Setting When Resources Are Available for Work

It’s likely that many of your work resources will work full-time on your project. However, you might have some who work part-time, or who work part-time on your project because they’re being loaned from another group. You might have several individuals or machines (work resources) who perform the same function. You might also have a resource who will work full-time on your project until October, at which time she will be shared half-time with another project that is ramping up them. All of your work resources will take your designated holidays off, and most of them will take vacations and other days off throughout the year.

In Microsoft Project, you can account for all these different kinds of resource availability and working times to schedule resources most effectively and accurately for your project.

Setting Working Times and Days Off for Work Resources

The basis of setting the availability of resources on the project is the resource’s working time calendar, also simply known as the resource calendar. Each work resource has an individual resource calendar, which is initially based on the project calendar. You can customize each resource calendar as necessary to reflect the individual resource’s specific working times and days off. Because the resource calendar indicates when a resource is available to work on assigned tasks, it affects the manner in which tasks are scheduled.

Note

For more information about the project calendar, see the section titled Setting Your Project Calendar in Chapter 3.

Note

If you’re working with enterprise projects and enterprise resources, the calendars are set by the project administrator. Therefore, your ability to assign different calendars to resources might be limited.

Viewing a Resource Calendar

As soon as you create a resource, the project calendar is assigned by default as the resource’s working time calendar. To view a resource’s working time calendar:

  1. Display the Resource Sheet or other resource view.

  2. Click the resource whose working time calendar you want to view.

  3. On the Standard toolbar, click Resource Information.

  4. On the General tab in the Resource Information dialog box, click the Change Working Time button.

    Note

    In previous versions of Microsoft Office Project, the Resource Information dialog box had a Working Time tab. Now in Microsoft Office Project 2007, the Change Working Time button on the General tab opens the Change Working Time dialog box, which is the same as choosing Change Working Time on the Tools menu.

    The working time calendar for the selected resource appears (see Figure 6-10). The resource calendar is identical to the project calendar until you change it.

    Use the Change Working Time dialog box to view or modify an individual resource’s working times. These are the days and times when assigned tasks can be scheduled for this resource.

    Figure 6-10. Use the Change Working Time dialog box to view or modify an individual resource’s working times. These are the days and times when assigned tasks can be scheduled for this resource.

  5. To see the working times for a particular day, click on a date in the calendar thumbnail. The working times for that day appear to the right of the calendar.

  6. To see the working times and days off for a typical week, click the Work Weeks tab. Make sure that the [Default] row is selected and then click the Details button. In the Select Day(s) box, click the day of the week to see the working times in the grid to the right. When finished, click OK or Cancel.

  7. Click OK or Cancel in the Change Working Time dialog box and then click OK or Cancel in the Resource Information dialog box.

Applying a Different Base Calendar to a Resource

Microsoft Project comes with three base calendars: Standard, Night Shift, and 24 Hours. These base calendars are like calendar templates that you can apply to a set of resources, a set of tasks, or the project as a whole.

You can apply the base calendar you want for a resource. This can be useful if most of your team works the standard 8:00 A.M. to 5:00 P.M. day shift, but one or two of your resources work a graveyard shift. In that case, you can apply the Night Shift base calendar to those resources. To change which base calendar is applied to a resource, follow these steps:

  1. In the Resource Sheet or other resource view, double-click the resource whose working time calendar you want to change.

  2. On the General tab in the Resource Information dialog box, click the Change Working Time button.

  3. In the Base Calendar box, click the name of the base calendar you want to make the origin of the current resource’s calendar.

  4. Click OK in the Change Working Time dialog box and then click OK in the Resource Information dialog box.

Modifying a Resource Calendar

You can change an individual resource’s calendar to reflect a different work schedule from others on the project team. For example, most everyone on your team might work Monday through Friday, 8:00 A.M. until 5:00 P.M. But suppose one team member works just three days a week, and another team member works weekend nights. You can change their resource calendars to fit their actual work schedules. This way, their assigned tasks will be scheduled only when they’re actually available to work on them.

A resource might need an alternative work week specified for a particular period of time. One example might be a trainer working a combination of day, swing, graveyard, and weekend shifts throughout the next two weeks to train individuals on those shifts.

You can also update resource calendars to reflect team member work week exceptions such as vacation time, personal time off, sabbaticals, and so on. Updating the resource calendars helps keep your schedule accurate.

Note

For more information about changing base calendars, including specifying the normal work week, alternative work weeks, one-time calendar exceptions, and recurring calendar exceptions, see the section titled Modifying a Base Calendar in Chapter 3.

Creating a New Base Calendar for Resources

If you find you’re making the same modifications to individual resource calendars repeatedly, you might do well to create an entirely new base calendar and apply it to the applicable resources. If you have a group of resources who work a different schedule, for example, a weekend shift or "four-tens," create a new base calendar and apply it to those resources.

Note

For details, see the section titled Creating a New Base Calendar in Chapter 3.

When you create a new base calendar, it becomes available in any of the three calendar applications: project calendar, task calendar, or resource calendar. To apply the new base calendar to a resource, follow these steps:

  1. Display the Resource Sheet or other resource view.

  2. Double-click the resource to whom you want to assign the new base calendar.

  3. In the Resource Information dialog box, click the Change Working Time button.

  4. In the Base Calendar field, select the base calendar you want to apply to the selected resource.

  5. Make any additional changes to the calendar as needed for this resource.

    These changes apply only to the selected resource; they do not change the original base calendar.

You can also set your resource working times using the Project Guide. On the Project Guide toolbar, click Resources. In the Project Guide pane, click the Define Working Times For Resources link. Read the succeeding panes and make choices as directed (see Figure 6-11).

The Resource Working Times pane of the Project Guide assists you through the process of setting resource calendars.

Figure 6-11. The Resource Working Times pane of the Project Guide assists you through the process of setting resource calendars.

Specifying Resource Availability with Max Units

Suppose that your team includes three full-time resources, one half-time resource, and another who is available three days each week or 60 percent of the time.

You can specify this kind of resource availability by setting the resource’s maximum units, which you might also think of as resource units.

By definition, the full-time resources are each available at 100% max units. The half-time resource is available at 50%maximum units. The other part-timer is available at 60% max units. When you assign resources to tasks, those tasks are scheduled according to that resource’s availability and indicates the point when the resource is considered overallocated.

But 100 percent or 50 percent of what, you might ask? The max units setting is multiplied by the availability shown in the resource calendar of working time and days off to determine the maximum level of availability of this resource on this project. If a resource calendar reflects a 40-hour work week, then 100% max units means a 40-hour work week for this project, while 50% max units means a 20-hour work week for this project (see Figure 6-12).

Given the same 40-hour-per-week resource calendar, a 100% max units resource works 8 hours per day, while a 50% max units resource works 4 hours per day.

Figure 6-12. Given the same 40-hour-per-week resource calendar, a 100% max units resource works 8 hours per day, while a 50% max units resource works 4 hours per day.

Likewise, if a resource calendar reflects a 20-hour work week, then 100% max units means a 20-hour work week while 50% max units for this resource would be a 10-hour work week. Again, max units plays against the resource calendar. Figure 6-13 illustrates the schedules for these two scenarios.

Given the same 20-hour-per-week resource calendar, a 100% max units resource works 4 hours per day, while a 50% max units resource works 2 hours per day.

Figure 6-13. Given the same 20-hour-per-week resource calendar, a 100% max units resource works 4 hours per day, while a 50% max units resource works 2 hours per day.

Here’s another scenario: Suppose that you have three engineers, two architects, and four drafters, all working a full-time schedule. Instead of naming them individually, you decide you want to name your resources by their functions and consolidate them into a single resource representing multiple individuals. You can do that with max units as well. The three engineers together are available at 300 percent, the two architects at 200 percent, and the four drafters at 400 percent.

If you have three full-time drafters and one half-time drafter, your Drafter resource is available at 350% max units.

To enter max units, simply type the percentage in the Max. Units field in the Resource Sheet (see Figure 6-14). The default for the Max. Units field is 100%.

You can enter max units when you enter resource names, or come back to it later.

Figure 6-14. You can enter max units when you enter resource names, or come back to it later.

Now, suppose your staffing plan specifies that you’ll start the project life cycle needing four drafters. After three months, you’ll need only three drafters. Two months later, you’ll need only one. To specify variable resource quantity or availability over time, follow these steps:

  1. In the Resource Sheet, double-click the resource whose maximum units you want to adjust.

    The Resource Information dialog box appears. Make sure the General tab is displayed.

  2. In the Resource Availability table, enter the first date range for the resource’s first max units specification.

    That is, enter the beginning date in the first Available From field, the ending date in the first Available To field, and the max units that will be available during those dates in the Units field. For example, in the first row enter 4/2/07 under Available From; enter 6/29/04 under Available To; enter 400% under Units.

  3. In the second row, enter the second date range for the resource’s max units specification.

    For example, enter 7/2/07 under Available From; enter 9/21/07 under Available To; enter 300% under Units.

  4. Continue in this manner until your entire resource availability specification is set.

    For example, enter 9/24/07 under Available From; enter 10/26/07 under Available To; enter 100% under Units (see Figure 6-15).

    Use the Resource Availability table in the Resource Information dialog box to specify multiple levels of max units throughout the project.

    Figure 6-15. Use the Resource Availability table in the Resource Information dialog box to specify multiple levels of max units throughout the project.

Note

By default, maximum units are expressed as a percentage. You can represent them as a decimal if you prefer. Click Tools, Options and then click the Schedule tab. In the Show Assignment Units As A box, select Decimal. Now, instead of 100%, one full-time resource is shown as having 1 max unit.

Note

You can enter max units with varying availability and a customized resource calendar for equipment resources just as you can for human resources. Both equipment and human resources are considered work resources. Setting equipment working times and availability can help account for other projects using the same equipment at different times, and schedule downtime for preventive maintenance.

..................Content has been hidden....................

You can't read the all page of ebook, please click here login for view all page.
Reset
18.191.189.23