Sharing Resources by Using a Resource Pool

Typically, when you create a project file, you set up and schedule your tasks and then add resources and assign tasks to them. Often, however, resources are assigned to tasks in multiple projects. You might be the manager of these different projects and use the same resources in all of them. Or multiple project managers might share the same resources for their projects.

To prevent conflicts between projects and avoid resource overallocation among multiple projects, you can create a resource pool. A resource pool is a project file that’s devoted to maintaining information about resources, including their availability, costs, and current usage or allocation.

Any project manager who wants to use the resources in the resource pool file can link the project file to the resource pool file and make the project file a sharer file. When you link a project file to the resource pool file, the resource names and other information appear in your project file. You can then assign those resources to tasks as if you originally created them in this project file.

Setting Up a Resource Pool

Resource pools are easier to manage in the long run if you have a project file whose only job is to serve as the resource pool file. However, if all the resources you need for the pool are already in a project you’re executing, you can use that as your resource pool file as well.

To create a resource pool in its own dedicated project file, follow these steps:

  1. On the Standard toolbar, click New.

    A new project window appears.

  2. Click View, Resource Sheet.

  3. Enter the information for all work or equipment resources you want to be included in the resource pool.

    This information should include at least the resource name, maximum units, and standard rate. If different from the default, also enter the cost per use, cost accrual method, and calendar. Enter the initials, group, and overtime rate if such information is applicable to your projects.

  4. If you want material resources to be a part of your resource pool, enter at least the material resource names, identify them as material resources, and then enter the material labels and the unit costs.

  5. If you want cost resources to be a part of your resource pool, enter at least the cost resource names and identify them as cost resources.

  6. On the Standard toolbar, click Save. Select the drive and folder in which you want to store the resource pool file.

    Setting Up a Resource Pool

    Save

    If other project managers will be using this resource pool, make sure that you save the file in a location to which you all have access, such as a central file server or a shared folder.

  7. Enter a name for the resource pool file in the File Name box and then click the Save button.

    Give the resource pool file a name that identifies it as such, for example, ResPool.mpp or Marketing Resources.mpp.

    Note

    For more information about entering resource information, see Chapter 6.

If you already have resource information in an existing project file, you can use it to create your resource pool file and cut down on your data entry. One method for doing this is to copy the existing project file and then delete the task information from the new copy. To do this, follow these steps:

  1. Open the project file that contains the resource information you want to use.

  2. Click File, Save As.

  3. Select the drive and folder in which you want to store the resource pool file.

  4. Enter a unique name for the resource pool file in the File Name box and then click the Save button.

  5. Display the Gantt Chart or other task sheet.

  6. Click the Select All box in the upper-left corner of the sheet, above the row 1 header.

    The entire sheet is selected.

  7. Press the Delete key.

    All task information is deleted.

  8. Display the Resource Sheet and check the resource information.

    Update any information as necessary, including adding or removing resources.

  9. On the Standard toolbar, click Save.

Another method of using existing resource information is to copy and paste information from the existing project files to the new resource pool file. To do this, follow these steps:

  1. Open the project file that contains resource information you want to copy.

  2. Display the Resource Sheet.

  3. Select resource information by selecting the row headers.

    To select adjacent resource rows, drag from the first to the last row header. Or click the first row, hold down the Shift key, and then click the last row.

    To select nonadjacent resource rows, click the first row header. Then hold down the Ctrl key and click all other rows you want to select.

    Be sure to select the row headers, not just the task names. Selecting row headers copies all the necessary information—including maximum units and costs—associated with the resource, even if that information isn’t displayed in the sheet.

  4. On the Standard toolbar, click Copy.

    Setting Up a Resource Pool

    Copy

  5. On the Standard toolbar, click New.

    A new project window appears.

  6. Display the Resource Sheet.

  7. On the Standard toolbar, click Paste.

    Setting Up a Resource Pool

    Paste

    The resource information you copied from the other project file is inserted into the appropriate fields in the Resource Sheet.

  8. Click File, Save As.

  9. Select the drive and folder in which you want to store the resource pool file.

    Enter a name for the resource pool file in the File Name box and then click Save on the Standard toolbar.

Linking a Project to Your Resource Pool

After the resource pool is set up, you can link project files to it. The project file that uses a resource pool is called the sharer file. As long as the resource pool and the sharer file are open at the same time, the resources in the resource pool file appear in the sharer file as if they were originally entered there. Even if you have resources in your project file, you can still use resources from the resource pool.

To link your project to a resource pool, follow these steps:

  1. Open the resource pool file.

  2. Open your project file that you want to share resources from the resource pool.

    In this project file, click Tools, Resource Sharing, Share Resources.

    The Share Resources dialog box appears (see Figure 14-10).

    Use the Share Resources dialog box to specify that you want your project file to use the resource pool.

    Figure 14-10. Use the Share Resources dialog box to specify that you want your project file to use the resource pool.

  3. Select the Use Resources option.

  4. In the From list, click the name of the resource pool file. All open files are displayed in this list.

  5. Specify how you want any resource information conflicts to be handled.

    If you want the resource pool information to be the final authority in a conflict, select the Pool Takes Precedence option. This is the default, and it is the recommended option.

    If you want the resource information in the sharer file (your project file) to be the final authority, select the Sharer Takes Precedence option.

  6. Click OK. Your project file is now designated as a sharer file of the resource pool, thereby linking the two.

    Now all resource information in the resource pool appears in your project file (see Figure 14-11), and any resource information in your project file is added to the resource pool.

    With the resource pool and sharer file linked, the resource information for both files is merged.

    Figure 14-11. With the resource pool and sharer file linked, the resource information for both files is merged.

You can now work with your project file and the resources as usual, including assigning resources from the pool to tasks. Be sure to save both the sharer file and the resource pool file because you’re saving the link between the two. You’re also saving any resource information from your sharer file as additional resources in the resource pool.

Note

You can make a regular project file into a resource pool file. Open the project file you want to use as a resource pool file. Also open the project file that is to become the sharer file. In the sharer file, click Tools, Resource Sharing, Share Resources. Select the Use Resources option and then select the other project file in the From list.

Although making a regular project file into a resource pool can be convenient at first, keep in mind that when the project ends, the assignments will still be a part of the resource pool file, even though they’re no longer relevant.

The next time you open your sharer file, you’ll be prompted to open the resource pool also (see Figure 14-12).

If you choose to open the resource file, you’ll be able to see all resources, including their assignments, in your sharer file.

Figure 14-12. If you choose to open the resource file, you’ll be able to see all resources, including their assignments, in your sharer file.

Click OK to open the resource file. It’s opened with read-only privileges. If you select the Do Not Open Other Files option, the resources you’re using from the resource pool do not appear.

If you open a resource pool file before opening any of its sharer files, you are prompted to select whether you want read-only or read-write privileges in the resource pool file (see Figure 14-13).

You see this alert whenever you directly open a resource pool file. Specify whether you want to open the resource pool as read-only or read-write.

Figure 14-13. You see this alert whenever you directly open a resource pool file. Specify whether you want to open the resource pool as read-only or read-write.

Select the first option to open the resource pool as a read-only file. This is the default, and you should use this option in most cases. You can still update assignment information when working with a read-only resource pool.

Select the second option to open the resource pool as a read-write file. Choose this option when you need to explicitly change basic resource information such as cost or group information. Only one user can open a resource pool as a read-write file at one time.

Select the third option to open the resource pool as a read-write file along with all of its sharer files. These files will be combined into a master project file.

Checking Availability of Resource Pool Resources

Display the Resource Usage view or the Resource Graph in the resource pool file to check the availability of resources across all sharer projects. In these views, you can see all the assignments for all the resources in the resource pool. You can see the amount of time they’re assigned, if they’re overallocated, or if they have time available to take on more assignments.

Note

For more information about checking resource allocation, see the section titled Monitoring and Adjusting Resource Workload in Chapter 11.

When assigning resources to tasks, you can also use the filters in the Assign Resources dialog box to find resources with the right skills and availability (see Figure 14-14).

Use the Assign Resources dialog box to check resource availability while making assignments.

Figure 14-14. Use the Assign Resources dialog box to check resource availability while making assignments.

For example, you can find only those resources from the resource pool who are associated with a particular defined group. Or you can list only material resources. You can also specify that you just want to see a list of resources who have at least 16 hours of availability across all the projects to which they’re assigned.

Note

For more information about filtering resources and reviewing availability graphs, see the section titled Assigning Work Resources to Tasks in Chapter 7.

You can see more availability information about a resource by selecting the name in the dialog box and then clicking the Graphs button. Review the Work, Remaining Availability, or Assignment Work graphs.

Updating Resource Pool Information

If you need to change resource-specific information—such as cost information, notes, maximum units, or working time calendar—you need to open the resource pool file with read-write privileges and change the information. After you save these changes, the next time any users of the sharer files open the resource pool or refresh their resource pool information, they’ll see the updated information.

If you’re changing resource assignments, there’s more flexibility. You can open the resource pool file with read-only privileges, access all your resource information, and change assignment information as needed. When you start to save the sharer file, a message appears, asking if you want to update the resource pool with your changes (see Figure 14-15). Click OK. Even though the resource pool is read-only, it’s updated with your changes at that moment. Any other users of the resource pool will see the changes the next time they open the resource pool or when they refresh the open resource pool.

This message appears when you’re working with a read-only resource pool and you make changes that affect resources in the pool.

Figure 14-15. This message appears when you’re working with a read-only resource pool and you make changes that affect resources in the pool.

Another way to update the resource pool after making assignment changes is to click Tools, Resource Sharing, Update Resource Pool.

If you’re working with a sharer file and the resource pool that others also use, it’s a good idea to periodically refresh the resource pool to make sure that you have the latest changes to resource and assignment information. Click Tools, Resource Sharing, Refresh Resource Pool.

Disconnecting a Resource Pool from a Project Plan

If you no longer need the resource pool and the sharer file to be linked, you can disconnect them, as follows:

  1. Open both the resource pool and the sharer file.

  2. Display the sharer file.

  3. Click Tools, Resource Sharing, Share Resources.

  4. Select the Use Own Resources option.

The resources assigned to tasks in the sharer project remain in the project file. Any assignment information for these resources is removed from the resource pool file.

You can also disconnect the link from within the resource pool, as follows:

  1. Open the resource pool.

  2. Click Tools, Resource Sharing, Share Resources. The Share Resources dialog box opens (see Figure 14-16).

    In the resource pool, the Share Resources dialog box shows the path of all sharer files.

    Figure 14-16. In the resource pool, the Share Resources dialog box shows the path of all sharer files.

  3. In the Sharing Links box, click the name of the sharer file that you want to disconnect from the resource pool.

  4. Click the Break Link button.

..................Content has been hidden....................

You can't read the all page of ebook, please click here login for view all page.
Reset
18.191.147.77