Planning Fixed Task Costs

You might have a task cost that is independent of any resource. For example, the performance of a task could include printing costs for reports for a customer review meeting task or it could include the purchase of a flash drive for transferring the files for the development of a deliverable from one resource to another. Such a task cost can be some kind of "miscellaneous" or incidental cost on the task. If the cost does not need to be tracked as its own category, or if it’s only going to be incurred for a single task in the project, it might be a good candidate to be entered as a fixed cost for a task.

To enter a fixed cost for a task, follow these steps:

  1. Display the Gantt Chart or other task sheet.

  2. Click View, Table, Cost.

    The Cost table with the Fixed Cost and Fixed Cost Accrual fields is applied to the task sheet (see Figure 8-6).

    Apply the Cost table to enter fixed costs for tasks.

    Figure 8-6. Apply the Cost table to enter fixed costs for tasks.

  3. In the Fixed Cost field for the task, enter the cost.

  4. In the Fixed Cost Accrual field, specify when the cost should be accrued: at the beginning of the task, at the end, or prorated throughout the duration of the task. The planned fixed cost for the task is added to the planned cost for the task based on assigned resources and is shown in the Total Cost field.

Note

To set the default fixed cost accrual method, click Tools, Options and then click the Calculation tab. In the Default Fixed Costs Accrual list, select your preferred accrual method. This default accrual applies only to fixed costs for tasks, not resource costs.

You can also enter a fixed cost for the project as a whole. To do this, follow these steps:

  1. Display the Gantt Chart or other task sheet.

  2. Click View, Table, Cost.

    The Cost table is applied.

  3. Click Tools, Options and then click the View tab.

  4. Under Outline Options, select the Show Project Summary Task check box and then click OK.

    The project summary task row appears at the top of the view and includes rolled-up costs for tasks (see Figure 8-7).

    Add the project summary task to add a fixed cost for the entire project.

    Figure 8-7. Add the project summary task to add a fixed cost for the entire project.

  5. In the Fixed Cost field for the project summary task, enter the fixed cost for the project.

  6. In the Fixed Cost Accrual field, specify when the cost should be accrued: at the beginning of the project, at the end, or prorated throughout the duration of the project.

    The planned fixed cost for the project is added to all other costs calculated for assignments and tasks throughout the project. This total is shown in the Total Cost field of the project summary task.

As you see, when you enter a fixed cost for either a task or the entire project, all you need to do is enter the amount and you’re done. You’re not asked to enter what the cost is for. Because of this, it’s a good practice to document the fixed cost by entering a note. To enter a note about a fixed cost, follow these steps:

  1. Select the task (or the project summary task) for which you have entered a fixed cost.

  2. On the Standard toolbar, click Task Notes.

    Add the project summary task to add a fixed cost for the entire project.

    Task Notes

  3. On the Notes tab in the Task Information (or Summary Task Information) dialog box, enter a note that explains the fixed cost.

Add the project summary task to add a fixed cost for the entire project.

Notes indicator

To review notes that have been entered on a task, select the task and then click Task Notes again. In many tables, including the default Entry table, the notes icon appears in the Indicators column. Rest your mouse pointer over the notes icon to read the note (see Figure 8-8). You can also double-click the notes icon to open the Notes tab in the Task Information dialog box.

Rest your mouse pointer over the notes icon to read the note explaining details about the fixed cost.

Figure 8-8. Rest your mouse pointer over the notes icon to read the note explaining details about the fixed cost.

..................Content has been hidden....................

You can't read the all page of ebook, please click here login for view all page.
Reset
18.217.147.193