Representing Project Data in a Visio Diagram

If you decide to build a project directly in Visio, or if you plan to export Microsoft Project information to a Visio diagram, it’s helpful to understand how the four Visio templates for schedules work. The templates that apply to projects or other date-related information include the following:

  • Timeline. The Timeline template displays tasks and events in a way that Microsoft Project does not. It shows them along a horizontal or vertical bar. This can be useful, for example, to summarize the phases of a multiyear project and key milestones toward its completion.

  • Gantt Chart. Although you can use Visio to build simple Gantt charts, it is more useful as a presentation tool when you’re using data exported from Microsoft Project.

  • PERT Chart. The Microsoft Project Network Diagram view is a much better option than its Visio PERT Chart counterpart, because Microsoft Project calculates start and finish dates for tasks in addition to showing the hierarchy of tasks.

    Note

    For more information about using the PERT Chart in Microsoft Project, see the section titled Working with Network Diagrams in Chapter 4.

  • Calendar. Although the Calendar template is a member of the Schedule category in Visio, it doesn’t integrate with Microsoft Project. You can build calendars for special events within a project, but, to show the work that’s scheduled for a project, the Calendar view in Microsoft Project is a better tool.

    Note

    For more information about the Microsoft Project Calendar view, see the section titled Working with Graph Views in Chapter 4.

Using the Visio Timeline Template

The Visio Timeline template summarizes the time span for phases and tasks, and highlights milestones along the horizontal or vertical timeline. By expanding portions of a timeline, you can emphasize critical portions of a project.

Configuring the Time Period and Time Format

Configure the time period and time format for a timeline by doing the following:

  1. Right-click a timeline shape, such as Block Timeline or Cylindrical Timeline, and then click Configure Timeline on the shortcut menu.

  2. In the Configure Timeline dialog box (see Figure 19-11), under Time Period, type the start and finish dates for the time period that the timeline represents. If the timeline spans a short period, you can specify the start and finish times, too.

    The Configure Timeline dialog box contains controls for specifying the start and finish dates and time intervals for a timeline.

    Figure 19-11. The Configure Timeline dialog box contains controls for specifying the start and finish dates and time intervals for a timeline.

  3. In the Time Scale dropdown list, choose the time interval to show on the timeline, such as Months. When you select Quarters, you can also specify the Start Fiscal Year On date. For Weeks, you can specify the first day of the week.

  4. Specify the date format by choosing a language in the Timeline Language box on the Time Format tab.

  5. Control whether dates and times appear on a timeline by clicking the Time Format tab and selecting the check boxes that control whether the start date, finish date, and interim time scales appear. In addition, you can select the date format for dates and specify whether interim marks show the date or only tick marks.

Configuring a Timeline Interval

Configure an interval within a timeline, for example, to adjust the phases of a project or the duration of a task, by doing the following:

  1. Right-click an Interval shape, such as Block Interval, and then click Configure Interval on the shortcut menu.

  2. In the Configure Interval dialog box, specify the start date and finish dates, and optionally, the start and finish times.

  3. In the Description box, type the text that you want within the interval.

Configuring Milestones

Configure milestones for events or key dates by doing the following:

  1. Right-click a Milestone shape, such as Diamond Milestone, and then click Configure Milestone on the shortcut menu.

  2. In the Configure Milestone dialog box, specify the date (and, optionally, the time) in the Milestone Date box.

  3. In the Description box, type the text for the milestone.

Expanding a Portion of a Timeline

For a multiyear project, activities that span only a few days or weeks are barely visible in a timeline, but they might nevertheless be essential to success. By adding Expanded Timeline shapes to a timeline diagram, you can display more detail for a small portion of the total project. Furthermore, you can expand a timeline to more than one level.

To expand a timeline, follow these steps:

  1. From the Timeline Shapes stencil, drag the Expanded Timeline shape onto the drawing.

  2. In the Configure Timeline dialog box, specify the start and finish dates for the expanded timeline, and optionally, the start and finish times as well. The dates that you specify for the expanded timeline must be within the date range of the overview timeline.

  3. In the Time Scale box, select the time intervals the expanded timeline covers.

  4. Click OK to add the expanded timeline to the drawing. Visio adds milestones, intervals, and date markers that occur during the expanded time period.

Synchronizing Milestones and Intervals

Visio synchronizes milestones and intervals between higher-level and expanded timelines, but you can synchronize milestones and intervals across any number of timelines on a page. To synchronize a milestone or interval with another, follow these steps:

  1. Select the milestone or interval you want to synchronize or drag the Synchronized Milestone or Synchronized Interval shape onto the timeline.

  2. Click Timeline, Synchronize Milestone or Timeline, Synchronize Interval.

  3. In the Synchronize With dropdown list, select the other milestone or interval with which to synchronize.

  4. Select the date format, if necessary, and click OK. A gray dotted line shows the synchronization between the milestones or intervals.

Using the Gantt Chart Template

Just as in Microsoft Project, in a Visio Gantt Chart, task data appears in both a table as well as a chart of task bars, milestones, and other symbols that represent the relationships and schedule of project tasks. The major difference, of course, is that a Visio Gantt Chart does not calculate start and finish dates, resource assignments, costs, and other project management information. For this reason, the Visio Gantt Chart template is best for presentations or status reports. If you don’t have easy access to Microsoft Project, you can add shapes to a Visio drawing to build a Gantt Chart.

Whether you import a Visio Gantt Chart from Microsoft Project or build one from scratch, you can modify the Gantt Chart in Visio in the following ways:

  • Add task bars and milestones by dragging Row, Task Bar, and Milestone shapes onto a Gantt Chart frame or by clicking Gantt Chart, New Task. Type the name of the new task along with the start date, finish date, duration, and any other task information.

  • Delete tasks by selecting the tasks and then clicking Gantt Chart, Delete Task.

  • Rename a task by double-clicking the task name, typing the new name, and pressing Esc.

  • Add project fields, such as Resource Names or % Complete, in the table area of the Gantt Chart by right-clicking a Gantt Chart frame and then clicking Insert Column on the shortcut menu. In the Insert Column dialog box, click the field you want to add.

  • Remove a column from the table by clicking anywhere in the column and then clicking Gantt Chart, Hide Column.

  • Indent and outdent tasks to specify summary tasks and their subtasks.

  • Link tasks by using the Link Lines shape to show dependencies between predecessor and successor tasks.

  • Specify the working days and hours for your project team by clicking Gantt Chart, Configure Working Time. The Configure Working Time dialog box appears (see Figure 19-12). Then, select the check boxes for work days and click the times in the Start Time and Finish Time boxes.

    You can specify working days and times in the Configure Working Time dialog box.

    Figure 19-12. You can specify working days and times in the Configure Working Time dialog box.

  • Annotate the Gantt Chart for presentations by adding Title, Legend, Text Block, and Horizontal Callout shapes.

  • Configure the Gantt Chart time units, duration, and timescale by clicking Gantt Chart, Options, clicking the Date tab, and then choosing the settings you want, such as the start and finish dates for the Gantt Chart.

  • Format task bars, milestones, and summary task bars by clicking Gantt Chart, Options and then clicking the Format tab.

  • Change start date, finish date, and duration by typing values in the fields in the table within the Gantt Chart shape or by dragging task bars in the chart area. Dragging task bars is quick, but typically not as accurate as typing values. You can also show progress by dragging the yellow control handle on the left side of a task bar toward the right.

Using the PERT Chart Template

Program Evaluation and Review Technique (PERT) charts display project tasks as a network or hierarchy of boxes, much like a work breakdown structure. However, always keep in mind that the Visio PERT Chart is primarily designed for presentation, not actual project management. It does not calculate start dates, finish dates, or durations. If you need to use a PERT Chart as a project management tool rather than just a communications tool, use the Network Diagram in Microsoft Project.

To build a PERT Chart in Visio, drag shapes onto the drawing and type values in the boxes. There’s no wizard for transferring information between Microsoft Project and Visio PERT Charts. However, you can use the data features in Office Visio Professional to link boxes on a diagram to data in a Microsoft Project database.

..................Content has been hidden....................

You can't read the all page of ebook, please click here login for view all page.
Reset
18.221.99.174