You might have a task cost that is independent of any resource. For example, the performance of a task could include printing costs for reports for a customer review meeting task or it could include the purchase of a flash drive for transferring the files for the development of a deliverable from one resource to another. Such a task cost can be some kind of "miscellaneous" or incidental cost on the task. If the cost does not need to be tracked as its own category, or if it’s only going to be incurred for a single task in the project, it might be a good candidate to be entered as a fixed cost for a task.
To enter a fixed cost for a task, follow these steps:
Display the Gantt Chart or other task sheet.
Click View, Table, Cost.
The Cost table with the Fixed Cost and Fixed Cost Accrual fields is applied to the task sheet (see Figure 8-6).
In the Fixed Cost field for the task, enter the cost.
In the Fixed Cost Accrual field, specify when the cost should be accrued: at the beginning of the task, at the end, or prorated throughout the duration of the task. The planned fixed cost for the task is added to the planned cost for the task based on assigned resources and is shown in the Total Cost field.
To set the default fixed cost accrual method, click Tools, Options and then click the Calculation tab. In the Default Fixed Costs Accrual list, select your preferred accrual method. This default accrual applies only to fixed costs for tasks, not resource costs.
You can also enter a fixed cost for the project as a whole. To do this, follow these steps:
Display the Gantt Chart or other task sheet.
Click View, Table, Cost.
The Cost table is applied.
Click Tools, Options and then click the View tab.
Under Outline Options, select the Show Project Summary Task check box and then click OK.
The project summary task row appears at the top of the view and includes rolled-up costs for tasks (see Figure 8-7).
In the Fixed Cost field for the project summary task, enter the fixed cost for the project.
In the Fixed Cost Accrual field, specify when the cost should be accrued: at the beginning of the project, at the end, or prorated throughout the duration of the project.
The planned fixed cost for the project is added to all other costs calculated for assignments and tasks throughout the project. This total is shown in the Total Cost field of the project summary task.
As you see, when you enter a fixed cost for either a task or the entire project, all you need to do is enter the amount and you’re done. You’re not asked to enter what the cost is for. Because of this, it’s a good practice to document the fixed cost by entering a note. To enter a note about a fixed cost, follow these steps:
Select the task (or the project summary task) for which you have entered a fixed cost.
On the Standard toolbar, click Task Notes.
On the Notes tab in the Task Information (or Summary Task Information) dialog box, enter a note that explains the fixed cost.
To review notes that have been entered on a task, select the task and then click Task Notes again. In many tables, including the default Entry table, the notes icon appears in the Indicators column. Rest your mouse pointer over the notes icon to read the note (see Figure 8-8). You can also double-click the notes icon to open the Notes tab in the Task Information dialog box.
Figure 8-8. Rest your mouse pointer over the notes icon to read the note explaining details about the fixed cost.
Troubleshooting
The rolled-up value for fixed task costs looks wrong
If you have fixed costs for individual tasks, and possibly a fixed cost for the project as a whole, these values are not rolled up into the project summary task or outline summary tasks.
Instead, the fixed costs for tasks and any resource costs are calculated and displayed in the Total Cost field for the individual tasks. In turn, the Total Cost field is rolled up in the project summary task, and that’s where you can see project cost totals (see Figure 8-9)
Figure 8-9. Fixed costs are not rolled up into summary tasks or the project summary task, enabling you to enter a fixed cost for a phase or the project as a whole.
The reasoning is that you might need to enter a fixed cost for a project phase, represented in a summary task. Likewise, you might need to enter a fixed cost for the project as a whole. Not rolling up totals in the Fixed Cost field makes it possible for you to do this, although at first glance it looks wrong. Keep your eye on the Total Cost field instead.
18.217.147.193