Updating Actual Costs

When you enter progress information for tasks or assignments, by default, the costs associated with those tasks and assignments are calculated accordingly.

Updating Actual Costs for Work Resources

If your assigned work resources (people and equipment) are associated with cost rates or per-use costs, when you enter progress information on their tasks or assignments, not only is actual work calculated, but actual costs are as well.

Updating Actual Costs for Material Resources

If you have entered costs for material resources, actual costs are also calculated based on the completion of the task.

If you need to, in the Actual Work field, you can change the value for the material by specifying the amount of material actually used. Material is measured by its material label, for example, board feet, cubic yards, or cartons, while the Work and Actual Work fields use a time unit such as hours or days for work resources. However, you can edit the Work or Actual Work fields for material resource assignments in the Task Usage view, Resource Usage view, or Tracking tab on the Assignment Information dialog box (see Figure 10-18).

You can enter the actual amount of material used or the actual cost for the material on the Tracking tab in the Assignment Information dialog box.

Figure 10-18. You can enter the actual amount of material used or the actual cost for the material on the Tracking tab in the Assignment Information dialog box.

Updating Actuals for Cost Resources

When you specify a percentage complete for a task, the work amount and costs for any assigned work and costs for any material resources are calculated automatically. So are any fixed costs associated with the task.

However, any assigned cost resources are not included in this automatic calculation of actual costs. You can only enter progress for cost resources on the assignment level. To do this, follow these steps:

  1. In the Task Usage or Resource Usage view, double-click the assignment of the cost resource to the task.

  2. In the Assignment Information dialog box, click the Tracking tab.

  3. Even though cost resources are not associated with work, you can enter a percentage in the % Work Complete field, and an actual cost amount will be calculated.

    For example, if a cost resource assigned to a task is set to $100, and you enter 50% in the % Work Complete field, the actual cost will be calculated as $50.

  4. If the task is 100% complete and the total cost for the cost resource has been incurred, enter that cost in the Actual Cost field.

Updating Actuals for Fixed Costs on Tasks

When you enter progress information on a task that includes a fixed cost, the actual fixed cost is calculated with the progress according to the accrual method you selected (start, finish, or prorated).

If a fixed cost has changed from your original setting, simply change the amount. In a task sheet, apply the Cost table and then change the amount in the Fixed Cost field for the task.

Manually Updating Project Costs

If resources are assigned to tasks in your project plan, and those resources also have their costs entered in Microsoft Project, costs are updated whenever you enter actual progress information. For example, suppose that a $25/hour resource is assigned to 8 hours of work on a task. When you enter that the task is 50 percent complete, $100 of actual cost is recorded for this task.

If you do not want Microsoft Project to calculate costs for you in this manner, you can turn off this option and enter costs yourself. To turn off automatic cost calculation, follow these steps:

  1. Click Tools, Options and then click the Calculation tab.

  2. Clear the Actual Costs Are Always Calculated By Microsoft Office Project check box.

  3. By default, any edits you make to cost will be distributed evenly across the actual duration of a task.

    If you would rather distribute the costs to the status date, select the Edits To Total Actual Cost Will Be Spread To The Status Date check box.

To enter task costs manually, display a task sheet and click View, Table, Cost to apply the Cost table. Enter total actual costs in the Actual field for the task.

To manually enter timephased costs for tasks or assignments, display the Task Usage view. Click Format, Details, Actual Cost to add the Actual Cost field to the timephased portion of the view.

Note

It can be cumbersome and tricky to update costs manually. You’ll experience more accurate results if you enter work resources and their costs in your project plan, along with any cost resources and fixed costs of tasks. When you assign those resources to tasks, costs are forecasted. When you enter progress on tasks, actual costs are calculated.

..................Content has been hidden....................

You can't read the all page of ebook, please click here login for view all page.
Reset
18.116.21.239