis, the testing phase for the full line may last up to several years.
In order to have an earlier revenue service date, a common practice is to post-
pone the inclusion of advanced functions in the rst CBTC versions used for reve-
nue service. e advanced functions and subsequent changes are tested after the
CBTC starts revenue service. erefore, in addition to xing issues discovered dur-
ing rst months of revenue service, the supplier performs tests for these advanced
functions. It is worth noting that in many projects, CBTC testing is not completely
over when CBTC starts revenue service. Converging to the nal error-free service
may take as much time as original eld testing.
2.13 Constraints on Field Tests
Testing CBTC is a dicult task for several reasons. e most common issues
encountered are as follows:
◾ Diculty to obtain track access: is is especially true on browneld projects
where the line is already in revenue service. e tracks are used during the
day for revenue service operations and during the night or o-peak times
for maintenance. For greeneld projects, track access is relatively easier to
obtain, but still it is competitive because all other subsystems may also need
the tracks to complete their installation and tests.
◾ Coordination with the installation: During integration tests, where eld ele-
ments are veried one by one, a prerequisite is of course the equipment instal-
lation. e long-term planning, including the equipment installation order,
must be reviewed carefully to match with the test planning. Because CBTC
projects are very large with many stakeholders and companies involved,
itmay happen that testing is planned and testers discover that the equipment