Working with Task Calendars

The scheduling of your tasks is driven by task duration, task dependencies, and constraints. It’s also driven by the project calendar. If your project calendar dictates that work is done Monday through Friday, 8:00 A.M. until 5:00 P.M., initially that’s when your tasks are scheduled.

Note

For more information about calendars, see the section titled Setting Your Project Calendar in Chapter 3.

However, if a task is assigned to a resource who works Saturday and Sunday, 9:00 A.M. until 9:00 P.M., the task is scheduled for those times instead. That is, the task is scheduled according to the assigned resource’s working times calendar rather than the project calendar.

Sometimes, you have a task that needs to be scheduled differently from the working times reflected in the project calendar or the assigned resource calendars. For example, you might have a task that specifies preventive maintenance on equipment at specified intervals. Or you might have a task being completed by a machine running 24 hours a day. In any case, the task has its own working time, and you want it to be scheduled according to that working time rather than the project or resource working time so it can accurately reflect what’s really happening with this task.

Note

Unlike project or resource calendars, which are essential to the accuracy of your schedule, task calendars are more of an optional scheduling feature. Create and apply task calendars only in those special situations when a task has its own unique schedule that tends to be independent of the project or assigned resource calendar.

Setting Up the Task Calendar

To have a task scheduled according to its own working times, you must first set up the calendar. You can use or adapt a built-in base calendar, which is like a calendar template you can apply to the project as a whole, to resources, or in this case, to tasks. If the task’s working times are quite different from anything available in the existing base calendars, you can create your own.

Note

For specific procedures on modifying an existing base calendar, see the section titled Modifying a Base Calendar in Chapter 3. To create a new base calendar, see the section titled Creating a New Base Calendar in Chapter 3.

Note

When creating a base calendar to be used as a task calendar, give the new base calendar a specific name that indicates its role as a task calendar. This makes the differences among the base calendars very clear to you (and possibly other project managers) to prevent confusion and the application of the wrong calendars for the wrong purposes.

Note

If you have a set of tasks that are carried out entirely by equipment on the equipment’s own schedule, an alternative to creating a task calendar is to set up the equipment as a work resource. You can then apply a working times calendar to the equipment resource and assign the equipment resource to the appropriate tasks.

Note

For more information about creating work resources, see the section titled Adding Work Resources to the Project in Chapter 6.

Assigning a Base Calendar to a Task

To assign a base calendar to a task, follow these steps:

  1. Select the task to which you want to assign a base calendar.

  2. On the Standard toolbar, click Task Information and then click the Advanced tab.

  3. In the Calendar box, click the name of the calendar you want to assign to this task. All base calendars are listed, including ones you have created yourself.

  4. Click OK.

Assigning a Base Calendar to a Task

Task Calendar indicator

A task calendar icon appears in the Indicator column. If you rest your mouse pointer over the indicator, a ScreenTip displays the name of the assigned calendar (see Figure 5-23). Follow this same procedure to change to a different task calendar or to remove the task calendar.

Assign a calendar to a task to schedule it independently from the project or resource calendars.

Figure 5-23. Assign a calendar to a task to schedule it independently from the project or resource calendars.

Don’t confuse the task calendar with the Calendar view. A task calendar reflects working days and times for one or more selected tasks. The Calendar view is a graphical representation of tasks and durations in a monthly calendar format.

Note

For more information about the Calendar view, see the section titled Working with Graph Views in Chapter 4.

..................Content has been hidden....................

You can't read the all page of ebook, please click here login for view all page.
Reset
18.118.186.143